Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in SE Safety Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
EK000FP025 — FP Gas Detection Location Plans - Not Required | 22-Feb-25 → 23-Aug-25 | Complete 100% | float — EK000FP025 EK000FP050 — FP Overall Firewater P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK000FP050 EK000FP055 — FP Overall Firewater P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK000FP055 EK000FP060 — FP Overall Firewater P&IDs - Development & Issue IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP065 — FP Overall Firewater P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —