EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 150
activities
in MJ Machinery Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000MJ005
Prepare Machinery Specs (Motors, Pkg Equipment)
05-Feb-25
25-Feb-25
—
100%
EK000MJ31C
Prepare & Issue Prelim. RFQ - MJ301 to Proc.
13-Feb-25
13-Feb-25
—
100%
EK000MJ32C
Prepare & Issue Prelim. RFQ - MJ302 to Proc.
13-Feb-25
13-Feb-25
—
100%
EK000MJ22C
Prepare & Issue Prelim. RFQ - MJ201 to Proc.
19-Feb-25
19-Feb-25
—
100%
EK000MJ22B
Develop & Issue Design Data for ERW - MJ201
19-Feb-25
23-Feb-25
—
100%
EK000ML31C
Prepare & Issue Prelim. RFQ - ML313 to Proc.
19-Feb-25
23-Feb-25
—
100%
EK000MJ35C
Prepare & Issue Prelim. RFQ - MJ305 to Proc.
19-Feb-25
02-Mar-25
—
100%
EK000MJ36C
Prepare & Issue Prelim. RFQ - MJ306 to Proc.
19-Feb-25
02-Mar-25
—
100%
EK000MJ39C
Prepare & Issue Prelim. RFQ - MJ391 to Proc.
19-Feb-25
09-Mar-25
—
100%
EK000MJ21C
Prepare & Issue Prelim. RFQ - MJ202 to Proc.
20-Feb-25
20-Feb-25
—
100%
EK000ML50C
Prepare & Issue Prelim. RFQ - ML500 to Proc.
20-Feb-25
26-Feb-25
—
100%
EK000MJ21B
Develop & Issue Design Data for ERW - MJ202
22-Feb-25
07-Mar-25
—
100%
EK000MJ22F
Update/Issue Formal Inquiry for ERW - MJ201
26-Feb-25
09-Mar-25
—
100%
EK000MJ21D
Technical Evaluation - MJ202
05-Mar-25
05-Mar-25
—
100%
EK000ML42C
Prepare & Issue Prelim. RFQ - ML420 to Proc.
05-Mar-25
09-Mar-25
—
100%
EK000MU33C
Prepare & Issue Prelim. RFQ - MU330 to Proc.
05-Mar-25
09-Mar-25
—
100%
EK000ML50F
Update/Issue Formal Inquiry for ERW - ML500
06-Mar-25
27-Apr-25
—
100%
EK000MJ21F
Update/Issue Formal Inquiry for ERW - MJ202
08-Mar-25
13-Mar-25
—
100%
EK000MJ31B
Develop & Issue Design Data for ERW - MJ301
08-Mar-25
12-Apr-25
—
100%
EK000MU41F
Develop & Issue Inquiry for ERW - MU410
12-Mar-25
16-Mar-25
—
100%
EK000ML31F
Update/Issue Formal Inquiry for ERW - ML313
16-Mar-25
16-Mar-25
—
100%
EK000MJ22D
Technical Evaluation - MJ201
16-Mar-25
19-Mar-25
—
100%
EK000MU30F
Develop & Issue Inquiry for ERW - MU300
19-Mar-25
26-Mar-25
—
100%
EK000ML42F
Update/Issue Formal Inquiry for ERW - ML420
19-Mar-25
24-Apr-25
—
100%
EK000MU61F
Develop & Issue Inquiry for ERW - MU611
20-Mar-25
25-Mar-25
—
100%
EK000MU35F
Update/Issue Formal Inquiry for ERW - MU350
21-Mar-25
22-Mar-25
—
100%
EK000MJ32B
Develop & Issue Design Data for ERW - MJ302
21-Mar-25
13-Apr-25
—
100%
EK000MJ39B
Develop/Issue Load Sht & Design Data ERW - MJ391
25-Mar-25
29-Mar-25
—
100%
EK000ML50D
Technical Evaluation - ML500
25-Mar-25
27-Apr-25
—
100%
EK000MU33F
Update/Issue Formal Inquiry for ERW - MU330
26-Mar-25
04-Apr-25
—
100%
EK000MJ35D
Technical Evaluation - MJ305
27-Mar-25
02-Apr-25
—
100%
EK000MJ36D
Technical Evaluation - MJ306
27-Mar-25
02-Apr-25
—
100%
EK000MJ34B
Develop/Issue Load Sht & Design Data ERW - MJ304
01-Apr-25
08-Apr-25
—
100%
EK000MJ39F
Update/Issue Formal Inquiry for ERW - MJ391
01-Apr-25
27-Apr-25
—
100%
EK000MJ35B
Develop & Issue Design Data for ERW - MJ305
05-Apr-25
09-May-25
—
100%
EK000ML31D
Technical Evaluation - ML313
05-Apr-25
19-Apr-25
—
100%
EK000MU35D
Technical Evaluation - MU350
08-Apr-25
19-Apr-25
—
100%
EK000ML42D
Technical Evaluation - ML420
09-Apr-25
19-Apr-25
—
100%
EK000MJ34F
Update/Issue Formal Inquiry for ERW - MJ304
09-Apr-25
26-Apr-25
—
100%
EK000MJ33B
Develop/Issue Load Sht & Design Data ERW - MJ303
11-Apr-25
23-May-25
—
100%
EK000MJ32D
Technical Evaluation - MJ302
12-Apr-25
19-Apr-25
—
100%
EK000MJ31D
Technical Evaluation - MJ301
12-Apr-25
25-Apr-25
—
100%
EK000MJ37B
Develop & Issue Design Data for ERW - MJ340
19-Apr-25
09-May-25
—
100%
EK000MJ73B
Develop/Issue Load Sht & Design Data ERW - MJ730
20-Apr-25
30-Apr-25
—
100%
EK000ML51F
Develop & Issue Inquiry for ERW - ML512
27-Apr-25
01-May-25
—
100%
EK000MJ31F
Update/Issue Formal Inquiry for ERW - MJ301
27-Apr-25
08-May-25
—
100%
EK000ML33F
Develop & Issue Inquiry for ERW - ML330
27-Apr-25
13-May-25
—
100%
EK000MJ32F
Update/Issue Formal Inquiry for ERW - MJ302
27-Apr-25
29-May-25
—
100%
EK000MJ36B
Develop/Issue Load Sht & Design Data ERW - MJ306
27-Apr-25
08-Jun-25
—
100%
EK000MJ75B
Develop & Issue Design Data for ERW - MJ750
01-May-25
20-May-25
—
100%
EK000MJ73F
Develop & Issue Inquiry for ERW - MJ730
01-May-25
12-Jun-25
—
100%
EK000MJ34D
Technical Evaluation - MJ304
02-May-25
03-May-25
—
100%
EK000MU41D
Technical Evaluation - MU410
03-May-25
28-Jun-25
—
100%
EK000MU61D
Technical Evaluation - MU611
07-May-25
20-Jun-25
—
100%
EK000MJ37F
Develop & Issue Inquiry for ERW - MJ340
09-May-25
05-Jun-25
—
100%
EK000MJ35F
Update/Issue Formal Inquiry for ERW - MJ305
10-May-25
24-May-25
—
100%
EK000MU30D
Technical Evaluation - MU300
13-May-25
27-Sep-25
—
100%
EK000MJ75F
Develop & Issue Inquiry for ERW - MJ750
21-May-25
28-May-25
—
100%
EK000MJ33F
Develop & Issue Inquiry for ERW - MJ303
28-May-25
18-Jun-25
—
100%
EK000MJ36F
Update/Issue Formal Inquiry for ERW - MJ306
28-May-25
19-Jun-25
—
100%
EK000MJ75D
Technical Evaluation - MJ750
29-May-25
30-May-25
—
100%
EK000ML43F
Develop & Issue Inquiry for ERW - ML430
31-May-25
06-Jun-25
—
100%
EK000MU33D
Technical Evaluation - MU330
04-Jun-25
01-Jul-25
—
100%
EK000MU22F
Develop & Issue Inquiry for ERW - MU222
05-Jun-25
26-Jun-25
—
100%
EK000MU21F
Develop & Issue Inquiry for ERW - MU221
26-Jun-25
03-Jul-25
—
100%
EK000ML33D
Technical Evaluation - ML330
10-Jul-25
23-Aug-25
—
100%
EK000ML43D
Technical Evaluation - ML430
10-Jul-25
06-Sep-25
—
100%
EK000MU22D
Technical Evaluation - MU222
22-Jul-25
06-Sep-25
—
100%
EK000MJ37D
Technical Evaluation - MJ340
24-Jul-25
28-Aug-25
—
100%
EK000MJ39D
Technical Evaluation - MJ391
25-Jul-25
21-Dec-25
—
100%
EK000MJ31X
Technical Evaluation - MJ301
25-Jul-25
10-Aug-25
—
100%
PK000MJ32X
Technical Evaluation - MJ302
25-Jul-25
10-Aug-25
—
100%
EK000MU11L
05B MU311 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MU25L
02G MU225 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MU32L
01D MU322 Define Chemical Treatment Requirements
29-Jul-25
09-Aug-25
—
100%
EK000MU31L
Define Chemical Treatment Requirements - MU310
30-Jul-25
10-Aug-25
—
100%
EK000ML51D
Technical Evaluation - ML512
30-Jul-25
19-Aug-25
—
100%
EK000MU21D
Technical Evaluation - MU221
30-Jul-25
14-Sep-25
—
100%
EK000MU35E
Prepare & Issue Purchase ERW - MU350
01-Aug-25
13-Aug-25
—
100%
EK000MJ73D
Technical Evaluation - MJ730
06-Aug-25
16-Sep-25
—
100%
PK000MJ21N
Recv. Planning V. Data MJ202
09-Aug-25
30-Aug-25
—
100%
PK000MJ75N
Recv. Planning V. Data MJ750
09-Aug-25
30-Aug-25
—
100%
PK000ML31N
Recv. Planning V. Data ML313
09-Aug-25
12-Sep-25
—
100%
EK000MJ21E
Prepare & Issue Purchase ERW - MJ202
12-Aug-25
30-Aug-25
—
100%
PK000MU35N
Recv. Planning V. Data MU350
12-Aug-25
27-Sep-25
—
100%
EK000MU61E
Prepare & Issue Purchase ERW - MU611
13-Aug-25
16-Aug-25
—
100%
EK000MJ75E
Prepare & Issue Purchase ERW - MJ750
19-Aug-25
28-Sep-25
—
100%
PK000MJ35N
Recv. Planning V. Data MJ305
23-Aug-25
27-Sep-25
—
100%
PK000MJ36N
Recv. Planning V. Data MJ306
23-Aug-25
27-Sep-25
—
100%
EK000MJ33D
Technical Evaluation - MJ303
30-Aug-25
19-Dec-25
—
100%
PK000MU21N
Recv. Planning V. Data MU221
01-Sep-25
27-Sep-25
—
100%
PK000ML42N
Recv. Planning V. Data ML420
02-Sep-25
26-Sep-25
—
100%
PK000MJ32N
Recv. Planning V. Data MJ302
02-Sep-25
27-Sep-25
—
100%
PK000MJ34N
Recv. Planning V. Data MJ304
02-Sep-25
27-Sep-25
—
100%
PK000MJ37N
Recv. Planning V. Data MJ340
02-Sep-25
27-Sep-25
—
100%
PK000MJ39N
Recv. Planning V. Data MJ391
02-Sep-25
27-Sep-25
—
100%
PK000MJ73N
Recv. Planning V. Data MJ730
02-Sep-25
27-Sep-25
—
100%
PK000MU22N
Recv. Planning V. Data MU222
02-Sep-25
27-Sep-25
—
100%
EK000MU41E
Prepare & Issue Purchase ERW - MU410
03-Sep-25
05-Sep-25
—
100%
PK000MU61N
Recv. Planning V. Data MU611
03-Sep-25
26-Sep-25
—
100%
PK000MJ22N
Recv. Planning V. Data MJ201
05-Sep-25
27-Sep-25
—
100%
PK000MJ31N
Recv. Planning V. Data MJ301
06-Sep-25
27-Sep-25
—
100%
EK000ML51E
Prepare & Issue Purchase ERW - ML512
11-Sep-25
25-Sep-25
—
100%
PK000ML51N
Recv. Planning V. Data ML512
11-Sep-25
27-Sep-25
—
100%
EK000MJ36E
Prepare & Issue Purchase ERW - MJ306
13-Sep-25
25-Sep-25
—
100%
EK000MJ35E
Prepare & Issue Purchase ERW - MJ305
13-Sep-25
25-Sep-25
—
100%
EK000MJ22E
Prepare & Issue Purchase ERW - MJ201
13-Sep-25
13-Nov-25
—
100%
EK000ML33E
Prepare & Issue Purchase ERW - ML330
17-Sep-25
25-Sep-25
—
100%
PK000MU41N
Recv. Planning V. Data MU410
17-Sep-25
27-Sep-25
—
100%
EK000MJ32E
Prepare & Issue Purchase ERW - MJ302
20-Sep-25
13-Nov-25
—
100%
PK000ML33N
Recv. Planning V. Data ML330
20-Sep-25
27-Sep-25
—
100%
PK000ML43N
Recv. Planning V. Data ML430
20-Sep-25
01-Nov-25
—
100%
EK000MJ34E
Prepare & Issue Final Data Shts - MJ304
21-Sep-25
08-Nov-25
—
100%
EK000MU33E
Prepare & Issue Purchase ERW - MU330
21-Sep-25
26-Sep-25
—
100%
EK000MU31D
Technical Evaluation - MU310
24-Sep-25
30-Sep-25
—
100%
EK000MU30E
Prepare & Issue Purchase ERW - MU300
01-Oct-25
14-Oct-25
—
100%
EK000ML42E
Prepare & Issue Purchase ERW - ML420
01-Oct-25
10-Oct-25
—
100%
EK000MJ37E
Prepare & Issue Purchase ERW - MJ340
01-Oct-25
16-Oct-25
—
100%
EK000MU31E
Prepare & Issue Purchase ERW - MU310
04-Oct-25
08-Oct-25
—
100%
EK000MJ31E
Prepare & Issue Purchase ERW - MJ301
08-Oct-25
13-Nov-25
—
100%
PK000MJ33N
Recv. Planning V. Data MJ303
08-Oct-25
26-Dec-25
—
100%
EK000ML31E
Prepare & Issue Purchase ERW - ML313
08-Oct-25
09-Jan-26
—
100%
PK000MU33N
03E MU330 2001-U - Piping Conceptual V. Data
30-Oct-25
02-Feb-26
—
100%
EK000ML43E
Prepare & Issue Purchase ERW - ML430
01-Nov-25
07-Nov-25
—
100%
EK000MU21E
Prepare & Issue Purchase ERW - MU221
05-Nov-25
22-Nov-25
—
100%
EK000MU22E
Prepare & Issue Purchase ERW - MU222
05-Nov-25
22-Nov-25
—
100%
EK000MU29F
Develop & Issue Inquiry for ERW - MU292
05-Nov-25
23-Nov-25
—
100%
EK000MJ37S
Develop & Issue Design Data for ERW - MJ307
11-Nov-25
15-Nov-25
—
100%
EK000MJ38S
Develop & Issue Design Data for ERW - MJ308
11-Nov-25
15-Nov-25
—
100%
EK000MJ37T
Update/Issue Formal Inquiry for ERW - MJ307
18-Nov-25
26-Nov-25
—
100%
EK000MJ73E
Prepare & Issue Purchase ERW - MJ730
19-Nov-25
05-Dec-25
—
100%
PK000MU30N
Recv. Planning V. Data MU300 - EDR Unit
19-Nov-25
10-Jan-26
—
100%
EK000ML50Z
Technical Evaluation - ML500
10-Dec-25
31-Dec-25
—
100%
EK000MJ33E
Prepare & Issue Purchase ERW - MJ303
19-Dec-25
27-Dec-25
—
100%
EK000MU32D
01D MU322 Technical Evaluation
23-Dec-25
31-Jan-26
—
100%
EK000MU11D
05B MU311 Technical Evaluation
03-Jan-26
01-Feb-26
—
100%
EK000MJ37C
Prepare & Issue Purchase ERW - MJ307
17-Jan-26
20-Jan-26
—
100%
EK000MU29D
Technical Evaluation - MU292
20-Jan-26
03-Mar-26
—
100%
EK000MU25D
02G MU225 Technical Evaluation
28-Jan-26
21-Feb-26
—
100%
PK000ML50N
Recv. Planning V. Data ML500
29-Jan-26
24-Feb-26
—
100%
EK000MU11E
05B MU311 Prepare & Issue Purchase ERW
11-Feb-26
13-Feb-26
—
100%
PK000MU11N
05B MU311 Recv. Planning V. Data
13-Feb-26
28-Feb-26
—
100%
EK000MJ38T
Update/Issue Formal Inquiry for ERW - MJ308
25-Feb-26
03-Mar-26
—
100%
EK000ML50E
Prepare & Issue Purchase ERW - ML500
25-Feb-26
08-Mar-26
—
100%
EK000MJ39E
Prepare & Issue Purchase ERW - MJ391
27-Feb-26
09-Apr-26
—
100%
PK000MU29N
Recv. Planning V. Data MU292
19-Mar-26
09-Apr-26
—
100%
EK000MU29E
Prepare & Issue Purchase ERW - MU292
24-Mar-26
27-Mar-26
—
100%
EK000MU32E
01D MU322 Prepare & Issue Purchase ERW
31-Mar-26
31-Mar-26
—
100%
EK000MU25E
02G MU225 Prepare & Issue Purchase ERW
01-Apr-26
27-Dec-26
—
9%
EK000MJ38C
Prepare & Issue Purchase ERW - MJ308
23-Apr-26
27-Dec-26
—
5%