Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 37 activities in MB Furnaces & Flares Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000MB065
102-B Start-up Heater Prelim Data Sheets & ERW
19-Feb-25
23-Feb-25
100%
EK000MB33B
101-B Develop & Issue Design Data
19-Feb-25
13-Mar-25
100%
EK000MB81C
Prepare & Issue Prelim. RFQ - MB810 to Proc.
21-Feb-25
23-Feb-25
100%
EK000MB015
101-B API Furnace Data Sheets
09-Mar-25
22-Mar-25
100%
EK000MB025
Air Preheater data sheets
11-Mar-25
21-Mar-25
100%
EK000MB020
Burner Data Sheets
18-Mar-25
21-Mar-25
100%
EK000MB81F
Prepare & Issue Purchase ERW - MB810
23-Mar-25
24-May-25
100%
EK000MB81D
Technical Evaluation - MB810
29-Mar-25
04-Apr-25
100%
EK000MB030
ID & FD fan data sheets
01-Apr-25
12-Apr-25
100%
EK000MB035
101-B Damper & Expansion joint data sheets
30-Apr-25
24-May-25
100%
EK000MB040
Penthouse fan data sheets
30-Apr-25
25-May-25
100%
PK000MB63N
Recv. Planning V. Data MB630
12-Aug-25
27-Sep-25
100%
PK000MB61N
Recv. Planning V. Data MB610
12-Aug-25
01-Oct-25
100%
PK000MB81N
02M MB810 102-B Startup Heater Planning V. Data
12-Aug-25
09-Oct-25
100%
PK000MB62N
Recv. Planning V. Data MB621
12-Aug-25
17-Dec-25
100%
PK02HMB32
02H MB610 101-BA/B/C - Piping Prod. V. Data
01-Oct-25
18-Nov-25
100%
PK02HMB33
02H MB610 101-BA/B/C - Civil Prod. V. Data
01-Oct-25
18-Nov-25
100%
PK02HMB34
02H MB610 101-BA/B/C - E&I Prod. V. Data
01-Oct-25
18-Nov-25
100%
PK02HMB19
02H MB221 101-B - Piping Prod. V. Data
01-Oct-25
18-Oct-25
100%
PK02HMB20
02H MB221 101-B - Civil Prod. V. Data
01-Oct-25
18-Oct-25
100%
PK02HMB21
02H MB221 101-B - E&I Prod. V. Data
01-Oct-25
18-Oct-25
100%
PK02MMB02
02M MB810 102-B - Piping Prod. V. Data
10-Oct-25
10-Dec-25
100%
PK02MMB03
02M MB810 102-B - Civil Prod. V. Data
10-Oct-25
10-Dec-25
100%
PK02MMB04
02M MB810 102-B - E&I Prod. V. Data
10-Oct-25
10-Dec-25
100%
PK000MB21N
Recv. Planning V. Data MB212
07-Nov-25
09-Dec-25
100%
PK02HMB35
02H MB621 101-B I.D. & F.D. Fans - Piping Prod. V. Data
17-Dec-25
08-Jan-26
100%
PK02HMB36
02H MB621 101-B I.D. & F.D. Fans - Civil Prod. V. Data
17-Dec-25
08-Jan-26
100%
PK02HMB37
02H MB621 101-B I.D. & F.D. Fans - E&I Prod. V. Data
17-Dec-25
08-Jan-26
100%
PK02HMB41
02H MB630 101-BL1 Combustion Air Preheater - Piping Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK02HMB42
02H MB630 101-BL1 Combustion Air Preheater - Civil Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK02HMB43
02H MB630 101-BL1 Combustion Air Preheater - E&I Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK02HMB38
02H MB622 101-B - Piping Prod. V. Data
06-Jan-26
27-Dec-26
30%
PK02HMB39
02H MB622 101-B - Civil Prod. V. Data
06-Jan-26
27-Dec-26
30%
PK02HMB40
02H MB622 101-B - E&I Prod. V. Data
06-Jan-26
27-Dec-26
30%
PK02HMB50
02H MB692 101-BL2 - Piping Prod. V. Data
01-Apr-26
27-Dec-26
9%
PK02HMB51
02H MB692 101-BL2 - Civil Prod. V. Data
01-Apr-26
27-Dec-26
9%
PK02HMB52
02H MB692 101-BL2 - E&I Prod. V. Data
01-Apr-26
27-Dec-26
9%
Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK000MB065 — 102-B Start-up Heater Prelim Data Sheets & ERW | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MB065 EK000MB33B — 101-B Develop & Issue Design Data | 19-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000MB33B EK000MB81C — Prepare & Issue Prelim. RFQ - MB810 to Proc. | 21-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000MB015 — 101-B API Furnace Data Sheets | 09-Mar-25 → 22-Mar-25 | Complete 100% | float — EK000MB015 EK000MB025 — Air Preheater data sheets | 11-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MB025 EK000MB020 — Burner Data Sheets | 18-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MB81F — Prepare & Issue Purchase ERW - MB810 | 23-Mar-25 → 24-May-25 | Complete 100% | float — EK000MB81F EK000MB81D — Technical Evaluation - MB810 | 29-Mar-25 → 04-Apr-25 | Complete 100% | float — EK000MB81D EK000MB030 — ID & FD fan data sheets | 01-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MB030 EK000MB035 — 101-B Damper & Expansion joint data sheets | 30-Apr-25 → 24-May-25 | Complete 100% | float — EK000MB035 EK000MB040 — Penthouse fan data sheets | 30-Apr-25 → 25-May-25 | Complete 100% | float — EK000MB040 PK000MB63N — Recv. Planning V. Data MB630 | 12-Aug-25 → 27-Sep-25 | Complete 100% | float — PK000MB63N PK000MB61N — Recv. Planning V. Data MB610 | 12-Aug-25 → 01-Oct-25 | Complete 100% | float — PK000MB61N PK000MB81N — 02M MB810 102-B Startup Heater Planning V. Data | 12-Aug-25 → 09-Oct-25 | Complete 100% | float — PK000MB81N PK000MB62N — Recv. Planning V. Data MB621 | 12-Aug-25 → 17-Dec-25 | Complete 100% | float — PK000MB62N PK02HMB32 — 02H MB610 101-BA/B/C - Piping Prod. V. Data | 01-Oct-25 → 18-Nov-25 | Complete 100% | float — PK02HMB32 PK02HMB33 — 02H MB610 101-BA/B/C - Civil Prod. V. Data | 01-Oct-25 → 18-Nov-25 | Complete 100% | float — PK02HMB33 PK02HMB34 — 02H MB610 101-BA/B/C - E&I Prod. V. Data | 01-Oct-25 → 18-Nov-25 | Complete 100% | float — PK02HMB34 PK02HMB19 — 02H MB221 101-B - Piping Prod. V. Data | 01-Oct-25 → 18-Oct-25 | Complete 100% | float — PK02HMB19 PK02HMB20 — 02H MB221 101-B - Civil Prod. V. Data | 01-Oct-25 → 18-Oct-25 | Complete 100% | float — PK02HMB20 PK02HMB21 — 02H MB221 101-B - E&I Prod. V. Data | 01-Oct-25 → 18-Oct-25 | Complete 100% | float — PK02HMB21 PK02MMB02 — 02M MB810 102-B - Piping Prod. V. Data | 10-Oct-25 → 10-Dec-25 | Complete 100% | float — PK02MMB02 PK02MMB03 — 02M MB810 102-B - Civil Prod. V. Data | 10-Oct-25 → 10-Dec-25 | Complete 100% | float — PK02MMB03 PK02MMB04 — 02M MB810 102-B - E&I Prod. V. Data | 10-Oct-25 → 10-Dec-25 | Complete 100% | float — PK02MMB04 PK000MB21N — Recv. Planning V. Data MB212 | 07-Nov-25 → 09-Dec-25 | Complete 100% | float — PK000MB21N PK02HMB35 — 02H MB621 101-B I.D. & F.D. Fans - Piping Prod. V. Data | 17-Dec-25 → 08-Jan-26 | Complete 100% | float — PK02HMB35 PK02HMB36 — 02H MB621 101-B I.D. & F.D. Fans - Civil Prod. V. Data | 17-Dec-25 → 08-Jan-26 | Complete 100% | float — PK02HMB36 PK02HMB37 — 02H MB621 101-B I.D. & F.D. Fans - E&I Prod. V. Data | 17-Dec-25 → 08-Jan-26 | Complete 100% | float — PK02HMB37 PK02HMB41 — 02H MB630 101-BL1 Combustion Air Preheater - Piping Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK02HMB42 — 02H MB630 101-BL1 Combustion Air Preheater - Civil Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK02HMB43 — 02H MB630 101-BL1 Combustion Air Preheater - E&I Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK02HMB38 — 02H MB622 101-B - Piping Prod. V. Data | 06-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK02HMB38 PK02HMB39 — 02H MB622 101-B - Civil Prod. V. Data | 06-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK02HMB39 PK02HMB40 — 02H MB622 101-B - E&I Prod. V. Data | 06-Jan-26 → 27-Dec-26 | In Progress 30% | float — PK02HMB40 PK02HMB50 — 02H MB692 101-BL2 - Piping Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK02HMB50 PK02HMB51 — 02H MB692 101-BL2 - Civil Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK02HMB51 PK02HMB52 — 02H MB692 101-BL2 - E&I Prod. V. Data | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — PK02HMB52