EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 9
activities
in EL Electrical Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK05BEL150
Switchgear One line diagrams - ICA Dock
12-Feb-25
15-Nov-25
—
100%
EK05BEL170
MCC One line diagrams - ICA Dock
12-Feb-25
22-Nov-25
—
100%
EK05BEL175
Client Review of MCC Oneline Diagrams
11-Nov-25
22-Nov-25
—
100%
EK05BEL155
Client Review of Switchgear Oneline Diagrams
14-Nov-25
22-Nov-25
—
100%
EK05BELED0
Substation Building Layout
28-Dec-25
31-Dec-25
—
100%
EK05BEL160
Switchgear One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL180
MCC One line Diagrams - IFD
04-Apr-26
27-Dec-26
—
7%
EK05BEL165
Switchgear One line Diagrams - IFC
27-Jan-27
30-Jan-27
276.0d
0%
EK05BEL185
MCC One line Diagrams - IFC
27-Jan-27
30-Jan-27
286.0d
0%