EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 9 activities in EL Electrical Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
100%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
7%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Data Date
EK05BEL150 — Switchgear One line diagrams - ICA Dock | 12-Feb-25 → 15-Nov-25 | Complete 100% | float — EK05BEL150 EK05BEL170 — MCC One line diagrams - ICA Dock | 12-Feb-25 → 22-Nov-25 | Complete 100% | float — EK05BEL170 EK05BEL175 — Client Review of MCC Oneline Diagrams | 11-Nov-25 → 22-Nov-25 | Complete 100% | float — EK05BEL155 — Client Review of Switchgear Oneline Diagrams | 14-Nov-25 → 22-Nov-25 | Complete 100% | float — EK05BELED0 — Substation Building Layout | 28-Dec-25 → 31-Dec-25 | Complete 100% | float — EK05BEL160 — Switchgear One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL160 EK05BEL180 — MCC One line Diagrams - IFD | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EK05BEL180 EK05BEL165 — Switchgear One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 276.0d EK05BEL185 — MCC One line Diagrams - IFC | 27-Jan-27 → 30-Jan-27 | Not Started 0% | float 286.0d