EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 71 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000MD005
Attend Alignment & strategy meetings
22-Jan-25
09-Feb-25
100%
EK000MD015
Conversion of drawings to metric units
22-Jan-25
19-Feb-25
100%
EK000MD31C
Prepare & Issue Prelim. RFQ - MD301 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD32C
Prepare & Issue Prelim. RFQ - MD302 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD34C
Prepare & Issue Prelim. RFQ - MD304 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD51C
Prepare & Issue Prelim. RFQ - MD501 to Proc.
12-Feb-25
16-Feb-25
100%
EK000MD41C
Prepare & Issue Prelim. RFQ - MD401 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD43C
Prepare & Issue Prelim. RFQ - MD403 to Proc.
19-Feb-25
20-Feb-25
100%
EK000MD33C
Prepare & Issue Prelim. RFQ - MD303 to Proc.
19-Feb-25
22-Feb-25
100%
EK000MD33B
Develop & Issue Design Data for ERW - MD303
26-Feb-25
08-Mar-25
100%
EK000MD060
Prepare Vessel work plan & other quality documents
02-Mar-25
02-Mar-25
100%
EK000MD020
Equipment Modeling for Vessel - MEC
13-Mar-25
25-Mar-26
100%
EK000MD31B
Develop & Issue Design Data for ERW - MD301
16-Mar-25
19-Mar-25
100%
EK000MD32B
Develop & Issue Design Data for ERW - MD302
16-Mar-25
19-Mar-25
100%
EK000MD34B
Develop & Issue Design Data for ERW - MD304
16-Mar-25
19-Mar-25
100%
EK000MD34D
Technical Evaluation - MD304
16-Mar-25
23-Apr-25
100%
EK000MD41D
Technical Evaluation - MD401
16-Mar-25
23-Apr-25
100%
EK000MF33B
Develop/Issue Load Sht & Design Data ERW - MF311
19-Mar-25
26-Mar-25
100%
EK000MF32B
Develop/Issue Load Sht & Design Data ERW - MF302
19-Mar-25
06-Apr-25
100%
EK000MD21B
Develop & Issue Design Data for ERW - MD201
19-Mar-25
08-May-25
100%
EK000MD51B
Develop & Issue Design Data for ERW - MD501
21-Mar-25
28-Mar-25
100%
EK000MD34F
Update/Issue Formal Inquiry for ERW - MD304
21-Mar-25
20-Apr-25
100%
EK000MD025
Prepare job quality drawings for ERW
25-Mar-25
28-May-25
100%
EK000MD51D
Technical Evaluation - MD501
26-Mar-25
03-Apr-25
100%
EK000MD33F
Update/Issue Formal Inquiry for ERW - MD303
26-Mar-25
11-May-25
100%
EK000MF32F
Develop & Issue Design Data for Tank Subcontract - MF302
26-Mar-25
08-Apr-25
100%
EK000MF33F
Develop & Issue Design Data for Tank Subcontract - MF311
27-Mar-25
09-Apr-25
100%
EK000MD51F
Update/Issue Formal Inquiry for ERW - MD501
29-Mar-25
08-Apr-25
100%
EK000MF31B
Develop & Issue Design Data for Tank Subcontrac - MF301
01-Apr-25
08-Apr-25
100%
EK000MD31F
Update/Issue Formal Inquiry for ERW - MD301
02-Apr-25
16-Apr-25
100%
EK000MD32F
Update/Issue Formal Inquiry for ERW - MD302
02-Apr-25
20-Apr-25
100%
EK000MD43D
Technical Evaluation - MD403
02-Apr-25
25-Apr-25
100%
EK000MD43B
Develop & Issue Design Data for ERW - MD403
08-Apr-25
12-Apr-25
100%
EK000MD45B
Develop & Issue Design Data for ERW - MD405
08-Apr-25
08-May-25
100%
EK000MD42B
Develop & Issue Design Data for ERW - MD402
09-Apr-25
13-Apr-25
100%
EK000MD41B
Develop & Issue Design Data for ERW - MD401
09-Apr-25
18-Apr-25
100%
EK000MD43F
Update/Issue Formal Inquiry for ERW - MD403
15-Apr-25
25-Apr-25
100%
EK000MD32D
Technical Evaluation - MD302
15-Apr-25
04-May-25
100%
EK000MD42F
Update/Issue Formal Inquiry for ERW - MD402
16-Apr-25
19-Apr-25
100%
EK000MD31D
Technical Evaluation - MD301
16-Apr-25
25-Apr-25
100%
EK000MD33D
Technical Evaluation - MD303
16-Apr-25
04-May-25
100%
EK000MD21F
Develop & Issue Inquiry ERW - MD201
17-Apr-25
17-Jun-25
100%
EK000MD41F
Update/Issue Formal Inquiry for ERW - MD401
20-Apr-25
26-Apr-25
100%
EK000MD44B
Develop & Issue Design Data for ERW - MD404
22-Apr-25
25-Apr-25
100%
EK000MD47B
Develop & Issue Design Data for ERW - MD406
22-Apr-25
25-Apr-25
100%
EK000MD22B
Develop & Issue Design Data for ERW - MD202
23-Apr-25
01-May-25
100%
EK000MD44F
Update/Issue Formal Inquiry for ERW - MD404
27-Apr-25
01-May-25
100%
EK000MD22F
Update/Issue Formal Inquiry for ERW - MD202
01-May-25
17-May-25
100%
EK000MD31E
Prepare & Issue Purchase ERW - MD301
04-May-25
11-May-25
100%
EK000MD34E
Prepare & Issue Purchase ERW - MD304
04-May-25
11-May-25
100%
EK000MD32E
Prepare & Issue Purchase ERW - MD302
06-May-25
10-May-25
100%
EK000MD43E
Prepare & Issue Purchase ERW - MD403
06-May-25
11-May-25
100%
EK000MD51E
Prepare & Issue Purchase ERW - MD501
09-May-25
11-May-25
100%
EK000MD45F
Update/Issue Formal Inquiry for ERW - MD405
13-May-25
31-May-25
100%
EK000MD46F
Update/Issue Formal Inquiry for ERW - MD411
14-May-25
31-May-25
100%
EK000MD33E
Prepare & Issue Purchase ERW - MD303
01-Jul-25
04-Jul-25
100%
EK000MD41E
Prepare & Issue Purchase ERW - MD401
01-Jul-25
04-Jul-25
100%
EK000MD21D
Technical Evaluation - MD201
16-Jul-25
10-Aug-25
100%
PK000MD31N
Recv. Planning V. Data MD301
09-Aug-25
09-Sep-25
100%
PK000MD41N
Recv. Planning V. Data MD401
09-Aug-25
17-Sep-25
100%
PK000MD33N
Recv. Planning V. Data MD303
09-Aug-25
25-Sep-25
100%
PK000MD43N
Recv. Planning V. Data MD403
09-Aug-25
14-Oct-25
100%
PK000MD32N
Recv. Planning V. Data MD302
16-Aug-25
02-Oct-25
100%
PK000MD34N
Recv. Planning V. Data MD304
16-Aug-25
12-Nov-25
100%
EK000MD21E
Prepare & Issue Purchase ERW - MD201
27-Aug-25
29-Aug-25
100%
PK000MD51N
Recv. Planning V. Data MD501
27-Aug-25
01-Nov-25
100%
EK000MD055
Pre-qualification trip to vendors shop (105-D)
03-Sep-25
05-Sep-25
100%
EK000MD103
MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW
10-Oct-25
26-Nov-25
100%
EK000MD102
MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur.
26-Nov-25
05-Dec-25
100%
EK000MD104
MD305 Merc. Removal Bed - Technical Evaluation
13-Jan-26
29-Jan-26
100%
EK000MD105
MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW
29-Jan-26
01-Feb-26
100%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Data Date
EK000MD005 — Attend Alignment & strategy meetings | 22-Jan-25 → 09-Feb-25 | Complete 100% | float — EK000MD015 — Conversion of drawings to metric units | 22-Jan-25 → 19-Feb-25 | Complete 100% | float — EK000MD31C — Prepare & Issue Prelim. RFQ - MD301 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD32C — Prepare & Issue Prelim. RFQ - MD302 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD34C — Prepare & Issue Prelim. RFQ - MD304 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD51C — Prepare & Issue Prelim. RFQ - MD501 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MD41C — Prepare & Issue Prelim. RFQ - MD401 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD43C — Prepare & Issue Prelim. RFQ - MD403 to Proc. | 19-Feb-25 → 20-Feb-25 | Complete 100% | float — EK000MD33C — Prepare & Issue Prelim. RFQ - MD303 to Proc. | 19-Feb-25 → 22-Feb-25 | Complete 100% | float — EK000MD33B — Develop & Issue Design Data for ERW - MD303 | 26-Feb-25 → 08-Mar-25 | Complete 100% | float — EK000MD060 — Prepare Vessel work plan & other quality documents | 02-Mar-25 → 02-Mar-25 | Complete 100% | float — EK000MD020 — Equipment Modeling for Vessel - MEC | 13-Mar-25 → 25-Mar-26 | Complete 100% | float — EK000MD020 EK000MD31B — Develop & Issue Design Data for ERW - MD301 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD32B — Develop & Issue Design Data for ERW - MD302 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34B — Develop & Issue Design Data for ERW - MD304 | 16-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MD34D — Technical Evaluation - MD304 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD34D EK000MD41D — Technical Evaluation - MD401 | 16-Mar-25 → 23-Apr-25 | Complete 100% | float — EK000MD41D EK000MF33B — Develop/Issue Load Sht & Design Data ERW - MF311 | 19-Mar-25 → 26-Mar-25 | Complete 100% | float — EK000MF32B — Develop/Issue Load Sht & Design Data ERW - MF302 | 19-Mar-25 → 06-Apr-25 | Complete 100% | float — EK000MD21B — Develop & Issue Design Data for ERW - MD201 | 19-Mar-25 → 08-May-25 | Complete 100% | float — EK000MD21B EK000MD51B — Develop & Issue Design Data for ERW - MD501 | 21-Mar-25 → 28-Mar-25 | Complete 100% | float — EK000MD34F — Update/Issue Formal Inquiry for ERW - MD304 | 21-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000MD025 — Prepare job quality drawings for ERW | 25-Mar-25 → 28-May-25 | Complete 100% | float — EK000MD025 EK000MD51D — Technical Evaluation - MD501 | 26-Mar-25 → 03-Apr-25 | Complete 100% | float — EK000MD33F — Update/Issue Formal Inquiry for ERW - MD303 | 26-Mar-25 → 11-May-25 | Complete 100% | float — EK000MD33F EK000MF32F — Develop & Issue Design Data for Tank Subcontract - MF302 | 26-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MF33F — Develop & Issue Design Data for Tank Subcontract - MF311 | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000MD51F — Update/Issue Formal Inquiry for ERW - MD501 | 29-Mar-25 → 08-Apr-25 | Complete 100% | float — EK000MF31B — Develop & Issue Design Data for Tank Subcontrac - MF301 | 01-Apr-25 → 08-Apr-25 | Complete 100% | float — EK000MD31F — Update/Issue Formal Inquiry for ERW - MD301 | 02-Apr-25 → 16-Apr-25 | Complete 100% | float — EK000MD32F — Update/Issue Formal Inquiry for ERW - MD302 | 02-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MD43D — Technical Evaluation - MD403 | 02-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD43B — Develop & Issue Design Data for ERW - MD403 | 08-Apr-25 → 12-Apr-25 | Complete 100% | float — EK000MD45B — Develop & Issue Design Data for ERW - MD405 | 08-Apr-25 → 08-May-25 | Complete 100% | float — EK000MD42B — Develop & Issue Design Data for ERW - MD402 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MD41B — Develop & Issue Design Data for ERW - MD401 | 09-Apr-25 → 18-Apr-25 | Complete 100% | float — EK000MD43F — Update/Issue Formal Inquiry for ERW - MD403 | 15-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD32D — Technical Evaluation - MD302 | 15-Apr-25 → 04-May-25 | Complete 100% | float — EK000MD42F — Update/Issue Formal Inquiry for ERW - MD402 | 16-Apr-25 → 19-Apr-25 | Complete 100% | float — EK000MD31D — Technical Evaluation - MD301 | 16-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD33D — Technical Evaluation - MD303 | 16-Apr-25 → 04-May-25 | Complete 100% | float — EK000MD21F — Develop & Issue Inquiry ERW - MD201 | 17-Apr-25 → 17-Jun-25 | Complete 100% | float — EK000MD21F EK000MD41F — Update/Issue Formal Inquiry for ERW - MD401 | 20-Apr-25 → 26-Apr-25 | Complete 100% | float — EK000MD44B — Develop & Issue Design Data for ERW - MD404 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD47B — Develop & Issue Design Data for ERW - MD406 | 22-Apr-25 → 25-Apr-25 | Complete 100% | float — EK000MD22B — Develop & Issue Design Data for ERW - MD202 | 23-Apr-25 → 01-May-25 | Complete 100% | float — EK000MD44F — Update/Issue Formal Inquiry for ERW - MD404 | 27-Apr-25 → 01-May-25 | Complete 100% | float — EK000MD22F — Update/Issue Formal Inquiry for ERW - MD202 | 01-May-25 → 17-May-25 | Complete 100% | float — EK000MD31E — Prepare & Issue Purchase ERW - MD301 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD34E — Prepare & Issue Purchase ERW - MD304 | 04-May-25 → 11-May-25 | Complete 100% | float — EK000MD32E — Prepare & Issue Purchase ERW - MD302 | 06-May-25 → 10-May-25 | Complete 100% | float — EK000MD43E — Prepare & Issue Purchase ERW - MD403 | 06-May-25 → 11-May-25 | Complete 100% | float — EK000MD51E — Prepare & Issue Purchase ERW - MD501 | 09-May-25 → 11-May-25 | Complete 100% | float — EK000MD45F — Update/Issue Formal Inquiry for ERW - MD405 | 13-May-25 → 31-May-25 | Complete 100% | float — EK000MD46F — Update/Issue Formal Inquiry for ERW - MD411 | 14-May-25 → 31-May-25 | Complete 100% | float — EK000MD33E — Prepare & Issue Purchase ERW - MD303 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MD41E — Prepare & Issue Purchase ERW - MD401 | 01-Jul-25 → 04-Jul-25 | Complete 100% | float — EK000MD21D — Technical Evaluation - MD201 | 16-Jul-25 → 10-Aug-25 | Complete 100% | float — PK000MD31N — Recv. Planning V. Data MD301 | 09-Aug-25 → 09-Sep-25 | Complete 100% | float — PK000MD41N — Recv. Planning V. Data MD401 | 09-Aug-25 → 17-Sep-25 | Complete 100% | float — PK000MD41N PK000MD33N — Recv. Planning V. Data MD303 | 09-Aug-25 → 25-Sep-25 | Complete 100% | float — PK000MD33N PK000MD43N — Recv. Planning V. Data MD403 | 09-Aug-25 → 14-Oct-25 | Complete 100% | float — PK000MD43N PK000MD32N — Recv. Planning V. Data MD302 | 16-Aug-25 → 02-Oct-25 | Complete 100% | float — PK000MD32N PK000MD34N — Recv. Planning V. Data MD304 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PK000MD34N EK000MD21E — Prepare & Issue Purchase ERW - MD201 | 27-Aug-25 → 29-Aug-25 | Complete 100% | float — PK000MD51N — Recv. Planning V. Data MD501 | 27-Aug-25 → 01-Nov-25 | Complete 100% | float — PK000MD51N EK000MD055 — Pre-qualification trip to vendors shop (105-D) | 03-Sep-25 → 05-Sep-25 | Complete 100% | float — EK000MD103 — MD305 Merc. Removal Bed - Develop & Issue Design Data for ERW | 10-Oct-25 → 26-Nov-25 | Complete 100% | float — EK000MD103 EK000MD102 — MD305 Merc. Removal Bed - Prepare & Issue Req for Inquiry to Procur. | 26-Nov-25 → 05-Dec-25 | Complete 100% | float — EK000MD104 — MD305 Merc. Removal Bed - Technical Evaluation | 13-Jan-26 → 29-Jan-26 | Complete 100% | float — EK000MD105 — MD305 Merc. Removal Bed - Prepare & Issue Purchase ERW | 29-Jan-26 → 01-Feb-26 | Complete 100% | float —