EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 10 activities in PE Project Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000PE085
Participate in Escalation confirmation effort
22-Jan-25
01-Mar-25
100%
EK000PE125
Preliminary Issue - Equipment List
29-Jan-25
12-Feb-25
100%
EK000PE050
Confirm of Split of Work for MEC
02-Feb-25
23-Feb-25
100%
EK000PE010
Publish Unit conversion standard
05-Feb-25
16-Feb-25
100%
EK000PE040
Devlop & Issue List of Project Specs & Standards
05-Feb-25
16-Feb-25
100%
EK000PE110
Issue Draft Project Design Data
05-Feb-25
06-Mar-25
100%
EK000PE090
Develop & Issue Engineering Plan
12-Feb-25
02-Mar-25
100%
EK000PE060
Define Task Force Area in MEC
26-Feb-25
28-Feb-25
100%
EK000PE075
MEC Organization Chart
26-Feb-25
28-Feb-25
100%
EK000PE070
Kick-off meeting at MEC
22-Aug-25
23-Aug-25
100%
30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug Data Date
EK000PE085 — Participate in Escalation confirmation effort | 22-Jan-25 → 01-Mar-25 | Complete 100% | float — EK000PE085 EK000PE125 — Preliminary Issue - Equipment List | 29-Jan-25 → 12-Feb-25 | Complete 100% | float — EK000PE125 EK000PE050 — Confirm of Split of Work for MEC | 02-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PE050 EK000PE010 — Publish Unit conversion standard | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE010 EK000PE040 — Devlop & Issue List of Project Specs & Standards | 05-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000PE040 EK000PE110 — Issue Draft Project Design Data | 05-Feb-25 → 06-Mar-25 | Complete 100% | float — EK000PE110 EK000PE090 — Develop & Issue Engineering Plan | 12-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000PE090 EK000PE060 — Define Task Force Area in MEC | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE060 EK000PE075 — MEC Organization Chart | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000PE075 EK000PE070 — Kick-off meeting at MEC | 22-Aug-25 → 23-Aug-25 | Complete 100% | float — EK000PE070