Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 9 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
100%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%
27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan Data Date
EK05BEL150 — Switchgear One line diagrams - ICA Dock | 12-Feb-25 → 15-Nov-25 | Complete 100% | float — EK05BEL150 EK05BEL170 — MCC One line diagrams - ICA Dock | 12-Feb-25 → 22-Nov-25 | Complete 100% | float — EK05BEL170 EK05BEL175 — Client Review of MCC Oneline Diagrams | 11-Nov-25 → 22-Nov-25 | Complete 100% | float — EK05BEL175 EK05BEL155 — Client Review of Switchgear Oneline Diagrams | 14-Nov-25 → 22-Nov-25 | Complete 100% | float — EK05BEL155 EK05BELED0 — Substation Building Layout | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK05BELED0 EK05BEL160 — Switchgear One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL160 EK05BEL180 — MCC One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL180 EK05BEL165 — Switchgear One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 276.0d EK05BEL165 EK05BEL185 — MCC One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 286.0d EK05BEL185