EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 69 activities in PM Payment Milestones × clear
Code
Activity
Start
Finish
Flt
%
EK000YA827
(PC-04) Issue Cooling Tower,Item No. 2101-U Purchase Order
03-Sep-25
03-Sep-25
100%
EK000YA812
(EP-13) Vendor Acceptance of Commitment for Boiler Package, 2002-U
05-Sep-25
05-Sep-25
100%
EK000YA820
(EP-20) Vendor Acceptance of Commitment for 101-B
20-Sep-25
20-Sep-25
100%
EK000YA803
(PC-02,EP-04) Issue Project Specific Quality Control Manual
30-Oct-25
30-Oct-25
100%
EK000YA815
(PC-05) Award Contract - Ammonia Storage Tanks - 2101-F/2102
03-Jan-26
03-Jan-26
100%
EK000YA000
(PC-01,EP-01, TLA-01) Receive Owner's ""Notice to Proceed""
17-Jan-26
17-Jan-26
100%
EK000YA814
(EP-15) Vendor Acceptance of Commitment for 101-J, 102-J, 103-J & 105-J
11-Feb-26
11-Feb-26
100%
EK000YA816
(EP-16) Vendor Acceptance of Commitment for 105-D
11-Feb-26
11-Feb-26
100%
EK000YA817
(EP-17) Vendor Acceptance of Commitment for High Pressure Boiler Feed Water pumps, 104-J & 107-J
11-Feb-26
11-Feb-26
100%
EK000YA819
(EP-19) Vendor Acceptance of Commitment for 120-C
11-Feb-26
11-Feb-26
100%
EK000YA821
(PC-03,EP-21) Vendor Acceptance of Commitment for Methanator, 106-D
11-Feb-26
11-Feb-26
100%
EK000YA818
(EP-18) Vendor Acceptance of Commitment for 101-C and 102-C
19-Feb-26
19-Feb-26
100%
EK000YA825
(EP-24) Vendor Acceptance of Commitment for Demineralizer, 2001-U, & remaining utility equipment
17-Mar-26
17-Mar-26
100%
EK000YA834
(PC-06,EP-28) Issue ISBL Plot Plan For Construction (IFC)
28-Mar-26
28-Mar-26
100%
EK000YA830
(EP-25) Vendor Acceptance of Commitment for Kellogg Advanced Ammonia Process (KAAP) Catalyst
11-Apr-26
11-Apr-26
100%
EK000YA828
(EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers
27-Dec-26
27-Dec-26
0%
EK000YA829
(EP-31) Vendor Acceptance of Commitment for Substation
27-Dec-26
27-Dec-26
0%
EK000YA836
(PC-07) Issue 101-B -Primary Reformer Erection Drawings
27-Dec-26
27-Dec-26
0%
EK000YA858
(EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site
27-Dec-26
27-Dec-26
0%
EK000YA845
(PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter
28-Dec-26
28-Dec-26
0%
EK000YA843
(PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection
28-Dec-26
28-Dec-26
750.0d
0%
EK000CS040
Issue Operation & Maintenance Manuals for Review
30-Dec-26
21-Mar-27
215.0d
0%
EK000CS060
Issue Proposed Operating Training Program for Review
27-Jan-27
21-Mar-27
215.0d
0%
EK000YA863
(PC-09) Complete >90% Compressor 101-J/JT Equipment Foundation
01-Feb-27
01-Feb-27
714.0d
0%
EK000YA844
(EP-40) Complete Fabrication of 101-F Steam Drum
07-Feb-27
07-Feb-27
708.0d
0%
EK000YA851
(PC-12) Complete >90% - ISBL - Unit 02 Underground Piping Fabrication and installation
26-Feb-27
26-Feb-27
689.0d
0%
EK000YA855
(EP-45) Deliver Air Compressor, 101-J, and Feed Gas Compressor, 102-J, to site
08-Mar-27
08-Mar-27
680.0d
0%
EK000YA859
(PC-11) Complete >90% - ISBL - Unit 02 Equipment Foundation
23-Mar-27
23-Mar-27
664.0d
0%
EK000YA854
(PC-13) Complete >90% - OSBL Unit 01 & 03 Underground Piping Fabrication & Installation
26-Mar-27
26-Mar-27
661.0d
0%
EK000CS050
Issue Operation & Maintenance Manuals IFC
07-Apr-27
08-Aug-27
375.0d
0%
EK000YA856
(EP-43) Deliver majority of tagged field Instruments
12-Apr-27
12-Apr-27
645.0d
0%
EK000YA852
(EP-42) Deliver BFW pumps, 104-J, & Lean Solution pumps, 107-J, to site
15-Apr-27
15-Apr-27
641.0d
0%
EK000YA865
(PC-16) Erect 101-B Primary Reformer Heater Stack ,Forced & Induced Draft Fans
30-Apr-27
30-Apr-27
626.0d
0%
EK000YA867
(PC-19) Complete >90% - Cooling Tower ,Item No. 2101-U Erection
04-May-27
04-May-27
622.0d
0%
EK000CS070
Issue Operating Training Program
05-May-27
27-Jun-27
375.0d
0%
EK000YA850
(PC-15) Complete >90% ISBL Unit 02 aboveground LB ,Greater than 2"" pipe fabrication
29-May-27
29-May-27
598.0d
0%
EK000YA861
(PC-17) Complete >90% - Erection of Steam Drum 101-F Structure
14-Jun-27
14-Jun-27
581.0d
0%
EK000YA842
(PC-10) Complete >90% - Ammonia Tanks - 2101-F/2102-F Foundation
16-Jun-27
16-Jun-27
579.0d
0%
EK000YA862
(PC-14) Complete >90% -Bldg No. 2601-K Main Control Building Erection
24-Jun-27
24-Jun-27
571.0d
0%
EK000YA846
(EP-41) Issue Proposed Operator Training Program
27-Jun-27
27-Jun-27
568.0d
0%
EK000YA868
(PC-26) Complete >90% 101-B Primary Reformer Erection
24-Jul-27
24-Jul-27
541.0d
0%
EK000YA857
(EP-46) Complete >90% delivery of all ISBL long lead equipment (except 103-J and 105-J) to site
29-Jul-27
29-Jul-27
536.0d
0%
EK000YA864
(PC-22) Complete >90% - ISBL - Unit 02 equipment installation
30-Jul-27
30-Jul-27
535.0d
0%
EK000YA853
(EP-44) Issue Operation & Maintenance Manuals
08-Aug-27
08-Aug-27
526.0d
0%
EK000YA871
(PC-20) Install export Ammonia Line from EBIC site to Storage Tank,2101-F/2102-F Battery Limit
09-Aug-27
09-Aug-27
526.0d
0%
EK000YA866
(PC-25) Complete >90% - OSBL - Unit 01 & 03 Electrical lighting installation
08-Sep-27
08-Sep-27
495.0d
0%
EK000YA873
(PC-21) Install DCS in Main Control Building
10-Sep-27
10-Sep-27
493.0d
0%
EK000YA876
(PC-23) Complete >90% - OSBL - Unit 01 & 03 pipe testing -visual,service,hydrostatic,or pneumatic testing
05-Oct-27
05-Oct-27
468.0d
0%
EK000YA890
(PC-27) Complete >10% - ISBL - Unit 02 Hot & Cold Pipe Insulation
02-Nov-27
02-Nov-27
108.0d
0%
EK000YA869
(PC-30) Complete >90% - ISBL - Unit 02 - Equipment Insulation
01-Dec-27
01-Dec-27
411.0d
0%
EK000YA879
(PC-24) Commence Pre-commissioning Activities
21-Dec-27
21-Dec-27
392.0d
0%
EK000YA878
(PC-28) Mechanical Completion - OSBL - Unit 01 & 03 Utilities &Plant site Offsites
04-Jan-28
04-Jan-28
377.0d
0%
EK000YA872
(EP-47) Deliver Converter Catalyst to site
12-Jan-28
12-Jan-28
369.0d
0%
EK000YA837
(PC-36) Complete >90% - Site Preparation within the EBIC Plant Site boundary wall
28-Jan-28
28-Jan-28
353.0d
0%
EK000YA874
(PC-31) Complete >90% - ISBL - Unit 02 - LB Greater than 2"" piping installation
07-Feb-28
07-Feb-28
343.0d
0%
EK000YA870
(PC-34) Complete >90% - ISBL - Unit 02 Instruments Installed
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA877
(PC-33) Complete >90% - ISBL - Unit 02 pipe testing -visual,service,hydrostatic,or pneumatic testing
14-Feb-28
14-Feb-28
336.0d
0%
EK000YA860
(PC-29) Complete Erection of Ammonia Storage Tanks 2101-F/2102-F
09-Mar-28
09-Mar-28
312.0d
0%
EK000YA875
(PC-35) Complete >90% - ISBL - Unit 02 Instrument loops checked
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA881
(PC-37) Mechanical Completion - ISBL - Unit 02 -Ammonia
19-Mar-28
19-Mar-28
302.0d
0%
EK000YA882
(PC-32) Complete >90% - ISBL - Unit 02 chemical cleaning LP,MP & HP steam systems
29-Mar-28
29-Mar-28
292.0d
0%
EK000YA880
(PC-38) Feed Gas into Ammonia Unit
11-May-28
11-May-28
250.0d
0%
EK000YA883
(PC-39) First Ammonia produced
31-May-28
31-May-28
55.0d
0%
EK000YA884
(PC-40) Begin Production Test run
31-May-28
31-May-28
55.0d
0%
EK000YA886
(PC-41) Begin Reliability Test
31-May-28
31-May-28
55.0d
0%
EK000YA885
(PC-42) Complete Production Test run
04-Jul-28
04-Jul-28
195.0d
0%
EK000YA887
(PC-43) Complete Reliability Test
22-Sep-28
22-Sep-28
-59.0d
0%
SC000T0120
(PC-44) Provisional Completion
22-Sep-28
22-Sep-28
-59.0d
0%
SC000YA700
Contractual Completion Date (15-Feb-09)
15-Mar-29
15-Mar-29
-59.0d
0%
Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 May 2027 Jun 2027 Jul 2027 Aug 2027 Sep 2027 Oct 2027 Nov 2027 Dec 2027 Jan 2028 Feb 2028 Mar 2028 Apr 2028 May 2028 Jun 2028 Jul 2028 Aug 2028 Sep 2028 Oct 2028 Nov 2028 Dec 2028 Jan 2029 Feb 2029 Mar 2029 Data Date
EK000YA827 — (PC-04) Issue Cooling Tower,Item No. 2101-U Purchase Order | 03-Sep-25 | Complete EK000YA812 — (EP-13) Vendor Acceptance of Commitment for Boiler Package, 2002-U | 05-Sep-25 | Complete EK000YA820 — (EP-20) Vendor Acceptance of Commitment for 101-B | 20-Sep-25 | Complete EK000YA803 — (PC-02,EP-04) Issue Project Specific Quality Control Manual | 30-Oct-25 | Complete EK000YA815 — (PC-05) Award Contract - Ammonia Storage Tanks - 2101-F/2102 | 03-Jan-26 | Complete EK000YA000 — (PC-01,EP-01, TLA-01) Receive Owner's ""Notice to Proceed"" | 17-Jan-26 | Complete EK000YA814 — (EP-15) Vendor Acceptance of Commitment for 101-J, 102-J, 103-J & 105-J | 11-Feb-26 | Complete EK000YA816 — (EP-16) Vendor Acceptance of Commitment for 105-D | 11-Feb-26 | Complete EK000YA817 — (EP-17) Vendor Acceptance of Commitment for High Pressure Boiler Feed Water pumps, 104-J & 107-J | 11-Feb-26 | Complete EK000YA819 — (EP-19) Vendor Acceptance of Commitment for 120-C | 11-Feb-26 | Complete EK000YA821 — (PC-03,EP-21) Vendor Acceptance of Commitment for Methanator, 106-D | 11-Feb-26 | Complete EK000YA818 — (EP-18) Vendor Acceptance of Commitment for 101-C and 102-C | 19-Feb-26 | Complete EK000YA825 — (EP-24) Vendor Acceptance of Commitment for Demineralizer, 2001-U, & remaining utility equipment | 17-Mar-26 | Complete EK000YA834 — (PC-06,EP-28) Issue ISBL Plot Plan For Construction (IFC) | 28-Mar-26 | Complete EK000YA830 — (EP-25) Vendor Acceptance of Commitment for Kellogg Advanced Ammonia Process (KAAP) Catalyst | 11-Apr-26 | Complete EK000YA828 — (EP-30) Vendor Acceptance of Commitment for Electrical 20 MVA Transformers | 27-Dec-26 | Not Started EK000YA829 — (EP-31) Vendor Acceptance of Commitment for Substation | 27-Dec-26 | Not Started EK000YA836 — (PC-07) Issue 101-B -Primary Reformer Erection Drawings | 27-Dec-26 | Not Started EK000YA858 — (EP-38) Deliver Syn Gas Compressor, 103-J, and Ammonia Refrig Compressor, 105-J, to site | 27-Dec-26 | Not Started EK000YA845 — (PC-08) Complete >10% - ISBL -Unit 02 - Pipe Spool Fabrication,>2 Inch Diameter | 28-Dec-26 | Not Started EK000YA843 — (PC-18) Complete >90% Bldg No. 2604-K Workshop / Warehouse Erection | 28-Dec-26 | Not Started EK000CS040 — Issue Operation & Maintenance Manuals for Review | 30-Dec-26 → 21-Mar-27 | Not Started 0% | float 215.0d EK000CS040 EK000CS060 — Issue Proposed Operating Training Program for Review | 27-Jan-27 → 21-Mar-27 | Not Started 0% | float 215.0d EK000CS060 EK000YA863 — (PC-09) Complete >90% Compressor 101-J/JT Equipment Foundation | 01-Feb-27 | Not Started EK000YA844 — (EP-40) Complete Fabrication of 101-F Steam Drum | 07-Feb-27 | Not Started EK000YA851 — (PC-12) Complete >90% - ISBL - Unit 02 Underground Piping Fabrication and installation | 26-Feb-27 | Not Started EK000YA855 — (EP-45) Deliver Air Compressor, 101-J, and Feed Gas Compressor, 102-J, to site | 08-Mar-27 | Not Started EK000YA859 — (PC-11) Complete >90% - ISBL - Unit 02 Equipment Foundation | 23-Mar-27 | Not Started EK000YA854 — (PC-13) Complete >90% - OSBL Unit 01 & 03 Underground Piping Fabrication & Installation | 26-Mar-27 | Not Started EK000CS050 — Issue Operation & Maintenance Manuals IFC | 07-Apr-27 → 08-Aug-27 | Not Started 0% | float 375.0d EK000CS050 EK000YA856 — (EP-43) Deliver majority of tagged field Instruments | 12-Apr-27 | Not Started EK000YA852 — (EP-42) Deliver BFW pumps, 104-J, & Lean Solution pumps, 107-J, to site | 15-Apr-27 | Not Started EK000YA865 — (PC-16) Erect 101-B Primary Reformer Heater Stack ,Forced & Induced Draft Fans | 30-Apr-27 | Not Started EK000YA867 — (PC-19) Complete >90% - Cooling Tower ,Item No. 2101-U Erection | 04-May-27 | Not Started EK000CS070 — Issue Operating Training Program | 05-May-27 → 27-Jun-27 | Not Started 0% | float 375.0d EK000CS070 EK000YA850 — (PC-15) Complete >90% ISBL Unit 02 aboveground LB ,Greater than 2"" pipe fabrication | 29-May-27 | Not Started EK000YA861 — (PC-17) Complete >90% - Erection of Steam Drum 101-F Structure | 14-Jun-27 | Not Started EK000YA842 — (PC-10) Complete >90% - Ammonia Tanks - 2101-F/2102-F Foundation | 16-Jun-27 | Not Started EK000YA862 — (PC-14) Complete >90% -Bldg No. 2601-K Main Control Building Erection | 24-Jun-27 | Not Started EK000YA846 — (EP-41) Issue Proposed Operator Training Program | 27-Jun-27 | Not Started EK000YA868 — (PC-26) Complete >90% 101-B Primary Reformer Erection | 24-Jul-27 | Not Started EK000YA857 — (EP-46) Complete >90% delivery of all ISBL long lead equipment (except 103-J and 105-J) to site | 29-Jul-27 | Not Started EK000YA864 — (PC-22) Complete >90% - ISBL - Unit 02 equipment installation | 30-Jul-27 | Not Started EK000YA853 — (EP-44) Issue Operation & Maintenance Manuals | 08-Aug-27 | Not Started EK000YA871 — (PC-20) Install export Ammonia Line from EBIC site to Storage Tank,2101-F/2102-F Battery Limit | 09-Aug-27 | Not Started EK000YA866 — (PC-25) Complete >90% - OSBL - Unit 01 & 03 Electrical lighting installation | 08-Sep-27 | Not Started EK000YA873 — (PC-21) Install DCS in Main Control Building | 10-Sep-27 | Not Started EK000YA876 — (PC-23) Complete >90% - OSBL - Unit 01 & 03 pipe testing -visual,service,hydrostatic,or pneumatic testing | 05-Oct-27 | Not Started EK000YA890 — (PC-27) Complete >10% - ISBL - Unit 02 Hot & Cold Pipe Insulation | 02-Nov-27 | Not Started EK000YA869 — (PC-30) Complete >90% - ISBL - Unit 02 - Equipment Insulation | 01-Dec-27 | Not Started EK000YA879 — (PC-24) Commence Pre-commissioning Activities | 21-Dec-27 | Not Started EK000YA878 — (PC-28) Mechanical Completion - OSBL - Unit 01 & 03 Utilities &Plant site Offsites | 04-Jan-28 | Not Started EK000YA872 — (EP-47) Deliver Converter Catalyst to site | 12-Jan-28 | Not Started EK000YA837 — (PC-36) Complete >90% - Site Preparation within the EBIC Plant Site boundary wall | 28-Jan-28 | Not Started EK000YA874 — (PC-31) Complete >90% - ISBL - Unit 02 - LB Greater than 2"" piping installation | 07-Feb-28 | Not Started EK000YA870 — (PC-34) Complete >90% - ISBL - Unit 02 Instruments Installed | 14-Feb-28 | Not Started EK000YA877 — (PC-33) Complete >90% - ISBL - Unit 02 pipe testing -visual,service,hydrostatic,or pneumatic testing | 14-Feb-28 | Not Started EK000YA860 — (PC-29) Complete Erection of Ammonia Storage Tanks 2101-F/2102-F | 09-Mar-28 | Not Started EK000YA875 — (PC-35) Complete >90% - ISBL - Unit 02 Instrument loops checked | 19-Mar-28 | Not Started EK000YA881 — (PC-37) Mechanical Completion - ISBL - Unit 02 -Ammonia | 19-Mar-28 | Not Started EK000YA882 — (PC-32) Complete >90% - ISBL - Unit 02 chemical cleaning LP,MP & HP steam systems | 29-Mar-28 | Not Started EK000YA880 — (PC-38) Feed Gas into Ammonia Unit | 11-May-28 | Not Started EK000YA883 — (PC-39) First Ammonia produced | 31-May-28 | Not Started EK000YA884 — (PC-40) Begin Production Test run | 31-May-28 | Not Started EK000YA886 — (PC-41) Begin Reliability Test | 31-May-28 | Not Started EK000YA885 — (PC-42) Complete Production Test run | 04-Jul-28 | Not Started EK000YA887 — (PC-43) Complete Reliability Test | 22-Sep-28 | Not Started SC000T0120 — (PC-44) Provisional Completion | 22-Sep-28 | Not Started SC000YA700 — Contractual Completion Date (15-Feb-09) | 15-Mar-29 | Not Started