EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 37 activities in MJ Machinery Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK01DMUV04
01D MU611 2101-U - Piping Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK01DMUV05
01D MU611 2101-U - Civil Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK01DMUV06
01D MU611 2101-U - E&I Prod. V. Data
03-Sep-25
03-Mar-26
100%
PK01BMJ154
01B Recv. Planning V. Data - Pumps (2001,4,7,2203,4)
27-Sep-25
27-Sep-25
100%
PK01HMJ135
01H Recv. Planning V.Data - Emerg Pwr Generator
01-Oct-25
01-Oct-25
100%
PK01FMU100
01F Recv. Planning V. Data - Utility Equip. 2603-K, 2607-K
01-Nov-25
15-Nov-25
100%
PK01DMJ154
01D Recv. Planning V. Data - Pumps 2210-J
26-Dec-25
26-Dec-25
100%
PK01BMJV03
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK01HMJV01
01H MJ730 2303-J - Civil Prod. V. Data
31-Dec-25
27-Dec-26
32%
PK01HMJV02
01H MJ730 2303-J - E&I Prod. V. Data
31-Dec-25
30-Dec-26
511.0d
31%
PK01EMUV01
01E MU221 Warehouse / Maintenance Area - Piping Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK01EMUV02
01E MU221 Warehouse / Maintenance Area - Civil Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK01EMUV03
01E MU221 Warehouse / Maintenance Area - E&I Prod. V. Data
31-Dec-25
31-Dec-25
100%
PK01BMJV02
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Civil Prod. V. Data
31-Dec-25
21-Mar-26
100%
PK01BMJV01
01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Piping Prod. V. Data
31-Dec-25
31-Mar-26
100%
PK01DMJV01
01D MJ303 2202-JA/JB/JC - Civil Prod. V. Data
03-Jan-26
07-Mar-26
100%
PK01DMJV02
01D MJ303 2202-JA/JB/JC - Piping Prod. V. Data
03-Jan-26
07-Mar-26
100%
PK01DMJV03
01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data
04-Jan-26
27-Dec-26
31%
PK01BMU100
01B Recv. Planning V. Data - 2007-L (No Req.)
10-Jan-26
10-Jan-26
100%
PK01DMUV01
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data
14-Jan-26
27-Dec-26
29%
PK01DMUV03
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data
14-Jan-26
27-Dec-26
29%
PK01DMUV02
01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L - Civil Prod. V. Data
14-Jan-26
31-Mar-26
100%
PK01CMUV01
01C MU300 2102-U - Piping Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK01CMUV02
01C MU300 2102-U - Civil Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK01CMUV03
01C MU300 2102-U - E&I Prod. V. Data
16-Jan-26
27-Dec-26
28%
PK01BMJV04
01B MJ391 2204-J/JA - Piping Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK01BMJV05
01B MJ391 2204-J/JA - Civil Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK01BMJV06
01B MJ391 2204-J/JA - E&I Prod. V. Data
18-Mar-26
27-Dec-26
13%
PK01DMUV07
01D MU322 2210-L,2211-L - Piping Prod. V. Data
31-Mar-26
27-Dec-26
9%
PK01DMUV09
01D MU322 2210-L,2211-L - E&I Prod. V. Data
31-Mar-26
27-Dec-26
9%
PK01DMUV08
01D MU322 2210-L,2211-L - Civil Prod. V. Data
31-Mar-26
01-Apr-26
100%
PK01AMLV01
01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK01AMLV02
01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK01AMLV03
01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data
02-Apr-26
27-Dec-26
8%
PK01AMJV01
01A MJ308 2408-JA/JB - Piping Prod. V. Data
23-Apr-26
27-Dec-26
5%
PK01AMJV02
01A MJ308 2408-JA/JB - Civil Prod. V. Data
23-Apr-26
27-Dec-26
5%
PK01AMJV03
01A MJ308 2408-JA/JB - E&I Prod. V. Data
23-Apr-26
27-Dec-26
5%
Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
PK01DMUV04 — 01D MU611 2101-U - Piping Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV04 PK01DMUV05 — 01D MU611 2101-U - Civil Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV05 PK01DMUV06 — 01D MU611 2101-U - E&I Prod. V. Data | 03-Sep-25 → 03-Mar-26 | Complete 100% | float — PK01DMUV06 PK01BMJ154 — 01B Recv. Planning V. Data - Pumps (2001,4,7,2203,4) | 27-Sep-25 → 27-Sep-25 | Complete 100% | float — PK01HMJ135 — 01H Recv. Planning V.Data - Emerg Pwr Generator | 01-Oct-25 → 01-Oct-25 | Complete 100% | float — PK01FMU100 — 01F Recv. Planning V. Data - Utility Equip. 2603-K, 2607-K | 01-Nov-25 → 15-Nov-25 | Complete 100% | float — PK01FMU100 PK01DMJ154 — 01D Recv. Planning V. Data - Pumps 2210-J | 26-Dec-25 → 26-Dec-25 | Complete 100% | float — PK01BMJV03 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - E&I Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK01BMJV03 PK01HMJV01 — 01H MJ730 2303-J - Civil Prod. V. Data | 31-Dec-25 → 27-Dec-26 | In Progress 32% | float — PK01HMJV01 PK01HMJV02 — 01H MJ730 2303-J - E&I Prod. V. Data | 31-Dec-25 → 30-Dec-26 | In Progress 31% | float 511.0d PK01HMJV02 PK01EMUV01 — 01E MU221 Warehouse / Maintenance Area - Piping Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK01EMUV02 — 01E MU221 Warehouse / Maintenance Area - Civil Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK01EMUV03 — 01E MU221 Warehouse / Maintenance Area - E&I Prod. V. Data | 31-Dec-25 → 31-Dec-25 | Complete 100% | float — PK01BMJV02 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Civil Prod. V. Data | 31-Dec-25 → 21-Mar-26 | Complete 100% | float — PK01BMJV02 PK01BMJV01 — 01B MJ305 2001-JA/JB/JC, 2004-J/JA,2007-J/JA,2007-J/JA - Piping Prod. V. Data | 31-Dec-25 → 31-Mar-26 | Complete 100% | float — PK01BMJV01 PK01DMJV01 — 01D MJ303 2202-JA/JB/JC - Civil Prod. V. Data | 03-Jan-26 → 07-Mar-26 | Complete 100% | float — PK01DMJV01 PK01DMJV02 — 01D MJ303 2202-JA/JB/JC - Piping Prod. V. Data | 03-Jan-26 → 07-Mar-26 | Complete 100% | float — PK01DMJV02 PK01DMJV03 — 01D MJ303 2202-JA/JB/JC - E&I Prod. V. Data | 04-Jan-26 → 27-Dec-26 | In Progress 31% | float — PK01DMJV03 PK01BMU100 — 01B Recv. Planning V. Data - 2007-L (No Req.) | 10-Jan-26 → 10-Jan-26 | Complete 100% | float — PK01DMUV01 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L-Piping Prod. V. Data | 14-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK01DMUV01 PK01DMUV03 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L,2212-L- E&I Prod. V. Data | 14-Jan-26 → 27-Dec-26 | In Progress 29% | float — PK01DMUV03 PK01DMUV02 — 01D MU310 2202-L,2203-L,2203-L,2205-L,2208-L - Civil Prod. V. Data | 14-Jan-26 → 31-Mar-26 | Complete 100% | float — PK01DMUV02 PK01CMUV01 — 01C MU300 2102-U - Piping Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV01 PK01CMUV02 — 01C MU300 2102-U - Civil Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV02 PK01CMUV03 — 01C MU300 2102-U - E&I Prod. V. Data | 16-Jan-26 → 27-Dec-26 | In Progress 28% | float — PK01CMUV03 PK01BMJV04 — 01B MJ391 2204-J/JA - Piping Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV04 PK01BMJV05 — 01B MJ391 2204-J/JA - Civil Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV05 PK01BMJV06 — 01B MJ391 2204-J/JA - E&I Prod. V. Data | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — PK01BMJV06 PK01DMUV07 — 01D MU322 2210-L,2211-L - Piping Prod. V. Data | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — PK01DMUV07 PK01DMUV09 — 01D MU322 2210-L,2211-L - E&I Prod. V. Data | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — PK01DMUV09 PK01DMUV08 — 01D MU322 2210-L,2211-L - Civil Prod. V. Data | 31-Mar-26 → 01-Apr-26 | Complete 100% | float — PK01AMLV01 — 01A ML900 2408-LA,LB,LC,LD - Piping Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV01 PK01AMLV02 — 01A ML900 2408-LA,LB,LC,LD - Civil Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV02 PK01AMLV03 — 01A ML900 2408-LA,LB,LC,LD - E&I Prod. V. Data | 02-Apr-26 → 27-Dec-26 | In Progress 8% | float — PK01AMLV03 PK01AMJV01 — 01A MJ308 2408-JA/JB - Piping Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV01 PK01AMJV02 — 01A MJ308 2408-JA/JB - Civil Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV02 PK01AMJV03 — 01A MJ308 2408-JA/JB - E&I Prod. V. Data | 23-Apr-26 → 27-Dec-26 | In Progress 5% | float — PK01AMJV03