EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 69
activities
in PM Payment Milestones
× clear
Code
Activity
Start
Finish
Flt
%
EK000YA827
(PC-04) Issue Cooling Tower,Item No. 2101-U Purchase Order
03-Sep-25
03-Sep-25
—
100%
EK000YA812
(EP-13) Vendor Acceptance of Commitment for Boiler Package, 2002-U
05-Sep-25
05-Sep-25
—
100%
EK000YA820
(EP-20) Vendor Acceptance of Commitment for 101-B
20-Sep-25
20-Sep-25
—
100%
EK000YA803
(PC-02,EP-04) Issue Project Specific Quality Control Manual
30-Oct-25
30-Oct-25
—
100%
EK000YA815
(PC-05) Award Contract - Ammonia Storage Tanks - 2101-F/2102
03-Jan-26
03-Jan-26
—
100%
EK000YA000
(PC-01,EP-01, TLA-01) Receive Owner's ""Notice to Proceed""
17-Jan-26
17-Jan-26
—
100%
EK000YA814
(EP-15) Vendor Acceptance of Commitment for 101-J, 102-J, 103-J & 105-J
11-Feb-26
11-Feb-26
—
100%
EK000YA816
(EP-16) Vendor Acceptance of Commitment for 105-D
11-Feb-26
11-Feb-26
—
100%
EK000YA817
(EP-17) Vendor Acceptance of Commitment for High Pressure Boiler Feed Water pumps, 104-J & 107-J
11-Feb-26
11-Feb-26
—
100%
EK000YA819
(EP-19) Vendor Acceptance of Commitment for 120-C
11-Feb-26
11-Feb-26
—
100%
EK000YA821
(PC-03,EP-21) Vendor Acceptance of Commitment for Methanator, 106-D
11-Feb-26
11-Feb-26
—
100%
EK000YA818
(EP-18) Vendor Acceptance of Commitment for 101-C and 102-C
19-Feb-26
19-Feb-26
—
100%
EK000YA825
(EP-24) Vendor Acceptance of Commitment for Demineralizer, 2001-U, & remaining utility equipment
17-Mar-26
17-Mar-26
—
100%
EK000YA834
(PC-06,EP-28) Issue ISBL Plot Plan For Construction (IFC)
28-Mar-26
28-Mar-26
—
100%
EK000YA830
(EP-25) Vendor Acceptance of Commitment for Kellogg Advanced Ammonia Process (KAAP) Catalyst
11-Apr-26
11-Apr-26
—
100%
EK000YA828
(EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers
27-Dec-26
27-Dec-26
—
0%
EK000YA829
(EP-31) Vendor Acceptance of Commitment for Substation
27-Dec-26
27-Dec-26
—
0%
EK000YA836
(PC-07) Issue 101-B -Primary Reformer Erection Drawings
27-Dec-26
27-Dec-26
—
0%
EK000YA858
(EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site
27-Dec-26
27-Dec-26
—
0%
EK000YA845
(PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter
28-Dec-26
28-Dec-26
—
0%
EK000YA843
(PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection
28-Dec-26
28-Dec-26
750.0d
0%
EK000CS040
Issue Operation & Maintenance Manuals for Review
30-Dec-26
21-Mar-27
215.0d
0%
EK000CS060
Issue Proposed Operating Training Program for Review
27-Jan-27
21-Mar-27
215.0d
0%
EK000YA863
(PC-09) Complete >90% Compressor 101-J/JT Equipment Foundation
01-Feb-27
01-Feb-27
714.0d
0%
EK000YA844
(EP-40) Complete Fabrication of 101-F Steam Drum
07-Feb-27
07-Feb-27
708.0d
0%
EK000YA851
(PC-12) Complete >90% - ISBL - Unit 02 Underground Piping Fabrication and installation
26-Feb-27
26-Feb-27
689.0d
0%
EK000YA855
(EP-45) Deliver Air Compressor, 101-J, and Feed Gas Compressor, 102-J, to site
08-Mar-27
08-Mar-27
680.0d
0%
EK000YA859
(PC-11) Complete >90% - ISBL - Unit 02 Equipment Foundation
23-Mar-27
23-Mar-27
664.0d
0%
EK000YA854
(PC-13) Complete >90% - OSBL Unit 01 & 03 Underground Piping Fabrication & Installation
26-Mar-27
26-Mar-27
661.0d
0%
EK000CS050
Issue Operation & Maintenance Manuals IFC
07-Apr-27
08-Aug-27
375.0d
0%
EK000YA856
(EP-43) Deliver majority of tagged field Instruments
12-Apr-27
12-Apr-27
645.0d
0%
EK000YA852
(EP-42) Deliver BFW pumps, 104-J, & Lean Solution pumps, 107-J, to site
15-Apr-27
15-Apr-27
641.0d
0%
EK000YA865
(PC-16) Erect 101-B Primary Reformer Heater Stack ,Forced & Induced Draft Fans
30-Apr-27
30-Apr-27
626.0d
0%
EK000YA867
(PC-19) Complete >90% - Cooling Tower ,Item No. 2101-U Erection
04-May-27
04-May-27
622.0d
0%
EK000CS070
Issue Operating Training Program
05-May-27
27-Jun-27
375.0d
0%
EK000YA850
(PC-15) Complete >90% ISBL Unit 02 aboveground LB ,Greater than 2"" pipe fabrication
29-May-27
29-May-27
598.0d
0%
EK000YA861
(PC-17) Complete >90% - Erection of Steam Drum 101-F Structure
14-Jun-27
14-Jun-27
581.0d
0%
EK000YA842
(PC-10) Complete >90% - Ammonia Tanks - 2101-F/2102-F Foundation
16-Jun-27
16-Jun-27
579.0d
0%
EK000YA862
(PC-14) Complete >90% -Bldg No. 2601-K Main Control Building Erection
24-Jun-27
24-Jun-27
571.0d
0%
EK000YA846
(EP-41) Issue Proposed Operator Training Program
27-Jun-27
27-Jun-27
568.0d
0%
EK000YA868
(PC-26) Complete >90% 101-B Primary Reformer Erection
24-Jul-27
24-Jul-27
541.0d
0%
EK000YA857
(EP-46) Complete >90% delivery of all ISBL long lead equipment (except 103-J and 105-J) to site
29-Jul-27
29-Jul-27
536.0d
0%
EK000YA864
(PC-22) Complete >90% - ISBL - Unit 02 equipment installation
30-Jul-27
30-Jul-27
535.0d
0%
EK000YA853
(EP-44) Issue Operation & Maintenance Manuals
08-Aug-27
08-Aug-27
526.0d
0%
EK000YA871
(PC-20) Install export Ammonia Line from EBIC site to Storage Tank,2101-F/2102-F Battery Limit
09-Aug-27
09-Aug-27
526.0d
0%
EK000YA866
(PC-25) Complete >90% - OSBL - Unit 01 & 03 Electrical lighting installation
08-Sep-27
08-Sep-27
495.0d
0%
EK000YA873
(PC-21) Install DCS in Main Control Building
10-Sep-27
10-Sep-27
493.0d
0%
EK000YA876
(PC-23) Complete >90% - OSBL - Unit 01 & 03 pipe testing -visual,service,hydrostatic,or pneumatic testing
05-Oct-27
05-Oct-27
468.0d
0%
EK000YA890
(PC-27) Complete >10% - ISBL - Unit 02 Hot & Cold Pipe Insulation
02-Nov-27
02-Nov-27
108.0d
0%
EK000YA869
(PC-30) Complete >90% - ISBL - Unit 02 - Equipment Insulation
01-Dec-27
01-Dec-27
411.0d
0%
EK000YA879
(PC-24) Commence Pre-commissioning Activities
21-Dec-27
21-Dec-27
392.0d
0%
EK000YA878
(PC-28) Mechanical Completion - OSBL - Unit 01 & 03 Utilities &Plant site Offsites
04-Jan-28
04-Jan-28
377.0d
0%
EK000YA872
(EP-47) Deliver Converter Catalyst to site
12-Jan-28
12-Jan-28
369.0d
0%
EK000YA837
(PC-36) Complete >90% - Site Preparation within the EBIC Plant Site boundary wall
28-Jan-28
28-Jan-28
353.0d
0%
EK000YA874
(PC-31) Complete >90% - ISBL - Unit 02 - LB Greater than 2"" piping installation
07-Feb-28
07-Feb-28
343.0d
0%
EK000YA870
(PC-34) Complete >90% - ISBL - Unit 02 Instruments Installed
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA877
(PC-33) Complete >90% - ISBL - Unit 02 pipe testing -visual,service,hydrostatic,or pneumatic testing
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA860
(PC-29) Complete Erection of Ammonia Storage Tanks 2101-F/2102-F
09-Mar-28
09-Mar-28
312.0d
0%
EK000YA875
(PC-35) Complete >90% - ISBL - Unit 02 Instrument loops checked
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA881
(PC-37) Mechanical Completion - ISBL - Unit 02 -Ammonia
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA882
(PC-32) Complete >90% - ISBL - Unit 02 chemical cleaning LP,MP & HP steam systems
29-Mar-28
29-Mar-28
292.0d
0%
EK000YA880
(PC-38) Feed Gas into Ammonia Unit
11-May-28
11-May-28
250.0d
0%
EK000YA883
(PC-39) First Ammonia produced
31-May-28
31-May-28
55.0d
0%
EK000YA884
(PC-40) Begin Production Test run
31-May-28
31-May-28
55.0d
0%
EK000YA886
(PC-41) Begin Reliability Test
31-May-28
31-May-28
55.0d
0%
EK000YA885
(PC-42) Complete Production Test run
04-Jul-28
04-Jul-28
195.0d
0%
EK000YA887
(PC-43) Complete Reliability Test
22-Sep-28
22-Sep-28
-59.0d
0%
SC000T0120
(PC-44) Provisional Completion
22-Sep-28
22-Sep-28
-59.0d
0%
SC000YA700
Contractual Completion Date (15-Feb-09)
15-Mar-29
15-Mar-29
-59.0d
0%