EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 23 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
100%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Data Date
EK000PI080 — Develop Split of work | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PI120 — Identify priority pipe classes | 05-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000PI115 — Develop Piping Class Index (IOPMC) | 05-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000PI132 — Develop Early Tech P-Class specs for Procurement | 05-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PI132 EK000PI040 — Prepare technology work plan - Piping Engr. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI060 — Prepare Other Project Documentation | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI051 — Prepare P/Mech Support Details | 12-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000PI110 — Locate FMCL Documents | 14-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PI160 — P&ID Area Break Mark-up | 19-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000PI020 — Develop Piping Specs (Paper) | 19-Feb-25 → 28-May-25 | Complete 100% | float — EK000PI020 EK000PI005 — Locate Permanent Tie in pnts Gas, Wtr, Storm wtr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PI133 — Dvlp/Issue V-class specs & Standads for Procurmt | 26-Feb-25 → 09-Apr-25 | Complete 100% | float — EK000PI133 EK000PI125 — Validate new plot layout (impacts on pipe stress | 02-Mar-25 → 21-May-25 | Complete 100% | float — EK000PI125 EK000PI055 — Prepare Object Engineering Work Instruction | 08-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI085 — Estimate/Schedule Review | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI105 — Performance Test of Citrix for PDS w/MEC | 12-Mar-25 → 12-Mar-25 | Complete 100% | float — EK000PI100 — Critical Line List | 12-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000PI131 — Devlop Balance Tech P-Class specs for Procuremnt | 06-Apr-25 → 25-May-25 | Complete 100% | float — EK000PI131 PK000PIA1C — Bulk Piping A/G & U/G - Tech Evaluation | 07-May-25 → 21-Jun-25 | Complete 100% | float — PK000PIA1C PK000PIA4C — Product Line Piping - Tech Evaluation | 07-Jun-25 → 04-Jul-25 | Complete 100% | float — PK000PTA0F — Engineered Pipe Supports - Planning V. Data | 14-Aug-25 → 24-Jan-26 | Complete 100% | float — PK000PTA0F PK000PTA0H — Engineered Pipe Supports - Production V. Data | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000PI200 — Final Delta Piping Bulk Quanities for Purchase | 03-Jan-27 | Not Started