EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 22 activities in SY Systems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK010SY010
010 Issue Marked up FMCL U&O / Dock P&ID's
19-Feb-25
21-Feb-25
100%
EK000SY060
010 Util & Offsites Conceptual Design revw mtngs
12-Mar-25
19-Mar-25
100%
EK000SY075
010 OSBL Hydraulic Calculations
12-Mar-25
30-Jul-25
100%
EK010SY020
010 CW Twr & FW Tanks P&ID development IDR Issue
06-Apr-25
25-Apr-25
100%
EK010SY030
010 CW Twr & FW Tanks P&ID IDR Meeting milestone
02-May-25
03-May-25
100%
EK010SY040
010 CW Twr & FW Tanks P&IDs - ICA Issue development
04-May-25
20-Jun-25
100%
EK010SY050
010 Twr & FW Tanks P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
100%
EK010SY060
010 CW Twr & FW Tanks P&ID's - IPL Issue Development
25-Jun-25
31-Oct-25
100%
EK010SY135
010 CW Twr & FW Tanks CV & FE Process Data
30-Jul-25
17-Aug-25
100%
EK010SY150
010 Relief Valve Calculations - CW Twr & FW Tanks
14-Aug-25
26-Sep-25
100%
EK010SY185
010 SP Item Data Sheets - CW Twr & FW Tanks
25-Sep-25
24-Dec-25
100%
EK010SY155
010 Issue Requisition - PSA08 Relief Valves - CW Twr & FW Tanks
05-Oct-25
19-Nov-25
100%
EK010SY090
010 CW Twr & FW Tanks P&IDs IPL Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01ASY170
01A OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01BSY170
01B OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01CSY170
01C OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01DSY170
01D OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01ESY170
01E OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01FSY170
01F OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01HSY170
01H OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01JSY170
01J OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
EK01YSY170
01Y OSBL P&IDs IPL & Line List Issue Milestone
31-Oct-25
31-Oct-25
100%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Data Date
EK010SY010 — 010 Issue Marked up FMCL U&O / Dock P&ID's | 19-Feb-25 → 21-Feb-25 | Complete 100% | float — EK000SY060 — 010 Util & Offsites Conceptual Design revw mtngs | 12-Mar-25 → 19-Mar-25 | Complete 100% | float — EK000SY075 — 010 OSBL Hydraulic Calculations | 12-Mar-25 → 30-Jul-25 | Complete 100% | float — EK000SY075 EK010SY020 — 010 CW Twr & FW Tanks P&ID development IDR Issue | 06-Apr-25 → 25-Apr-25 | Complete 100% | float — EK010SY030 — 010 CW Twr & FW Tanks P&ID IDR Meeting milestone | 02-May-25 → 03-May-25 | Complete 100% | float — EK010SY040 — 010 CW Twr & FW Tanks P&IDs - ICA Issue development | 04-May-25 → 20-Jun-25 | Complete 100% | float — EK010SY040 EK010SY050 — 010 Twr & FW Tanks P&IDs - ICA Issue Milestone | 20-Jun-25 | Complete EK010SY060 — 010 CW Twr & FW Tanks P&ID's - IPL Issue Development | 25-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010SY060 EK010SY135 — 010 CW Twr & FW Tanks CV & FE Process Data | 30-Jul-25 → 17-Aug-25 | Complete 100% | float — EK010SY150 — 010 Relief Valve Calculations - CW Twr & FW Tanks | 14-Aug-25 → 26-Sep-25 | Complete 100% | float — EK010SY150 EK010SY185 — 010 SP Item Data Sheets - CW Twr & FW Tanks | 25-Sep-25 → 24-Dec-25 | Complete 100% | float — EK010SY185 EK010SY155 — 010 Issue Requisition - PSA08 Relief Valves - CW Twr & FW Tanks | 05-Oct-25 → 19-Nov-25 | Complete 100% | float — EK010SY155 EK010SY090 — 010 CW Twr & FW Tanks P&IDs IPL Issue Milestone | 31-Oct-25 | Complete EK01ASY170 — 01A OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01BSY170 — 01B OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01CSY170 — 01C OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01DSY170 — 01D OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01ESY170 — 01E OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01FSY170 — 01F OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01HSY170 — 01H OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01JSY170 — 01J OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete EK01YSY170 — 01Y OSBL P&IDs IPL & Line List Issue Milestone | 31-Oct-25 | Complete