EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 30 activities in SY Systems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000SY005
Systems Work Plan & Project Setup
21-Jan-25
25-Mar-25
100%
EK000SY010
MEC Convert prelim P&ID's to Smart Plant P&ID's
22-Jan-25
16-Feb-25
100%
EK000SY015
Develop Utility & offsite block flow diagrams
05-Feb-25
16-Mar-25
100%
EK000SY065
Complete Utility Flow Diagrams
05-Feb-25
03-Apr-25
100%
EK000ML50B
Develop/Issue Load Sht & Design Data ERW - ML500
27-Feb-25
05-Mar-25
100%
EK000ML31B
Develop & Issue Design Data for ERW - ML313
06-Mar-25
15-Mar-25
100%
EK000MU41B
Develop & Issue Design Data for ERW - MU410
19-Mar-25
21-Mar-25
100%
EK000ML44B
Develop & Issue Design Data for ERW - ML440
26-Mar-25
27-Mar-25
100%
EK000MU61B
Develop/Issue Load Sht & Design Data ERW - MU611
02-Apr-25
14-May-25
100%
EK000MU30B
Develop/Issue Load Sht & Design Data ERW - MU300
09-Apr-25
25-Apr-25
100%
EK000ML51B
Develop/Issue Load Sht & Design Data ERW - ML512
15-Apr-25
19-Apr-25
100%
EK000ML42B
Develop & Issue Design Data for ERW - ML420
16-Apr-25
20-Apr-25
100%
EK000ML33B
Develop/Issue Load Sht & Design Data ERW - ML330
16-Apr-25
25-Apr-25
100%
EK000MU11B
05B MU311 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU25B
02G MU225 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU32B
01D MU322 Develop/Issue Load Sht & Design Data ERW
22-Apr-25
16-May-25
100%
EK000MU31B
Develop/Issue Load Sht & Design Data ERW - MU310
23-Apr-25
16-May-25
100%
EK000MU35B
Develop & Issue Design Data for ERW - MU350
01-May-25
14-May-25
100%
EK000MU11O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU25O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU310
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU32O
Finalize Water Analysis for Design Basis
01-May-25
16-Jul-25
100%
EK000MU33B
Develop/Issue Load Sht & Design Data ERW - MU330
07-May-25
20-May-25
100%
EK000MU21B
Develop/Issue Load Sht & Design Data ERW - MU221
08-May-25
10-May-25
100%
EK000MU22B
Develop/Issue Load Sht & Design Data ERW - MU222
08-May-25
20-May-25
100%
EK000MU29B
Develop/Issue Load Sht & Design Data ERW - MU292
08-May-25
20-May-25
100%
EK000MU34B
Develop/Issue Load Sht & Design Data ERW - Chlorination Unit
11-Jun-25
15-Jun-25
100%
PK000PSA8C
000 Relief Valves - Technical Evaluation
23-Dec-25
27-Dec-25
100%
EK000SY095
010 P&ID's - Tech Review
28-Jan-26
29-Jan-26
100%
EK000PS00C
000 SP Items - Technical Evaluation
11-Feb-26
01-Mar-26
100%
30-Dec 06-Jan 13-Jan 20-Jan 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar Data Date
EK000SY005 — Systems Work Plan & Project Setup | 21-Jan-25 → 25-Mar-25 | Complete 100% | float — EK000SY005 EK000SY010 — MEC Convert prelim P&ID's to Smart Plant P&ID's | 22-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000SY010 EK000SY015 — Develop Utility & offsite block flow diagrams | 05-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000SY015 EK000SY065 — Complete Utility Flow Diagrams | 05-Feb-25 → 03-Apr-25 | Complete 100% | float — EK000SY065 EK000ML50B — Develop/Issue Load Sht & Design Data ERW - ML500 | 27-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000ML50B EK000ML31B — Develop & Issue Design Data for ERW - ML313 | 06-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000ML31B EK000MU41B — Develop & Issue Design Data for ERW - MU410 | 19-Mar-25 → 21-Mar-25 | Complete 100% | float — EK000MU41B EK000ML44B — Develop & Issue Design Data for ERW - ML440 | 26-Mar-25 → 27-Mar-25 | Complete 100% | float — EK000MU61B — Develop/Issue Load Sht & Design Data ERW - MU611 | 02-Apr-25 → 14-May-25 | Complete 100% | float — EK000MU61B EK000MU30B — Develop/Issue Load Sht & Design Data ERW - MU300 | 09-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MU30B EK000ML51B — Develop/Issue Load Sht & Design Data ERW - ML512 | 15-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000ML51B EK000ML42B — Develop & Issue Design Data for ERW - ML420 | 16-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000ML42B EK000ML33B — Develop/Issue Load Sht & Design Data ERW - ML330 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000ML33B EK000MU11B — 05B MU311 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU11B EK000MU25B — 02G MU225 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU25B EK000MU32B — 01D MU322 Develop/Issue Load Sht & Design Data ERW | 22-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU32B EK000MU31B — Develop/Issue Load Sht & Design Data ERW - MU310 | 23-Apr-25 → 16-May-25 | Complete 100% | float — EK000MU31B EK000MU35B — Develop & Issue Design Data for ERW - MU350 | 01-May-25 → 14-May-25 | Complete 100% | float — EK000MU35B EK000MU11O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU11O EK000MU25O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU25O EK000MU310 — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU310 EK000MU32O — Finalize Water Analysis for Design Basis | 01-May-25 → 16-Jul-25 | Complete 100% | float — EK000MU32O EK000MU33B — Develop/Issue Load Sht & Design Data ERW - MU330 | 07-May-25 → 20-May-25 | Complete 100% | float — EK000MU33B EK000MU21B — Develop/Issue Load Sht & Design Data ERW - MU221 | 08-May-25 → 10-May-25 | Complete 100% | float — EK000MU21B EK000MU22B — Develop/Issue Load Sht & Design Data ERW - MU222 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU22B EK000MU29B — Develop/Issue Load Sht & Design Data ERW - MU292 | 08-May-25 → 20-May-25 | Complete 100% | float — EK000MU29B EK000MU34B — Develop/Issue Load Sht & Design Data ERW - Chlorination Unit | 11-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000MU34B PK000PSA8C — 000 Relief Valves - Technical Evaluation | 23-Dec-25 → 27-Dec-25 | Complete 100% | float — PK000PSA8C EK000SY095 — 010 P&ID's - Tech Review | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000PS00C — 000 SP Items - Technical Evaluation | 11-Feb-26 → 01-Mar-26 | Complete 100% | float — EK000PS00C