EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in GEN General & Admin. × clear
Code
Activity
Start
Finish
Flt
%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
100%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
19%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
EK000CS030 — Start-up Schedule (Prelim for 1st Planner) | 05-Mar-25 → 14-Mar-25 | Complete 100% | float — EK000CS030 EK000CS025 — Turnover System Definition for ISBL | 15-Apr-25 → 31-Jan-26 | Complete 100% | float — EK000CS025 EK000CS027 — Turnover System Definition for OSBL | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000CS027