EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 22 activities in CV Civil Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000CV005
Identify scope / Project set-up
23-Jan-25
23-Feb-25
100%
EK000CV020
Review FMCL documents - Specs & Drawings
29-Jan-25
16-Feb-25
100%
EK000CV025
Review SEGAS Wind & Earthquake Specs
05-Feb-25
19-Feb-25
100%
EK000CV010
HOC / MEC split of Work
07-Feb-25
16-Feb-25
100%
EK000CV030
Prepare EBIC Wind & EarthquakeSpecs
07-Feb-25
26-Feb-25
100%
EK000CV040
Prepare Topo Survey S/C Pkg
12-Feb-25
23-Feb-25
100%
EK000CV015
Civil work Plan & Safety check list
12-Feb-25
16-Mar-25
100%
EK000CV050
Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis
12-Feb-25
16-Mar-25
100%
EK000CV070
Validate Concrete & Steel by Planning Areas
19-Feb-25
15-Apr-25
100%
EK000CV060
Civil project highlights
26-Feb-25
16-Mar-25
100%
EK000CV035
Prepare Geotech S/C Pkgs
26-Feb-25
27-Apr-25
100%
EK000CV075
Egyptian Professional Engineer - Define Reqmnts
05-Mar-25
08-Mar-25
100%
EK000CV080
Egyptian Professional Eng. - Issue P.O/Subc. Pkg
08-Mar-25
09-Mar-25
100%
EK000CVK35
OSBL Rough Grading/Road
27-Mar-25
23-May-25
100%
EK000CV036
Issue Geotech S/C PKG
26-Apr-25
02-May-25
100%
EK000CV140
Issue Site Survey S/C PKG
26-Apr-25
14-May-25
100%
EK000CV145
Issue Site Leveling PKG
26-Apr-25
16-May-25
100%
EK000CV136
Issue Rough Grade (Ammonia) S/C PKG
01-May-25
27-May-25
100%
EK000CV065
Review Perimeter Wall Design - IFC (by OCI)
20-May-25
14-Jun-25
100%
EK000CV165
Issue ISBL Rough Grade Design Pkg.
09-Aug-25
04-Oct-25
100%
EK000CV137
Issue OSBL Rough Grade Design Pkg.
11-Sep-25
26-Nov-25
100%
EK000CV045
Prepare Foundation Design Criteria
16-Jan-26
14-Mar-26
100%
30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar 01-Apr 02-Apr 03-Apr 04-Apr 05-Apr 06-Apr 07-Apr 08-Apr 09-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr 01-May 02-May 03-May 04-May 05-May 06-May 07-May 08-May 09-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May 30-May 31-May 01-Jun 02-Jun 03-Jun 04-Jun 05-Jun 06-Jun 07-Jun 08-Jun 09-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 01-Jul 02-Jul 03-Jul 04-Jul 05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 01-Aug 02-Aug 03-Aug 04-Aug 05-Aug 06-Aug 07-Aug 08-Aug 09-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 01-Sep 02-Sep 03-Sep 04-Sep 05-Sep 06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep 01-Oct 02-Oct 03-Oct 04-Oct 05-Oct 06-Oct 07-Oct 08-Oct 09-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov 03-Nov 04-Nov 05-Nov 06-Nov 07-Nov 08-Nov 09-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 01-Dec 02-Dec 03-Dec 04-Dec 05-Dec 06-Dec 07-Dec 08-Dec 09-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec 29-Dec 30-Dec 31-Dec 01-Jan 02-Jan 03-Jan 04-Jan 05-Jan 06-Jan 07-Jan 08-Jan 09-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 01-Feb 02-Feb 03-Feb 04-Feb 05-Feb 06-Feb 07-Feb 08-Feb 09-Feb 10-Feb 11-Feb 12-Feb 13-Feb 14-Feb 15-Feb 16-Feb 17-Feb 18-Feb 19-Feb 20-Feb 21-Feb 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 01-Mar 02-Mar 03-Mar 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar 22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar Data Date
EK000CV005 — Identify scope / Project set-up | 23-Jan-25 → 23-Feb-25 | Complete 100% | float — EK000CV005 EK000CV020 — Review FMCL documents - Specs & Drawings | 29-Jan-25 → 16-Feb-25 | Complete 100% | float — EK000CV020 EK000CV025 — Review SEGAS Wind & Earthquake Specs | 05-Feb-25 → 19-Feb-25 | Complete 100% | float — EK000CV025 EK000CV010 — HOC / MEC split of Work | 07-Feb-25 → 16-Feb-25 | Complete 100% | float — EK000CV010 EK000CV030 — Prepare EBIC Wind & EarthquakeSpecs | 07-Feb-25 → 26-Feb-25 | Complete 100% | float — EK000CV030 EK000CV040 — Prepare Topo Survey S/C Pkg | 12-Feb-25 → 23-Feb-25 | Complete 100% | float — EK000CV040 EK000CV015 — Civil work Plan & Safety check list | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV015 EK000CV050 — Prepare EBIC Class 'C' & 'S' Spec - FMCL Basis | 12-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV050 EK000CV070 — Validate Concrete & Steel by Planning Areas | 19-Feb-25 → 15-Apr-25 | Complete 100% | float — EK000CV070 EK000CV060 — Civil project highlights | 26-Feb-25 → 16-Mar-25 | Complete 100% | float — EK000CV060 EK000CV035 — Prepare Geotech S/C Pkgs | 26-Feb-25 → 27-Apr-25 | Complete 100% | float — EK000CV035 EK000CV075 — Egyptian Professional Engineer - Define Reqmnts | 05-Mar-25 → 08-Mar-25 | Complete 100% | float — EK000CV075 EK000CV080 — Egyptian Professional Eng. - Issue P.O/Subc. Pkg | 08-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000CV080 EK000CVK35 — OSBL Rough Grading/Road | 27-Mar-25 → 23-May-25 | Complete 100% | float — EK000CVK35 EK000CV036 — Issue Geotech S/C PKG | 26-Apr-25 → 02-May-25 | Complete 100% | float — EK000CV036 EK000CV140 — Issue Site Survey S/C PKG | 26-Apr-25 → 14-May-25 | Complete 100% | float — EK000CV140 EK000CV145 — Issue Site Leveling PKG | 26-Apr-25 → 16-May-25 | Complete 100% | float — EK000CV145 EK000CV136 — Issue Rough Grade (Ammonia) S/C PKG | 01-May-25 → 27-May-25 | Complete 100% | float — EK000CV136 EK000CV065 — Review Perimeter Wall Design - IFC (by OCI) | 20-May-25 → 14-Jun-25 | Complete 100% | float — EK000CV065 EK000CV165 — Issue ISBL Rough Grade Design Pkg. | 09-Aug-25 → 04-Oct-25 | Complete 100% | float — EK000CV165 EK000CV137 — Issue OSBL Rough Grade Design Pkg. | 11-Sep-25 → 26-Nov-25 | Complete 100% | float — EK000CV137 EK000CV045 — Prepare Foundation Design Criteria | 16-Jan-26 → 14-Mar-26 | Complete 100% | float — EK000CV045