Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK01BMF02
01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF03
01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF04
01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF05
01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract)
28-Jan-26
27-Dec-26
26%
PK01BMF01
01B MF302 2001-FA/FB Water Tank - Fdn. V. Data (Subcontract)
28-Jan-26
21-Feb-26
100%
Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
PK01BMF02 — 01B MF302 2001-FA/FB Water Tank - Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF02 PK01BMF03 — 01B MF302 2001-FA/FB Water Tank - Piping Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF03 PK01BMF04 — 01B MF302 2001-FA/FB Water Tank - Civil Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF04 PK01BMF05 — 01B MF302 2001-FA/FB Water Tank - E&I Prod. V. Data (Subcontract) | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — PK01BMF05 PK01BMF01 — 01B MF302 2001-FA/FB Water Tank - Fdn. V. Data (Subcontract) | 28-Jan-26 → 21-Feb-26 | Complete 100% | float — PK01BMF01