Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 34 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK030PI005
Develop Plot Plan & ID Areas - Utility Plant IFI
02-Mar-25
09-Mar-25
100%
EK000PI140
Eqvlnt Line Counts / Planning Area-Utility Plant
05-Mar-25
09-Mar-25
100%
EK030PI010
Develop Plot Plan & ID Areas - Utility Plant ICA
23-Mar-25
11-Oct-25
100%
EK03FPI000
03F Preliminary Drawings for Supersketch U-2002
03-Jul-25
04-Jul-25
100%
EK03API000
03A Preliminary Drawings for Supersketch L-2003
13-Jul-25
13-Jul-25
100%
EK03API030
03A Conceptual Layout - Supersketches
15-Jul-25
22-Jul-25
100%
EK03DPI030
03D Conceptual Layout - Supersketches
01-Aug-25
07-Aug-25
100%
EK03UPIFWA
03U Plant Layout Model - Firewater
22-Aug-25
05-Oct-25
100%
EK030PI011
Plot Plan - Utility Plant Client ICA Approval
09-Sep-25
27-Sep-25
100%
EK03UPIOSA
03U Plant Layout Model - Outfall Sewer
17-Sep-25
26-Sep-25
100%
EK03UPIASA
03U Plant Layout Model - Acid Sewer
20-Sep-25
08-Oct-25
100%
EK03UPICSA
03U Plant Layout Model - Caustic Sewer
20-Sep-25
08-Oct-25
100%
EK03CPI030
03C Conceptual Layout - Supersketches
23-Sep-25
27-Sep-25
100%
EK03BPI030
03B Conceptual Layout - Supersketches
03-Oct-25
07-Oct-25
100%
EK03FPI030
03F Conceptual Layout - Supersketches (Need Dwgs)
07-Nov-25
01-Feb-26
100%
EK030PI012
Plot Plan - Utility Plant Issue IPL
28-Nov-25
20-Dec-25
100%
EK03EPI030
03E Conceptual Layout - Supersketches
17-Dec-25
31-Mar-26
100%
EK03DPI050
03D Model Comment Resolution Approval
18-Feb-26
06-Mar-26
100%
EK03CPI050
03C Model Comment Resolution Approval
05-Mar-26
07-Mar-26
100%
EK03API050
03A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03API143
03A OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03BPI050
03B Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03BPI143
03B OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03CPI143
03C OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03DPI145
03D OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03EPI050
03E Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03EPI144
03E OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03FPI050
03F Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03FPI144
03F OP's & Serv. Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03YPI050
03Y Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK03YPI144
03Y OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EK05API144
05A OP's & Serv. Model Comments Resolution Approval
27-Dec-26
27-Dec-26
0%
EM03YPI021
03Y Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EK035BI145
05B OP's & Serv. Model Comments Resolution Approval
11-Feb-27
13-Feb-27
75.0d
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Data Date
EK030PI005 — Develop Plot Plan & ID Areas - Utility Plant IFI | 02-Mar-25 → 09-Mar-25 | Complete 100% | float — EK000PI140 — Eqvlnt Line Counts / Planning Area-Utility Plant | 05-Mar-25 → 09-Mar-25 | Complete 100% | float — EK030PI010 — Develop Plot Plan & ID Areas - Utility Plant ICA | 23-Mar-25 → 11-Oct-25 | Complete 100% | float — EK030PI010 EK03FPI000 — 03F Preliminary Drawings for Supersketch U-2002 | 03-Jul-25 → 04-Jul-25 | Complete 100% | float — EK03API000 — 03A Preliminary Drawings for Supersketch L-2003 | 13-Jul-25 → 13-Jul-25 | Complete 100% | float — EK03API030 — 03A Conceptual Layout - Supersketches | 15-Jul-25 → 22-Jul-25 | Complete 100% | float — EK03DPI030 — 03D Conceptual Layout - Supersketches | 01-Aug-25 → 07-Aug-25 | Complete 100% | float — EK03UPIFWA — 03U Plant Layout Model - Firewater | 22-Aug-25 → 05-Oct-25 | Complete 100% | float — EK03UPIFWA EK030PI011 — Plot Plan - Utility Plant Client ICA Approval | 09-Sep-25 → 27-Sep-25 | Complete 100% | float — EK03UPIOSA — 03U Plant Layout Model - Outfall Sewer | 17-Sep-25 → 26-Sep-25 | Complete 100% | float — EK03UPIASA — 03U Plant Layout Model - Acid Sewer | 20-Sep-25 → 08-Oct-25 | Complete 100% | float — EK03UPICSA — 03U Plant Layout Model - Caustic Sewer | 20-Sep-25 → 08-Oct-25 | Complete 100% | float — EK03CPI030 — 03C Conceptual Layout - Supersketches | 23-Sep-25 → 27-Sep-25 | Complete 100% | float — EK03BPI030 — 03B Conceptual Layout - Supersketches | 03-Oct-25 → 07-Oct-25 | Complete 100% | float — EK03FPI030 — 03F Conceptual Layout - Supersketches (Need Dwgs) | 07-Nov-25 → 01-Feb-26 | Complete 100% | float — EK03FPI030 EK030PI012 — Plot Plan - Utility Plant Issue IPL | 28-Nov-25 → 20-Dec-25 | Complete 100% | float — EK03EPI030 — 03E Conceptual Layout - Supersketches | 17-Dec-25 → 31-Mar-26 | Complete 100% | float — EK03EPI030 EK03DPI050 — 03D Model Comment Resolution Approval | 18-Feb-26 → 06-Mar-26 | Complete 100% | float — EK03CPI050 — 03C Model Comment Resolution Approval | 05-Mar-26 → 07-Mar-26 | Complete 100% | float — EK03API050 — 03A Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03API143 — 03A OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BPI050 — 03B Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03BPI143 — 03B OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03CPI143 — 03C OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03DPI145 — 03D OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EPI050 — 03E Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03EPI144 — 03E OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FPI050 — 03F Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03FPI144 — 03F OP's & Serv. Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YPI050 — 03Y Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK03YPI144 — 03Y OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05API144 — 05A OP's & Serv. Model Comments Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI021 — 03Y Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK035BI145 — 05B OP's & Serv. Model Comments Resolution Approval | 11-Feb-27 → 13-Feb-27 | Not Started 0% | float 75.0d