EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 32
activities
in MJ Machinery Engineering
× clear
Code
Activity
Start
Finish
Flt
%
PK03EMU100
03E Recv. Planning V. Data - Utility Equip.
16-Sep-25
16-Sep-25
—
100%
PK03BMJ154
03B Recv. Planning V. Data - Pumps 2401-J, 2401-JA
17-Sep-25
17-Sep-25
—
100%
PK03CMJ154
03C Recv. Planning V. Data - Pumps 2205-J/JA, 2206-J/JA
17-Sep-25
17-Sep-25
—
100%
PK03DMJ154
03D Recv. Planning V. Data - Pumps 2202-J/JA
17-Sep-25
17-Sep-25
—
100%
PK03DMJV02
03D MJ305 2002-J/JA - Civil Prod. V. Data
27-Dec-25
27-Dec-26
—
32%
PK03DMJV01
03D MJ305 2002-J/JA - Piping Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
PK03DMJV03
03D MJ305 2002-J/JA - E&I Prod. V. Data
30-Dec-25
27-Dec-26
—
32%
PK03BMUV03
03B MU222,MJ305 2401-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03CMJV03
03C MJ305 2205-J/JA,2206-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV01
03E MU330 2001-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV02
03E MU330 2001-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03EMUV03
03E MU330 2001-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV03
03F MU222 2401-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV04
03F MU410 2002-U - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV05
03F MU410 2002-U - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03FMUV06
03F MU410 2002-U - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK03CMJV01
03C MJ305 2205-J/JA,2206-J/JA - Piping Prod. V. Data
31-Dec-25
03-Mar-26
—
100%
PK03FMUV01
03F MU222 2401-U - Piping Prod. V. Data
31-Dec-25
05-Mar-26
—
100%
PK03FMUV02
03F MU222 2401-U - Civil Prod. V. Data
31-Dec-25
05-Mar-26
—
100%
PK03BMUV01
03B MU222 2401-J/JA - Piping Prod. V. Data
31-Dec-25
08-Mar-26
—
100%
PK03BMUV02
03B MU222 2401-J/JA - Civil Prod. V. Data
31-Dec-25
08-Mar-26
—
100%
PK03CMJV02
03C MJ305 2205-J/JA,2206-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK03FMUV07
03F MU310 2001-L - Piping Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV08
03F MU310 2001-L - Civil Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03FMUV09
03F MU310 2001-L - E&I Prod. V. Data
15-Jan-26
27-Dec-26
—
29%
PK03AMLV01
03A ML500 2003-L - Piping Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV02
03A ML500 2003-L - Civil Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03AMLV03
03A ML500 2003-L - E&I Prod. V. Data
31-Jan-26
27-Dec-26
—
25%
PK03BMU100
03B Recv. Planning V. Data - Utility Equip. 2401-J/JA
15-Mar-26
31-Mar-26
—
100%
PK03BMUV04
03B MU292 2404-L - Piping Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV05
03B MU292 2404-L - Civil Prod. V. Data
19-Mar-26
27-Dec-26
—
13%
PK03BMUV06
03B MU292 2404-L - E&I Prod. V. Data
19-Mar-26
27-Dec-26
—
13%