Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 23 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
100%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
0%
Jan 2025 Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Data Date
EK000PI080 — Develop Split of work | 29-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000PI080 EK000PI120 — Identify priority pipe classes | 05-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000PI120 EK000PI115 — Develop Piping Class Index (IOPMC) | 05-Feb-25 → 13-Mar-25 | Complete 100% | float — EK000PI115 EK000PI132 — Develop Early Tech P-Class specs for Procurement | 05-Feb-25 → 22-Mar-25 | Complete 100% | float — EK000PI132 EK000PI040 — Prepare technology work plan - Piping Engr. | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI040 EK000PI060 — Prepare Other Project Documentation | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000PI060 EK000PI051 — Prepare P/Mech Support Details | 12-Feb-25 → 15-Mar-25 | Complete 100% | float — EK000PI051 EK000PI110 — Locate FMCL Documents | 14-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000PI110 EK000PI160 — P&ID Area Break Mark-up | 19-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000PI160 EK000PI020 — Develop Piping Specs (Paper) | 19-Feb-25 → 28-May-25 | Complete 100% | float — EK000PI020 EK000PI005 — Locate Permanent Tie in pnts Gas, Wtr, Storm wtr | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000PI005 EK000PI133 — Dvlp/Issue V-class specs & Standads for Procurmt | 26-Feb-25 → 09-Apr-25 | Complete 100% | float — EK000PI133 EK000PI125 — Validate new plot layout (impacts on pipe stress | 02-Mar-25 → 21-May-25 | Complete 100% | float — EK000PI125 EK000PI055 — Prepare Object Engineering Work Instruction | 08-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI055 EK000PI085 — Estimate/Schedule Review | 09-Mar-25 → 15-Mar-25 | Complete 100% | float — EK000PI085 EK000PI105 — Performance Test of Citrix for PDS w/MEC | 12-Mar-25 → 12-Mar-25 | Complete 100% | float — EK000PI100 — Critical Line List | 12-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000PI100 EK000PI131 — Devlop Balance Tech P-Class specs for Procuremnt | 06-Apr-25 → 25-May-25 | Complete 100% | float — EK000PI131 PK000PIA1C — Bulk Piping A/G & U/G - Tech Evaluation | 07-May-25 → 21-Jun-25 | Complete 100% | float — PK000PIA1C PK000PIA4C — Product Line Piping - Tech Evaluation | 07-Jun-25 → 04-Jul-25 | Complete 100% | float — PK000PIA4C PK000PTA0F — Engineered Pipe Supports - Planning V. Data | 14-Aug-25 → 24-Jan-26 | Complete 100% | float — PK000PTA0F PK000PTA0H — Engineered Pipe Supports - Production V. Data | 24-Jan-26 → 29-Jan-26 | Complete 100% | float — PK000PTA0H EK000PI200 — Final Delta Piping Bulk Quanities for Purchase | 03-Jan-27 | Not Started