EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK03FMD03
03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data
16-Aug-25
13-Sep-25
100%
PK03CMD06
03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03CMD07
03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK03DMF01
03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK03DMF00
03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
18-Mar-26
100%
Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
PK03FMD03 — 03F MD411 2006-F Boiler Blowdown Drum - Prod. V. Data | 16-Aug-25 → 13-Sep-25 | Complete 100% | float — PK03FMD03 PK03CMD06 — 03C MD411 2203-F 50% Caustic Storage Tank - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03CMD07 — 03C MD411 2204-F 98% Sulfuric Acid Drum - Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK03DMF01 — 03D MF302 2002-F Demineralized Water Tank - Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK03DMF01 PK03DMF00 — 03D MF302 2002-F Demineralized Water Tank - Fdn. V. Data (Subcontract) | 28-Jan-26 → 18-Mar-26 | Complete 100% | float — PK03DMF00