EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 5 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
PK000EL000
OSBL Motors & Drivers - Prod. V. Data (Information Only)
30-Dec-25
30-Dec-26
32%
PK000E001M
Sub Stations - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E002M
Transformer - Production V. Data
27-Dec-26
27-Dec-26
0%
PK000E004M
UPS System - Production V. Data
27-Dec-26
27-Dec-26
0%
PK010E008L
540-SG Admin. Area Pwr Supply - Production V. Data
27-Dec-26
27-Dec-26
0%
Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
PK000EL000 — OSBL Motors & Drivers - Prod. V. Data (Information Only) | 30-Dec-25 → 30-Dec-26 | In Progress 32% | float — PK000EL000 PK000E001M — Sub Stations - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E002M — Transformer - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK000E004M — UPS System - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — PK010E008L — 540-SG Admin. Area Pwr Supply - Production V. Data | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —