EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in EV Environmental Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000EV005
Conceptual Design of Wastewater Systems
19-Feb-25
23-Mar-25
100%
EK000EV025
Develop & Issue Enviromental Work Plan
26-Feb-25
09-Mar-25
100%
EK000EV020
Develop Preliminary noise model
12-Mar-25
20-Apr-25
100%
EK000EV010
Develop design basis for evaporation pond
22-Mar-25
11-May-25
100%
EK000EV015
Issue load sheets for wastewater systems
20-Apr-25
31-May-25
100%
27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May Data Date
EK000EV005 — Conceptual Design of Wastewater Systems | 19-Feb-25 → 23-Mar-25 | Complete 100% | float — EK000EV005 EK000EV025 — Develop & Issue Enviromental Work Plan | 26-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000EV025 EK000EV020 — Develop Preliminary noise model | 12-Mar-25 → 20-Apr-25 | Complete 100% | float — EK000EV020 EK000EV010 — Develop design basis for evaporation pond | 22-Mar-25 → 11-May-25 | Complete 100% | float — EK000EV010 EK000EV015 — Issue load sheets for wastewater systems | 20-Apr-25 → 31-May-25 | Complete 100% | float — EK000EV015