Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 64 activities in IC Control Sytems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000IC030
Develop & Issue FieldBus Main Instr Vendor ERW
22-Jan-25
08-Mar-25
100%
EK000IC35A
DCS - Engr ERW Issued
04-Feb-25
12-Feb-25
100%
EK000IC015
Modify Package Equipment Spec for IEC basis
05-Feb-25
05-Mar-25
100%
EK000IC005
Develop Typical SIL Values Worksheet
19-Feb-25
02-Mar-25
100%
EK000IC020
Establlish data warehouse - Intools Basic Setup
26-Feb-25
09-Mar-25
100%
EK000IC025
Review Instr. & Installation Details - ID Change
26-Feb-25
09-Mar-25
100%
EK000IC045
Develop & Issue CSE Work Plan
26-Feb-25
08-May-25
100%
EK000IC35D
DCS - Tech Evaluation
14-Mar-25
14-May-25
100%
EK000I210D
000 Control Valves - Technical Evaluation
20-Mar-25
23-May-25
100%
EK000I131D
Technical Evaluation - Transmitters
26-Mar-25
23-May-25
100%
EK000IC36D
DCS (MIV) - Tech Evaluation
15-Apr-25
17-May-25
100%
EK000IC010
Make decision of FF vs. Traditional DCS system
01-May-25
17-May-25
100%
EK000I220A
Issue Preliminary ERW Pkg - MOV Valves
13-May-25
31-May-25
100%
EK000I354A
ITCC - Engr ERW Issued
13-May-25
23-Jul-25
100%
EK000I110D
Technical Evaluation - Orific Plates
28-May-25
10-Jun-25
100%
EK000I115D
Technical Evaluation - Annubars
28-May-25
10-Jun-25
100%
EK000I116D
Technical Evaluation - Wedge Flow Meters
28-May-25
10-Jun-25
100%
EK000I121D
Technical Evaluation - Vortex Meters
28-May-25
10-Jun-25
100%
EK000I122D
Technical Evaluation - Coriolis Meters
28-May-25
10-Jun-25
100%
EK000I124D
Technical Evaluation - Rotameters
28-May-25
10-Jun-25
100%
EK000I611D
Technical Evaluation - Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I612D
Technical Evaluation - Differential Pressure Gauges
28-May-25
10-Jun-25
100%
EK000I616D
Technical Evaluation - Steam Drum Lvl Gauges
28-May-25
10-Jun-25
100%
EK000I617D
Technical Evaluation - Magnetic Lvl Gauges
28-May-25
10-Jun-25
100%
EK000I127D
Magnetic Flow Meters - Technical Evaluation
28-May-25
26-Jun-25
100%
EK000I230A
Issue Preliminary ERW Pkg - On/Off Valves
05-Jun-25
15-Jun-25
100%
EK000I112D
Technical Evaluation - Venturis
10-Jun-25
14-Jun-25
100%
EK000I221D
000 Everest Control Valves - Technical Evaluation
25-Jun-25
10-Jul-25
100%
EK000I220D
Technical Evaluation - MOV's
16-Jul-25
23-Jul-25
100%
EK000I230D
Technical Evaluation - On/Off Valves
17-Jul-25
24-Jul-25
100%
EK000I618D
Technical Evaluation - Temperature Gauges
22-Jul-25
26-Jul-25
100%
EK000I621D
Technical Evaluation - Temperature Elements
22-Jul-25
26-Jul-25
100%
EK000I623D
Technical Evaluation - Multi-Point Thermocouples
22-Jul-25
26-Jul-25
100%
EK000I352A
SIS - Engr ERW Issued
22-Jul-25
02-Aug-25
100%
EK000I444A
Develop & Issue Inquiry ERW - Analyzer Shelter
06-Aug-25
17-Aug-25
100%
EK000I221A
000 Everest Control Valves - Issue Inquiry Req
12-Aug-25
16-Aug-25
100%
EK000IC350
DCS - Develop Design Basis
12-Aug-25
04-Oct-25
100%
EK000I444D
Technical Evaluation - Analyzer Shelter
16-Sep-25
11-Dec-25
100%
EK000I352D
SIS - Tech Evaluation
30-Sep-25
07-Nov-25
100%
EK000IC351
DCS - Develop Purchase T-Req
05-Oct-25
07-Nov-25
100%
EK000I354D
ITCC - Tech Evaluation
15-Oct-25
12-Dec-25
100%
PK000IC35J
DCS - Planning V. Data
17-Oct-25
27-Dec-26
43%
EK000IC352
DCS - Final Tech Evaluation for Purchase
13-Nov-25
15-Nov-25
100%
EK000IC353
DCS - Software Programming by KBR
15-Jan-26
27-Dec-26
29%
EK000I3540
ITCC - Develop Final Design Basis
28-Jan-26
04-Mar-26
100%
EK000I3520
SIS - Develop Final Design Basis
28-Jan-26
12-Mar-26
100%
EK00012210
000 Everest Control Valves - D/S,Sizing,Tech Eval
03-Feb-26
05-Mar-26
100%
EK000I444B
Develop Final Design Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000I444M
Develop Final Deign Basis - Shelters/ Analyzers
17-Feb-26
22-Mar-26
100%
EK000I444F
Planning V. Data - Shelters/ Analyzers
25-Feb-26
27-Dec-26
19%
PK000I352J
SIS - Planning V. Data
25-Feb-26
27-Dec-26
19%
PK000I354J
ITCC - Planning V. Data
25-Feb-26
27-Dec-26
19%
EK000I3541
ITCC - Develop Purchase T-Req
27-Feb-26
05-Mar-26
100%
EK000I221F
000 Everest Control Valves - Purchase ERW
11-Mar-26
27-Dec-26
15%
EK000I3521
SIS - Develop Purchase T-Req
31-Mar-26
03-Apr-26
100%
EK000I3542
ITCC - Final Tech Evaluation for Purchase
01-Apr-26
03-Apr-26
100%
EK000I444C
Develop / Issue T-Req - Shelters/ Analyzers
01-Apr-26
03-Apr-26
100%
EK000I3523
SIS - Software Programming by KBR
18-Apr-26
27-Dec-26
5%
EK000I3522
SIS - Final Tech Evaluation for Purchase
27-Dec-26
27-Dec-26
0%
EK000I352M
SIS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I354M
ITCC - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
EK000I444E
Final Tech Evaluation - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
EK000I444G
Review / Approve V. Data - Shelters/ Analyzers
27-Dec-26
27-Dec-26
0%
PK000IC35M
DCS - Review / Approve V. Data
27-Dec-26
27-Dec-26
0%
Jan 2025 Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK000IC030 — Develop & Issue FieldBus Main Instr Vendor ERW | 22-Jan-25 → 08-Mar-25 | Complete 100% | float — EK000IC030 EK000IC35A — DCS - Engr ERW Issued | 04-Feb-25 → 12-Feb-25 | Complete 100% | float — EK000IC35A EK000IC015 — Modify Package Equipment Spec for IEC basis | 05-Feb-25 → 05-Mar-25 | Complete 100% | float — EK000IC015 EK000IC005 — Develop Typical SIL Values Worksheet | 19-Feb-25 → 02-Mar-25 | Complete 100% | float — EK000IC005 EK000IC020 — Establlish data warehouse - Intools Basic Setup | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC020 EK000IC025 — Review Instr. & Installation Details - ID Change | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000IC025 EK000IC045 — Develop & Issue CSE Work Plan | 26-Feb-25 → 08-May-25 | Complete 100% | float — EK000IC045 EK000IC35D — DCS - Tech Evaluation | 14-Mar-25 → 14-May-25 | Complete 100% | float — EK000IC35D EK000I210D — 000 Control Valves - Technical Evaluation | 20-Mar-25 → 23-May-25 | Complete 100% | float — EK000I210D EK000I131D — Technical Evaluation - Transmitters | 26-Mar-25 → 23-May-25 | Complete 100% | float — EK000I131D EK000IC36D — DCS (MIV) - Tech Evaluation | 15-Apr-25 → 17-May-25 | Complete 100% | float — EK000IC36D EK000IC010 — Make decision of FF vs. Traditional DCS system | 01-May-25 → 17-May-25 | Complete 100% | float — EK000IC010 EK000I220A — Issue Preliminary ERW Pkg - MOV Valves | 13-May-25 → 31-May-25 | Complete 100% | float — EK000I220A EK000I354A — ITCC - Engr ERW Issued | 13-May-25 → 23-Jul-25 | Complete 100% | float — EK000I354A EK000I110D — Technical Evaluation - Orific Plates | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I110D EK000I115D — Technical Evaluation - Annubars | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I115D EK000I116D — Technical Evaluation - Wedge Flow Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I116D EK000I121D — Technical Evaluation - Vortex Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I121D EK000I122D — Technical Evaluation - Coriolis Meters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I122D EK000I124D — Technical Evaluation - Rotameters | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I124D EK000I611D — Technical Evaluation - Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I611D EK000I612D — Technical Evaluation - Differential Pressure Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I612D EK000I616D — Technical Evaluation - Steam Drum Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I616D EK000I617D — Technical Evaluation - Magnetic Lvl Gauges | 28-May-25 → 10-Jun-25 | Complete 100% | float — EK000I617D EK000I127D — Magnetic Flow Meters - Technical Evaluation | 28-May-25 → 26-Jun-25 | Complete 100% | float — EK000I127D EK000I230A — Issue Preliminary ERW Pkg - On/Off Valves | 05-Jun-25 → 15-Jun-25 | Complete 100% | float — EK000I230A EK000I112D — Technical Evaluation - Venturis | 10-Jun-25 → 14-Jun-25 | Complete 100% | float — EK000I112D EK000I221D — 000 Everest Control Valves - Technical Evaluation | 25-Jun-25 → 10-Jul-25 | Complete 100% | float — EK000I221D EK000I220D — Technical Evaluation - MOV's | 16-Jul-25 → 23-Jul-25 | Complete 100% | float — EK000I220D EK000I230D — Technical Evaluation - On/Off Valves | 17-Jul-25 → 24-Jul-25 | Complete 100% | float — EK000I230D EK000I618D — Technical Evaluation - Temperature Gauges | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I618D EK000I621D — Technical Evaluation - Temperature Elements | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I621D EK000I623D — Technical Evaluation - Multi-Point Thermocouples | 22-Jul-25 → 26-Jul-25 | Complete 100% | float — EK000I623D EK000I352A — SIS - Engr ERW Issued | 22-Jul-25 → 02-Aug-25 | Complete 100% | float — EK000I352A EK000I444A — Develop & Issue Inquiry ERW - Analyzer Shelter | 06-Aug-25 → 17-Aug-25 | Complete 100% | float — EK000I444A EK000I221A — 000 Everest Control Valves - Issue Inquiry Req | 12-Aug-25 → 16-Aug-25 | Complete 100% | float — EK000I221A EK000IC350 — DCS - Develop Design Basis | 12-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000IC350 EK000I444D — Technical Evaluation - Analyzer Shelter | 16-Sep-25 → 11-Dec-25 | Complete 100% | float — EK000I444D EK000I352D — SIS - Tech Evaluation | 30-Sep-25 → 07-Nov-25 | Complete 100% | float — EK000I352D EK000IC351 — DCS - Develop Purchase T-Req | 05-Oct-25 → 07-Nov-25 | Complete 100% | float — EK000IC351 EK000I354D — ITCC - Tech Evaluation | 15-Oct-25 → 12-Dec-25 | Complete 100% | float — EK000I354D PK000IC35J — DCS - Planning V. Data | 17-Oct-25 → 27-Dec-26 | In Progress 43% | float — PK000IC35J EK000IC352 — DCS - Final Tech Evaluation for Purchase | 13-Nov-25 → 15-Nov-25 | Complete 100% | float — EK000IC353 — DCS - Software Programming by KBR | 15-Jan-26 → 27-Dec-26 | In Progress 29% | float — EK000IC353 EK000I3540 — ITCC - Develop Final Design Basis | 28-Jan-26 → 04-Mar-26 | Complete 100% | float — EK000I3540 EK000I3520 — SIS - Develop Final Design Basis | 28-Jan-26 → 12-Mar-26 | Complete 100% | float — EK000I3520 EK00012210 — 000 Everest Control Valves - D/S,Sizing,Tech Eval | 03-Feb-26 → 05-Mar-26 | Complete 100% | float — EK00012210 EK000I444B — Develop Final Design Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444B EK000I444M — Develop Final Deign Basis - Shelters/ Analyzers | 17-Feb-26 → 22-Mar-26 | Complete 100% | float — EK000I444M EK000I444F — Planning V. Data - Shelters/ Analyzers | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000I444F PK000I352J — SIS - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I352J PK000I354J — ITCC - Planning V. Data | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — PK000I354J EK000I3541 — ITCC - Develop Purchase T-Req | 27-Feb-26 → 05-Mar-26 | Complete 100% | float — EK000I3541 EK000I221F — 000 Everest Control Valves - Purchase ERW | 11-Mar-26 → 27-Dec-26 | In Progress 15% | float — EK000I221F EK000I3521 — SIS - Develop Purchase T-Req | 31-Mar-26 → 03-Apr-26 | Complete 100% | float — EK000I3542 — ITCC - Final Tech Evaluation for Purchase | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK000I444C — Develop / Issue T-Req - Shelters/ Analyzers | 01-Apr-26 → 03-Apr-26 | Complete 100% | float — EK000I3523 — SIS - Software Programming by KBR | 18-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK000I3523 EK000I3522 — SIS - Final Tech Evaluation for Purchase | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I352M — SIS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I354M — ITCC - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444E — Final Tech Evaluation - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000I444G — Review / Approve V. Data - Shelters/ Analyzers | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000IC35M — DCS - Review / Approve V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —