Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK000EL000
OSBL Motors & Drivers - Prod. V. Data (Information Only)
30-Dec-25
30-Dec-26
32%
PK000E001M
Sub Stations - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E002M
Transformer - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E004M
UPS System - Production V. Data
27-Dec-26
27-Dec-26
0%
PK010E008L
540-SG Admin. Area Pwr Supply - Production V. Data
27-Dec-26
27-Dec-26
0%
01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
PK000EL000 — OSBL Motors & Drivers - Prod. V. Data (Information Only) | 30-Dec-25 → 30-Dec-26 | In Progress 32% | float — PK000EL000 PK000E001M — Sub Stations - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002M — Transformer - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004M — UPS System - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008L — 540-SG Admin. Area Pwr Supply - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —