EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 17
activities
in SY Systems Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK030SY020
030 Utility Plant P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK030SY030
030 Utility Plant P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
EK030SY040
030 Utility Plant P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK030SY050
030 Utility Plant P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
EK030SY135
030 Utility Plant CV & FE Process Data
21-Jun-25
07-Sep-25
—
100%
EK030SY060
030 Utility Plant P&ID's - IPL Issue Development
25-Jun-25
19-Nov-25
—
100%
EK030SY150
030 Relief Valve Calculations - Utility Plant
10-Aug-25
26-Sep-25
—
100%
EK030SY185
030 SP Item Data Sheets - Utiliy Plant
27-Sep-25
24-Dec-25
—
100%
EK030SY155
030 Issue Requisition - PSA08 Relief Valves - Utility PLant
05-Oct-25
19-Nov-25
—
100%
EK030SY090
030 Utility Plant P&IDs IPL Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03ASY170
03A OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03BSY170
03B OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03CSY170
03C OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03DSY170
03D OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03ESY170
03E OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03FSY170
03F OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%
EK03YSY170
03Y OSBL P&IDs IPL & Line List Issue Milestone
19-Nov-25
19-Nov-25
—
100%