EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 9
activities
in SE Safety Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK010FP011
FP Firewater Pump P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
—
100%
EK010FP050
FP Deluge P&IDs - Development & Issue ICA
06-Apr-25
18-Jun-25
—
100%
EK010FP020
FP Firewater Pump P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
—
100%
EK010FP060
FP Deluge P&IDs - Development & Issue IPL
19-Jun-25
31-Oct-25
—
100%
EK020FP490
FP OSBL Fire Protection Eqmt. Location Plans - ICA
01-Aug-25
02-Sep-25
—
100%
EK000FP012
FP Electrical Area Classification OSBL - ICA
17-Sep-25
10-Oct-25
—
100%
EK010FP031
FP Firewater Pump P&IDs - Development & Issue IFD
01-Nov-25
27-Dec-26
—
41%
EK020FP460
FP Electrical Area Classification OSBL - IFC
31-Mar-26
27-Dec-26
—
9%
EK010FP040
FP Firewater Pump P&IDs - Development & Issue IFC
27-Dec-26
27-Dec-26
—