EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 71
activities
in MD Vessels Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
—
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
—
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
—
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
—
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
—
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
—
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
—
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
—
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
—
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
—
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
—
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
—
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
—
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
—
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
—
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
—
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
—
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
—
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
—
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
—
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
—
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
—
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
—
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
—
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
—
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
—
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
—
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
—
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
—
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
—
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
—
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
—
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
—
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
—
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
—
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
—
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
—
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
—
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
—
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
—
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
—
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
—
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
—
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
—
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
—
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
—
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
—
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
—
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
—
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
—
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
—
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
—
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
—
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
—
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
—
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
—
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
—
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
—
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
—
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
—
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
—
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
—
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
—
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
—
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
—
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
—
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
—
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
—
100%