EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 23
activities
in PI Piping Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000PI080
Develop Split of work
29-Jan-25
23-Feb-25
—
100%
EK000PI120
Identify priority pipe classes
05-Feb-25
20-Feb-25
—
100%
EK000PI115
Develop Piping Class Index (IOPMC)
05-Feb-25
13-Mar-25
—
100%
EK000PI132
Develop Early Tech P-Class specs for Procurement
05-Feb-25
22-Mar-25
—
100%
EK000PI040
Prepare technology work plan - Piping Engr.
12-Feb-25
09-Mar-25
—
100%
EK000PI060
Prepare Other Project Documentation
12-Feb-25
09-Mar-25
—
100%
EK000PI051
Prepare P/Mech Support Details
12-Feb-25
15-Mar-25
—
100%
EK000PI110
Locate FMCL Documents
14-Feb-25
23-Feb-25
—
100%
EK000PI160
P&ID Area Break Mark-up
19-Feb-25
08-Mar-25
—
100%
EK000PI020
Develop Piping Specs (Paper)
19-Feb-25
28-May-25
—
100%
EK000PI005
Locate Permanent Tie in pnts Gas, Wtr, Storm wtr
26-Feb-25
16-Mar-25
—
100%
EK000PI133
Dvlp/Issue V-class specs & Standads for Procurmt
26-Feb-25
09-Apr-25
—
100%
EK000PI125
Validate new plot layout (impacts on pipe stress
02-Mar-25
21-May-25
—
100%
EK000PI055
Prepare Object Engineering Work Instruction
08-Mar-25
15-Mar-25
—
100%
EK000PI085
Estimate/Schedule Review
09-Mar-25
15-Mar-25
—
100%
EK000PI105
Performance Test of Citrix for PDS w/MEC
12-Mar-25
12-Mar-25
—
100%
EK000PI100
Critical Line List
12-Mar-25
06-Apr-25
—
100%
EK000PI131
Devlop Balance Tech P-Class specs for Procuremnt
06-Apr-25
25-May-25
—
100%
PK000PIA1C
Bulk Piping A/G & U/G - Tech Evaluation
07-May-25
21-Jun-25
—
100%
PK000PIA4C
Product Line Piping - Tech Evaluation
07-Jun-25
04-Jul-25
—
100%
PK000PTA0F
Engineered Pipe Supports - Planning V. Data
14-Aug-25
24-Jan-26
—
100%
PK000PTA0H
Engineered Pipe Supports - Production V. Data
24-Jan-26
29-Jan-26
—
100%
EK000PI200
Final Delta Piping Bulk Quanities for Purchase
03-Jan-27
03-Jan-27
—
0%