Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 3 activities in GEN General & Admin. × clear
Code
Activity
Start
Finish
Flt
%
EK000CS030
Start-up Schedule (Prelim for 1st Planner)
05-Mar-25
14-Mar-25
100%
EK000CS025
Turnover System Definition for ISBL
15-Apr-25
31-Jan-26
100%
EK000CS027
Turnover System Definition for OSBL
25-Feb-26
27-Dec-26
19%
Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK000CS030 — Start-up Schedule (Prelim for 1st Planner) | 05-Mar-25 → 14-Mar-25 | Complete 100% | float — EK000CS030 EK000CS025 — Turnover System Definition for ISBL | 15-Apr-25 → 31-Jan-26 | Complete 100% | float — EK000CS025 EK000CS027 — Turnover System Definition for OSBL | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EK000CS027