EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 6 activities in IC Control Sytems Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK050I1100
050 Orific Plates - D/S Dock/Storage Area
04-Oct-25
05-Nov-25
100%
EK050I1105
050 Orific Plates - Purchase ERW Dock/Storage Area
31-Dec-25
11-Mar-26
100%
EK05AIC300
05A In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05BIC300
05B In Line Instrument Approved Vendor Data
01-Jan-26
27-Dec-26
31%
EK05AIC120
05A Instrument Detail Model / Review
22-Apr-26
27-Dec-26
5%
EK05BIC120
05B Instrument Model
30-Dec-26
30-Dec-26
110.0d
0%
Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Data Date
EK050I1100 — 050 Orific Plates - D/S Dock/Storage Area | 04-Oct-25 → 05-Nov-25 | Complete 100% | float — EK050I1100 EK050I1105 — 050 Orific Plates - Purchase ERW Dock/Storage Area | 31-Dec-25 → 11-Mar-26 | Complete 100% | float — EK050I1105 EK05AIC300 — 05A In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05AIC300 EK05BIC300 — 05B In Line Instrument Approved Vendor Data | 01-Jan-26 → 27-Dec-26 | In Progress 31% | float — EK05BIC300 EK05AIC120 — 05A Instrument Detail Model / Review | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EK05AIC120 EK05BIC120 — 05B Instrument Model | 30-Dec-26 → 30-Dec-26 | Not Started 0% | float 110.0d