EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in SE Safety Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000FP025
FP Gas Detection Location Plans - Not Required
22-Feb-25
23-Aug-25
100%
EK000FP050
FP Overall Firewater P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK000FP055
FP Overall Firewater P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK000FP060
FP Overall Firewater P&IDs - Development & Issue IFD
27-Dec-26
27-Dec-26
0%
EK000FP065
FP Overall Firewater P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK000FP025 — FP Gas Detection Location Plans - Not Required | 22-Feb-25 → 23-Aug-25 | Complete 100% | float — EK000FP025 EK000FP050 — FP Overall Firewater P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK000FP050 EK000FP055 — FP Overall Firewater P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK000FP055 EK000FP060 — FP Overall Firewater P&IDs - Development & Issue IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000FP065 — FP Overall Firewater P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —