EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 36 activities in SY Systems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000SY020
020 ISBL Hydraulic Calculations
14-Feb-25
18-May-25
100%
EK020SY020
020 ISBL P&ID development IDR & Line List Issue
19-Feb-25
23-Mar-25
100%
EK020SY030
020 ISBL P&ID IDR Meeting milestone
03-Apr-25
04-Apr-25
100%
EK020SY040
020 ISBL P&IDs - ICA & Line List Issue development
06-Apr-25
21-May-25
100%
EK020SY050
020 ISBL P&IDs - ICA & Line List Issue Milestone
21-May-25
21-May-25
100%
EK000SY126
020 ISBL CV & FE Process Data (Copy Areas)
06-Jun-25
23-Aug-25
100%
EK000SY127
020 ISBL CV & FE Process Data (Almost Copy)
19-Jun-25
23-Aug-25
100%
EK000SY125
020 ISBL CV & FE Process Data (New Areas)
24-Jun-25
23-Aug-25
100%
EK020SY060
020 ISBL P&ID's - IPL & Line List Issue (Copy Areas)
27-Jun-25
04-Oct-25
100%
EK020SY070
020 ISBL P&ID's - IPL & Line List Issue(Almost Copy)
27-Jun-25
04-Oct-25
100%
EK020SY146
020 Relief Valve Calculations - ISBL (Copy Areas)
15-Jul-25
28-Sep-25
100%
EK020SY147
020 Relief Valve Calculations - ISBL (Almost Copy)
15-Jul-25
28-Sep-25
100%
EK020SY145
020 Relief Valve Calculations - ISBL (New Areas)
24-Aug-25
28-Sep-25
100%
EK020SY195
020 Issue Requisition -PSA08 Relief Valves (New Areas)
03-Sep-25
19-Nov-25
100%
EK020SY080
020 ISBL P&ID's - IPL & Line List Issue (New Areas)
17-Sep-25
04-Oct-25
100%
EK020SY156
020 SP Item Data Sheets - ISBL
20-Sep-25
24-Dec-25
100%
EK000SY100
020 ISBL P&ID's - Tech Review
04-Oct-25
04-Oct-25
100%
EK020SY196
020 Issue Requisition - PSA08 Relief Valves (Copy Areas)
05-Oct-25
19-Nov-25
100%
EK020SY197
020 Issue Requisition - PSA08 Relief Valves (Almost Copy)
05-Oct-25
19-Nov-25
100%
EK020SY090
020 ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02ASY170
02A ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02BSY170
02B ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02CSY170
02C ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02DSY170
02D ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02ESY170
02E ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02FSY170
02F ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02GSY170
02G ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02HSY170
02H ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02JSY170
02J ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02KSY170
02K ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02LSY170
02L ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02MSY170
02M ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02NSY170
02N ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02PSY170
02P ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02QSY170
02Q ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
EK02YSY170
02Y ISBL P&IDs IPL & Line List Issue Milestone
07-Oct-25
07-Oct-25
100%
27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec Data Date
EK000SY020 — 020 ISBL Hydraulic Calculations | 14-Feb-25 → 18-May-25 | Complete 100% | float — EK000SY020 EK020SY020 — 020 ISBL P&ID development IDR & Line List Issue | 19-Feb-25 → 23-Mar-25 | Complete 100% | float — EK020SY020 EK020SY030 — 020 ISBL P&ID IDR Meeting milestone | 03-Apr-25 → 04-Apr-25 | Complete 100% | float — EK020SY030 EK020SY040 — 020 ISBL P&IDs - ICA & Line List Issue development | 06-Apr-25 → 21-May-25 | Complete 100% | float — EK020SY040 EK020SY050 — 020 ISBL P&IDs - ICA & Line List Issue Milestone | 21-May-25 | Complete EK000SY126 — 020 ISBL CV & FE Process Data (Copy Areas) | 06-Jun-25 → 23-Aug-25 | Complete 100% | float — EK000SY126 EK000SY127 — 020 ISBL CV & FE Process Data (Almost Copy) | 19-Jun-25 → 23-Aug-25 | Complete 100% | float — EK000SY127 EK000SY125 — 020 ISBL CV & FE Process Data (New Areas) | 24-Jun-25 → 23-Aug-25 | Complete 100% | float — EK000SY125 EK020SY060 — 020 ISBL P&ID's - IPL & Line List Issue (Copy Areas) | 27-Jun-25 → 04-Oct-25 | Complete 100% | float — EK020SY060 EK020SY070 — 020 ISBL P&ID's - IPL & Line List Issue(Almost Copy) | 27-Jun-25 → 04-Oct-25 | Complete 100% | float — EK020SY070 EK020SY146 — 020 Relief Valve Calculations - ISBL (Copy Areas) | 15-Jul-25 → 28-Sep-25 | Complete 100% | float — EK020SY146 EK020SY147 — 020 Relief Valve Calculations - ISBL (Almost Copy) | 15-Jul-25 → 28-Sep-25 | Complete 100% | float — EK020SY147 EK020SY145 — 020 Relief Valve Calculations - ISBL (New Areas) | 24-Aug-25 → 28-Sep-25 | Complete 100% | float — EK020SY145 EK020SY195 — 020 Issue Requisition -PSA08 Relief Valves (New Areas) | 03-Sep-25 → 19-Nov-25 | Complete 100% | float — EK020SY195 EK020SY080 — 020 ISBL P&ID's - IPL & Line List Issue (New Areas) | 17-Sep-25 → 04-Oct-25 | Complete 100% | float — EK020SY080 EK020SY156 — 020 SP Item Data Sheets - ISBL | 20-Sep-25 → 24-Dec-25 | Complete 100% | float — EK020SY156 EK000SY100 — 020 ISBL P&ID's - Tech Review | 04-Oct-25 → 04-Oct-25 | Complete 100% | float — EK020SY196 — 020 Issue Requisition - PSA08 Relief Valves (Copy Areas) | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK020SY196 EK020SY197 — 020 Issue Requisition - PSA08 Relief Valves (Almost Copy) | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK020SY197 EK020SY090 — 020 ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02ASY170 — 02A ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02BSY170 — 02B ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02CSY170 — 02C ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02DSY170 — 02D ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02ESY170 — 02E ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02FSY170 — 02F ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02GSY170 — 02G ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02HSY170 — 02H ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02JSY170 — 02J ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02KSY170 — 02K ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02LSY170 — 02L ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02MSY170 — 02M ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02NSY170 — 02N ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02PSY170 — 02P ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02QSY170 — 02Q ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete EK02YSY170 — 02Y ISBL P&IDs IPL & Line List Issue Milestone | 07-Oct-25 | Complete