Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 9 activities in SE Safety Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK010FP011
FP Firewater Pump P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK010FP050
FP Deluge P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
100%
EK010FP020
FP Firewater Pump P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK010FP060
FP Deluge P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
100%
EK020FP490
FP OSBL Fire Protection Eqmt. Location Plans - ICA
01-Aug-25
02-Sep-25
100%
EK000FP012
FP Electrical Area Classification OSBL - ICA
17-Sep-25
10-Oct-25
100%
EK010FP031
FP Firewater Pump P&IDs - Development & Issue IFD
01-Nov-25
27-Dec-26
41%
EK020FP460
FP Electrical Area Classification OSBL - IFC
31-Mar-26
27-Dec-26
9%
EK010FP040
FP Firewater Pump P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
0%
31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
EK010FP011 — FP Firewater Pump P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK010FP011 EK010FP050 — FP Deluge P&IDs - Development & Issue ICA | 06-Apr-25 → 18-Jun-25 | Complete 100% | float — EK010FP050 EK010FP020 — FP Firewater Pump P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010FP020 EK010FP060 — FP Deluge P&IDs - Development & Issue IPL | 19-Jun-25 → 31-Oct-25 | Complete 100% | float — EK010FP060 EK020FP490 — FP OSBL Fire Protection Eqmt. Location Plans - ICA | 01-Aug-25 → 02-Sep-25 | Complete 100% | float — EK020FP490 EK000FP012 — FP Electrical Area Classification OSBL - ICA | 17-Sep-25 → 10-Oct-25 | Complete 100% | float — EK000FP012 EK010FP031 — FP Firewater Pump P&IDs - Development & Issue IFD | 01-Nov-25 → 27-Dec-26 | In Progress 41% | float — EK010FP031 EK020FP460 — FP Electrical Area Classification OSBL - IFC | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — EK020FP460 EK010FP040 — FP Firewater Pump P&IDs - Development & Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —