Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 37 activities in MC Exchangers Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000MC010
Develop & Issue Exchanger Work Plan
05-Feb-25
09-Mar-25
100%
EK000MC31C
Prepare & Issue Prelim. RFQ - MC310 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MC61C
Prepare & Issue Prelim. RFQ - MC610 to Proc.
16-Feb-25
16-Feb-25
100%
EK000MC32C
Issue Prelim. RFQ - MC311
19-Feb-25
19-Feb-25
100%
EK020MC31A
MC312 - (120,121-C) - Issue Prelim. RFQ
19-Feb-25
19-Feb-25
100%
EK000MC210
Cooling Water Balance Review
19-Feb-25
26-Feb-25
100%
EK000MC21C
Prepare & Issue Prelim. RFQ - MC210 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC23C
Prepare & Issue Prelim. RFQ - MC230 to Proc.
26-Feb-25
27-Feb-25
100%
EK000MC31B
Develop & Issue Design Data for ERW - MC310
02-Mar-25
13-Mar-25
100%
EK000MC31F
Finalize Equip. Data Sheets for ERW - MC310
02-Mar-25
12-Apr-25
100%
EK000MC32B
Develop & Issue Design Data for ERW - MC311
05-Mar-25
19-Mar-25
100%
EK000MC32F
Finalize Equip. Data Sheets for ERW - MC311
05-Mar-25
24-May-25
100%
EK000MC21B
Develop & Issue Design Data for ERW - MC210
08-Mar-25
01-Apr-25
100%
EK000MC21F
Finalize Equip. Data Sheets for ERW - MC210
12-Mar-25
13-Jun-25
100%
EK000MC61D
Technical Evaluation - MC610
21-Mar-25
01-Apr-25
100%
EK000MC61F
Finalize Equip. Data Sheets for ERW - MC610
21-Mar-25
10-Apr-25
100%
EK000MC61B
Develop & Issue Design Data for ERW - MC610
04-Apr-25
20-Apr-25
100%
EK000MC21D
Technical Evaluation - MC210
08-Apr-25
23-Apr-25
100%
EK000MC23D
Technical Evaluation - MC230
08-Apr-25
23-Apr-25
100%
EK000MC23B
Develop & Issue Design Data for ERW - MC230
09-Apr-25
13-Apr-25
100%
EK000MC63B
Develop & Issue Design Data for ERW - MC630
15-Apr-25
20-Apr-25
100%
EK000MC31P
Develop & Issue Setting Plans for ERW - MC310
15-Apr-25
28-May-25
100%
EK000MC21P
Develop & Issue Setting Plans for ERW - MC210
15-Apr-25
20-Jun-25
100%
EK000MC23F
Finalize Equip. Data Sheets for ERW - MC230
23-Apr-25
13-Jun-25
100%
EK000MC23P
Develop & Issue Setting Plans for ERW - MC230
01-May-25
21-Jun-25
100%
EK000MC32P
Develop & Issue Setting Plans for ERW - MC311
02-May-25
20-Jun-25
100%
EK000MC31D
Technical Evaluation - MC310
07-May-25
24-May-25
100%
EK000MC32D
Technical Evaluation - MC311
07-May-25
24-May-25
100%
EK020MC31D
MC312 - (120,121-C) - Technical Evaluation
07-May-25
24-May-25
100%
PK000MC61N
Recv. Planning V. Data MC610
10-Sep-25
03-Dec-25
100%
EK000MC61E
Prepare & Issue Purchase ERW - MC610
18-Sep-25
25-Sep-25
100%
EK020MC31C
MC312 - (120,121-C) - Prepare & Issue Purchase ERW
23-Sep-25
27-Sep-25
100%
PK020MC31F
MC312 - (120,121-C) - Planning V. Data (Setting Plans)
23-Sep-25
08-Oct-25
100%
EK000MC23E
Prepare & Issue Purchase ERW - MC230
30-Sep-25
15-Oct-25
100%
EK000MC21E
Prepare & Issue Purchase ERW - MC210
30-Sep-25
07-Nov-25
100%
EK000MC32E
Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4)
10-Oct-25
15-Nov-25
100%
EK000MC31E
Prepare & Issue Purchase ERW - MC310
03-Jan-26
12-Feb-26
100%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Data Date
EK000MC010 — Develop & Issue Exchanger Work Plan | 05-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000MC31C — Prepare & Issue Prelim. RFQ - MC310 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MC61C — Prepare & Issue Prelim. RFQ - MC610 to Proc. | 16-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000MC32C — Issue Prelim. RFQ - MC311 | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK020MC31A — MC312 - (120,121-C) - Issue Prelim. RFQ | 19-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000MC210 — Cooling Water Balance Review | 19-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000MC21C — Prepare & Issue Prelim. RFQ - MC210 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC23C — Prepare & Issue Prelim. RFQ - MC230 to Proc. | 26-Feb-25 → 27-Feb-25 | Complete 100% | float — EK000MC31B — Develop & Issue Design Data for ERW - MC310 | 02-Mar-25 → 13-Mar-25 | Complete 100% | float — EK000MC31F — Finalize Equip. Data Sheets for ERW - MC310 | 02-Mar-25 → 12-Apr-25 | Complete 100% | float — EK000MC31F EK000MC32B — Develop & Issue Design Data for ERW - MC311 | 05-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000MC32F — Finalize Equip. Data Sheets for ERW - MC311 | 05-Mar-25 → 24-May-25 | Complete 100% | float — EK000MC32F EK000MC21B — Develop & Issue Design Data for ERW - MC210 | 08-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC21F — Finalize Equip. Data Sheets for ERW - MC210 | 12-Mar-25 → 13-Jun-25 | Complete 100% | float — EK000MC21F EK000MC61D — Technical Evaluation - MC610 | 21-Mar-25 → 01-Apr-25 | Complete 100% | float — EK000MC61F — Finalize Equip. Data Sheets for ERW - MC610 | 21-Mar-25 → 10-Apr-25 | Complete 100% | float — EK000MC61B — Develop & Issue Design Data for ERW - MC610 | 04-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MC21D — Technical Evaluation - MC210 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC23D — Technical Evaluation - MC230 | 08-Apr-25 → 23-Apr-25 | Complete 100% | float — EK000MC23B — Develop & Issue Design Data for ERW - MC230 | 09-Apr-25 → 13-Apr-25 | Complete 100% | float — EK000MC63B — Develop & Issue Design Data for ERW - MC630 | 15-Apr-25 → 20-Apr-25 | Complete 100% | float — EK000MC31P — Develop & Issue Setting Plans for ERW - MC310 | 15-Apr-25 → 28-May-25 | Complete 100% | float — EK000MC31P EK000MC21P — Develop & Issue Setting Plans for ERW - MC210 | 15-Apr-25 → 20-Jun-25 | Complete 100% | float — EK000MC21P EK000MC23F — Finalize Equip. Data Sheets for ERW - MC230 | 23-Apr-25 → 13-Jun-25 | Complete 100% | float — EK000MC23F EK000MC23P — Develop & Issue Setting Plans for ERW - MC230 | 01-May-25 → 21-Jun-25 | Complete 100% | float — EK000MC23P EK000MC32P — Develop & Issue Setting Plans for ERW - MC311 | 02-May-25 → 20-Jun-25 | Complete 100% | float — EK000MC32P EK000MC31D — Technical Evaluation - MC310 | 07-May-25 → 24-May-25 | Complete 100% | float — EK000MC32D — Technical Evaluation - MC311 | 07-May-25 → 24-May-25 | Complete 100% | float — EK020MC31D — MC312 - (120,121-C) - Technical Evaluation | 07-May-25 → 24-May-25 | Complete 100% | float — PK000MC61N — Recv. Planning V. Data MC610 | 10-Sep-25 → 03-Dec-25 | Complete 100% | float — PK000MC61N EK000MC61E — Prepare & Issue Purchase ERW - MC610 | 18-Sep-25 → 25-Sep-25 | Complete 100% | float — EK020MC31C — MC312 - (120,121-C) - Prepare & Issue Purchase ERW | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — PK020MC31F — MC312 - (120,121-C) - Planning V. Data (Setting Plans) | 23-Sep-25 → 08-Oct-25 | Complete 100% | float — EK000MC23E — Prepare & Issue Purchase ERW - MC230 | 30-Sep-25 → 15-Oct-25 | Complete 100% | float — EK000MC21E — Prepare & Issue Purchase ERW - MC210 | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000MC21E EK000MC32E — Prepare & Issue Purchase ERW - MC311 (103-C1/C2, 123-C1/CF1-4) | 10-Oct-25 → 15-Nov-25 | Complete 100% | float — EK000MC31E — Prepare & Issue Purchase ERW - MC310 | 03-Jan-26 → 12-Feb-26 | Complete 100% | float — EK000MC31E