EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 17 activities in SY Systems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK030SY020
030 Utility Plant P&ID development IDR Issue
06-Apr-25
25-Apr-25
100%
EK030SY030
030 Utility Plant P&ID IDR Meeting milestone
02-May-25
03-May-25
100%
EK030SY040
030 Utility Plant P&IDs - ICA Issue development
04-May-25
20-Jun-25
100%
EK030SY050
030 Utility Plant P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
100%
EK030SY135
030 Utility Plant CV & FE Process Data
21-Jun-25
07-Sep-25
100%
EK030SY060
030 Utility Plant P&ID's - IPL Issue Development
25-Jun-25
19-Nov-25
100%
EK030SY150
030 Relief Valve Calculations - Utility Plant
10-Aug-25
26-Sep-25
100%
EK030SY185
030 SP Item Data Sheets - Utiliy Plant
27-Sep-25
24-Dec-25
100%
EK030SY155
030 Issue Requisition - PSA08 Relief Valves - Utility PLant
05-Oct-25
19-Nov-25
100%
EK030SY090
030 Utility Plant P&IDs IPL Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03ASY170
03A OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03BSY170
03B OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03CSY170
03C OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03DSY170
03D OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03ESY170
03E OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03FSY170
03F OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
EK03YSY170
03Y OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
100%
Q2 2025 Q3 2025 Q4 2025 Data Date
EK030SY020 — 030 Utility Plant P&ID development IDR Issue | 06-Apr-25 → 25-Apr-25 | Complete 100% | float — EK030SY030 — 030 Utility Plant P&ID IDR Meeting milestone | 02-May-25 → 03-May-25 | Complete 100% | float — EK030SY040 — 030 Utility Plant P&IDs - ICA Issue development | 04-May-25 → 20-Jun-25 | Complete 100% | float — EK030SY040 EK030SY050 — 030 Utility Plant P&IDs - ICA Issue Milestone | 20-Jun-25 | Complete EK030SY135 — 030 Utility Plant CV & FE Process Data | 21-Jun-25 → 07-Sep-25 | Complete 100% | float — EK030SY135 EK030SY060 — 030 Utility Plant P&ID's - IPL Issue Development | 25-Jun-25 → 19-Nov-25 | Complete 100% | float — EK030SY060 EK030SY150 — 030 Relief Valve Calculations - Utility Plant | 10-Aug-25 → 26-Sep-25 | Complete 100% | float — EK030SY150 EK030SY185 — 030 SP Item Data Sheets - Utiliy Plant | 27-Sep-25 → 24-Dec-25 | Complete 100% | float — EK030SY185 EK030SY155 — 030 Issue Requisition - PSA08 Relief Valves - Utility PLant | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK030SY155 EK030SY090 — 030 Utility Plant P&IDs IPL Issue Milestone | 19-Nov-25 | Complete EK03ASY170 — 03A OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03BSY170 — 03B OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03CSY170 — 03C OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03DSY170 — 03D OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03ESY170 — 03E OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03FSY170 — 03F OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete EK03YSY170 — 03Y OSBL P&IDs IPL & Line List Issue Milestone | 19-Nov-25 | Complete