Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 27 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000ELZE0
Area Classification
11-Feb-25
30-Dec-25
100%
EK000EL005
Electrical Work Plans
12-Feb-25
09-Mar-25
100%
EK000EL020
Define bulk material requirements
19-Feb-25
23-Feb-25
100%
EK000EL015
Split of work with MEC and Other Discipline
26-Feb-25
28-Feb-25
100%
EK000EL025
Develop installation details
26-Feb-25
07-May-25
100%
EK000EL035
Voltage drop table
05-Mar-25
09-Mar-25
100%
EK020ELEG2
Cathodic Protection - Subcontract Consultant ERW Package
09-Oct-25
01-Mar-26
100%
EK000E001A
Sub Stations - Issue ERW
22-Nov-25
31-Dec-25
100%
EK000E002A
Transformer - Issue ERW
18-Dec-25
30-Dec-25
100%
EK000ELEJ1
Lighting, Installation Details
28-Dec-25
31-Dec-25
100%
EK000ELEK1
A/G Power & Control, Details
28-Dec-25
31-Dec-25
100%
EK010E008A
540-SB Admin. Area Pwr Supply - ERW Package
01-Feb-26
14-Feb-26
100%
EK000E004A
UPS System - Issue ERW
17-Feb-26
28-Mar-26
100%
EK000E001D
Sub Stations - Tech Evaluation
19-Feb-26
27-Dec-26
21%
EK000E002D
Transformer - Tech Evaluation
04-Mar-26
27-Dec-26
17%
EK010E008D
540-SB Admin. Area Pwr Supply - Tech Evaluation
03-Apr-26
27-Dec-26
8%
EK000E004D
UPS System - Tech Evaluation
27-Dec-26
27-Dec-26
0%
EK000ELEG0
Electrical Heat Tracing - ERW Package
27-Dec-26
27-Dec-26
0%
PK000E001J
Sub Stations - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E002J
Transformer - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK000E004J
UPS System - Planning V. Data
27-Dec-26
27-Dec-26
0%
PK010E008J
540-SG Admin. Area Pwr Supply - Planning V. Data
27-Dec-26
27-Dec-26
0%
EK000ELEGP
Electrical Heat Tracing - Design & BOM by Consultant
30-Dec-26
30-Jan-27
91.0d
0%
EK000ELEN1
01,03,04 LV Wiring Diagrams - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN2
01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC
30-Dec-26
03-Feb-27
509.0d
0%
EK000ELEN3
01,03, Equipment Interconnection Diagrams - IFC
30-Dec-26
30-Jan-27
511.0d
0%
PK000E001Z
Sub Stations - FAT
17-Feb-27
28-Feb-27
62.0d
0%
27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan 01-Feb 08-Feb 15-Feb 22-Feb Data Date
EK000ELZE0 — Area Classification | 11-Feb-25 → 30-Dec-25 | Complete 100% | float — EK000ELZE0 EK000EL005 — Electrical Work Plans | 12-Feb-25 → 09-Mar-25 | Complete 100% | float — EK000EL005 EK000EL020 — Define bulk material requirements | 19-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000EL020 EK000EL015 — Split of work with MEC and Other Discipline | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EK000EL015 EK000EL025 — Develop installation details | 26-Feb-25 → 07-May-25 | Complete 100% | float — EK000EL025 EK000EL035 — Voltage drop table | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000EL035 EK020ELEG2 — Cathodic Protection - Subcontract Consultant ERW Package | 09-Oct-25 → 01-Mar-26 | Complete 100% | float — EK020ELEG2 EK000E001A — Sub Stations - Issue ERW | 22-Nov-25 → 31-Dec-25 | Complete 100% | float — EK000E001A EK000E002A — Transformer - Issue ERW | 18-Dec-25 → 30-Dec-25 | Complete 100% | float — EK000E002A EK000ELEJ1 — Lighting, Installation Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ELEJ1 EK000ELEK1 — A/G Power & Control, Details | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK000ELEK1 EK010E008A — 540-SB Admin. Area Pwr Supply - ERW Package | 01-Feb-26 → 14-Feb-26 | Complete 100% | float — EK010E008A EK000E004A — UPS System - Issue ERW | 17-Feb-26 → 28-Mar-26 | Complete 100% | float — EK000E004A EK000E001D — Sub Stations - Tech Evaluation | 19-Feb-26 → 27-Dec-26 | In Progress 21% | float — EK000E001D EK000E002D — Transformer - Tech Evaluation | 04-Mar-26 → 27-Dec-26 | In Progress 17% | float — EK000E002D EK010E008D — 540-SB Admin. Area Pwr Supply - Tech Evaluation | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — EK010E008D EK000E004D — UPS System - Tech Evaluation | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000ELEG0 — Electrical Heat Tracing - ERW Package | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E001J — Sub Stations - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002J — Transformer - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004J — UPS System - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008J — 540-SG Admin. Area Pwr Supply - Planning V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK000ELEGP — Electrical Heat Tracing - Design & BOM by Consultant | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 91.0d EK000ELEGP EK000ELEN1 — 01,03,04 LV Wiring Diagrams - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN1 EK000ELEN2 — 01,03,04 LV//MV WIRING DIAGRAMS & CTL SCHEMATICS - IFC | 30-Dec-26 → 03-Feb-27 | Not Started 0% | float 509.0d EK000ELEN2 EK000ELEN3 — 01,03, Equipment Interconnection Diagrams - IFC | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EK000ELEN3 PK000E001Z — Sub Stations - FAT | 17-Feb-27 → 28-Feb-27 | Not Started 0% | float 62.0d PK000E001Z