Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in IC Control Sytems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK050I1100
050 Orific Plates - D/S Dock/Storage Area
04-Oct-25
05-Nov-25
100%
EK050I1105
050 Orific Plates - Purchase ERW Dock/Storage Area
31-Dec-25
11-Mar-26
100%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
5%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
EK050I1100 — 050 Orific Plates - D/S Dock/Storage Area | 04-Oct-25 → 05-Nov-25 | Complete 100% | float — EK050I1100 EK050I1105 — 050 Orific Plates - Purchase ERW Dock/Storage Area | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK050I1105 EK05AIC300 — 05A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05AIC300 EK05BIC300 — 05B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05BIC300 EK05AIC120 — 05A Instrument Detail Model / Review | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK05AIC120 EK05BIC120 — 05B Instrument Model | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 110.0d