EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 10
activities
in PE Project Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
—
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
—
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
—
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
—
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
—
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
—
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
—
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
—
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
—
100%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
—
100%