EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 9
activities
in SE Safety Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000FP030
FP ISBL Firewater P&IDs - Development & Issue ICA
06-Apr-25
19-Jun-25
—
100%
EK020FP480
FP ISBL Fire Protection Eqmt. Location Plans - ICA
03-May-25
28-Jun-25
—
100%
EK000FP005
FP Electrical Area Classification ISBL - ICA
28-May-25
27-Jun-25
—
100%
EK000FP032
FP ISBL Firewater P&IDs - Development & Issue IPL
19-Jun-25
07-Oct-25
—
100%
EK000FP036
FP ISBL Firewater P&IDs - Development & Issue IFC
17-Sep-25
27-Dec-26
—
47%
EK020FP410
FP Electrical Area Classification ISBL - IPL
02-Oct-25
10-Oct-25
—
100%
EK020FP500
FP ISBL Fire Protection Eqmt. Location Plans - IPL
02-Oct-25
31-Oct-25
—
100%
EK020FP450
FP Electrical Area Classification ISBL - IFC
31-Mar-26
22-Apr-26
—
100%
EK000FP034
FP ISBL Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
—
0%