Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 2 activities in CV Civil Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000CV146
Receive Site Survey Data Areas 04 & 05
27-Dec-26
27-Dec-26
0%
EK05ACV200
05A Redesign Piling & Ammonia Tank Foundations
30-Dec-26
10-Jan-27
-44.0d
0%
Dec 2026 Jan 2027 Data Date
EK000CV146 — Receive Site Survey Data Areas 04 & 05 | 27-Dec-26 | Not Started EK05ACV200 — 05A Redesign Piling & Ammonia Tank Foundations | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float -44.0d EK05ACV200