EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK03FMD03
03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data
16-Aug-25
13-Sep-25
100%
PK03CMD06
03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03CMD07
03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03DMF01
03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK03DMF00
03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
18-Mar-26
100%
Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
PK03FMD03 — 03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data | 16-Aug-25 → 13-Sep-25 | Complete 100% | float — PK03CMD06 — 03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03CMD07 — 03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03DMF01 — 03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK03DMF01 PK03DMF00 — 03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract) | 28-Jan-26 → 18-Mar-26 | Complete 100% | float — PK03DMF00