Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 18 activities in IC Control Sytems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK030I1100
030 Orific Plates - D/S Utility Plant
24-Sep-25
05-Nov-25
100%
EK030IC210
030 Control Valves - D/S, Sizing,Tech Eval
24-Sep-25
21-Dec-25
100%
EK030I1105
030 Orific Plates - Purchase ERW Utility Plant
31-Dec-25
11-Mar-26
100%
EK030IC213
030 Control Valves - Purchase ERW
01-Jan-26
27-Dec-26
31%
EK03AIC300
03A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03BIC300
03B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03DIC300
03D In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03EIC300
03E In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03FIC300
03F In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03YIC300
03Y In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK03CIC300
03C In Line Instrument Approved Vendor Data
01-Jan-26
15-Apr-26
100%
EK03CIC120
03C Instrument Detail Model / Review
22-Mar-26
18-Apr-26
100%
EK03AIC120
03A Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03BIC120
03B Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03DIC120
03D Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03EIC120
03E Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03FIC120
03F Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
EK03YIC120
03Y Instrument Detail Model / Review
27-Dec-26
27-Dec-26
0%
Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK030I1100 — 030 Orific Plates - D/S Utility Plant | 24-Sep-25 → 05-Nov-25 | Complete 100% | float — EK030I1100 EK030IC210 — 030 Control Valves - D/S, Sizing,Tech Eval | 24-Sep-25 → 21-Dec-25 | Complete 100% | float — EK030IC210 EK030I1105 — 030 Orific Plates - Purchase ERW Utility Plant | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK030I1105 EK030IC213 — 030 Control Valves - Purchase ERW | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK030IC213 EK03AIC300 — 03A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03AIC300 EK03BIC300 — 03B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03BIC300 EK03DIC300 — 03D In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03DIC300 EK03EIC300 — 03E In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03EIC300 EK03FIC300 — 03F In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03FIC300 EK03YIC300 — 03Y In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK03YIC300 EK03CIC300 — 03C In Line Instrument Approved Vendor Data | 01-Jan-26 → 15-Apr-26 | Complete 100% | float — EK03CIC300 EK03CIC120 — 03C Instrument Detail Model / Review | 22-Mar-26 → 18-Apr-26 | Complete 100% | float — EK03CIC120 EK03AIC120 — 03A Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BIC120 — 03B Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03DIC120 — 03D Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EIC120 — 03E Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FIC120 — 03F Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YIC120 — 03Y Instrument Detail Model / Review | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —