Projects
EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 448 activities in E Engineering (MEC) × clear
Code
Activity
Start
Finish
Flt
%
EM000MD42C
Prepare & Issue Prelim. RFQ - MD402 to Proc.
12-Feb-25
16-Feb-25
100%
EM000PI025
Develop Piping Specs (PDS)
19-Feb-25
23-Jul-25
100%
EM000MD22C
Prepare & Issue Prelim. RFQ - MD202 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD44C
Prepare & Issue Prelim. RFQ - MD404 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD46C
Prepare & Issue Prelim. RFQ - MD411 to Proc.
26-Feb-25
28-Feb-25
100%
EM00MD45C
Prepare & Issue Prelim. RFQ - MD405 to Proc.
26-Feb-25
28-Feb-25
100%
EM000MD22D
Technical Evaluation - MD202
22-Mar-25
18-Apr-25
100%
EM000MD42D
Technical Evaluation - MD402
22-Mar-25
18-Apr-25
100%
EM000MD44D
Technical Evaluation - MD404
22-Mar-25
18-Apr-25
100%
EM000MD46D
Technical Evaluation - MD411
22-Mar-25
19-Apr-25
100%
EM000MD45D
Technical Evaluation - MD405
26-Mar-25
18-Apr-25
100%
EM000MD47F
Develop & Issue Inquiry for ERW - MD406
27-Apr-25
11-May-25
100%
EM000MD42E
Prepare & Issue Purchase ERW - MD402
01-May-25
04-May-25
100%
EM000MD44E
Prepare & Issue Purchase ERW - MD404
03-Jun-25
05-Jun-25
100%
EM000MD45E
Prepare & Issue Purchase ERW - MD405
03-Jun-25
05-Jun-25
100%
EM000MD46E
Prepare & Issue Purchase ERW - MD411
03-Jun-25
05-Jun-25
100%
EM000MD22E
Prepare & Issue Purchase ERW - MD202
10-Jun-25
13-Jun-25
100%
EM03EPI120
03E Plant Layout Model
14-Jun-25
27-Dec-26
56%
EM01YPI120
01Y Plant Layout Model
14-Jun-25
18-Dec-25
100%
EM03EEL120
03E Electrical Conceptual Layouts
01-Jul-25
01-Mar-26
100%
EM000MD47D
Technical Evaluation - MD406
02-Jul-25
06-Jul-25
100%
EM03API120
03A Plant Layout Model
22-Jul-25
27-Dec-26
53%
EM03YPI120
03Y Plant Layout Model
22-Jul-25
27-Dec-26
53%
EM03AEL120
03A Electrical Conceptual Layouts
23-Jul-25
27-Sep-25
100%
EM03DPI120
03D Plant Layout Model
08-Aug-25
15-Feb-26
100%
EM03DEL120
03D Electrical Conceptual Layouts
09-Aug-25
19-Oct-25
100%
EM03BEL120
03B Electrical Conceptual Layouts
12-Aug-25
19-Oct-25
100%
EM03API123
03A Plant Layout Nozzle Release
15-Aug-25
27-Sep-25
100%
EM000MD47E
Prepare & Issue Purchase ERW - MD406
16-Aug-25
21-Aug-25
100%
PM000MD45N
Recv. Planning V. Data MD405
16-Aug-25
02-Sep-25
100%
PM000MD42N
Recv. Planning V. Data MD402
16-Aug-25
19-Oct-25
100%
PM000MD22N
Recv. Planning V. Data MD202
16-Aug-25
12-Nov-25
100%
EM03YEL120
03Y Electrical Conceptual Layouts
19-Aug-25
11-Oct-25
100%
EM03FEL120
03F Electrical Conceptual Layouts
19-Aug-25
23-Oct-25
100%
EM01BPI120
01B Plant Layout Model
21-Aug-25
01-Feb-26
100%
EM01CPI120
01C Plant Layout Model
24-Aug-25
27-Dec-26
50%
PM000MD46N
Recv. Planning V. Data MD411
27-Aug-25
13-Sep-25
100%
EM01YEL120
01Y Electrical Conceptual Layouts
28-Aug-25
03-Oct-25
100%
EM01CEL120
01C Electrical Conceptual Layouts
02-Sep-25
17-Feb-26
100%
EM01DCV110
01D Design & Model Cooling Tower Basin
03-Sep-25
20-Nov-25
100%
EM01DPI120
01D Plant Layout Model
03-Sep-25
29-Jan-26
100%
EM01DCV120
01D Design & Model Structural Steel Sleepers
03-Sep-25
01-Feb-26
100%
EM01DCV160
01D Design & Model Major Eq. Fdns
03-Sep-25
01-Feb-26
100%
PM000MD44N
Recv. Planning V. Data MD404
17-Sep-25
30-Sep-25
100%
EM03DPI123
03D Plant Layout Nozzle Release
18-Sep-25
27-Sep-25
100%
EM01BEL120
01B Electrical Conceptual Layouts
21-Sep-25
03-Oct-25
100%
EM01DEL120
01D Electrical Conceptual Layouts
21-Sep-25
03-Oct-25
100%
EM01GCV160
01G Design & Model Control Building Fdns
21-Sep-25
10-Dec-25
100%
PM000MD47N
Recv. Planning V. Data MD406
23-Sep-25
09-Oct-25
100%
EM03DCV160
03D Design & Model Major Eq. Fdns
24-Sep-25
13-Nov-25
100%
EM01DCV130
01D Design & Model S/S Sleeper Fdns
25-Sep-25
01-Feb-26
100%
EM01EEL120
01E Electrical Conceptual Layouts
27-Sep-25
12-Nov-25
100%
EM01AEL120
01A Electrical Conceptual Layouts
01-Oct-25
08-Oct-25
100%
EM05UPI175
05U Plant Layout Model - Common
01-Oct-25
11-Oct-25
100%
EM000CV164
Issue Anchor Bolts,Rebar, & Misc. Fnd Matl. Take-Off's to OCI
01-Oct-25
29-Oct-25
100%
EM03CEL120
03C Electrical Conceptual Layouts
01-Oct-25
06-Nov-25
100%
EM03CPI120
03C Plant Layout Model
01-Oct-25
17-Dec-25
100%
EM01JPI120
01J Plant Layout Model
01-Oct-25
17-Apr-26
100%
EM01UPIBSB
01U IDP - Plant Layout - Benfield Sewer
01-Oct-25
11-Oct-25
100%
EM01UPICWB
01U IDP - Plant Layout - Cooling Water
01-Oct-25
11-Oct-25
100%
EM01UPIFWB
01U IDP - Plant Layout - Firewater
01-Oct-25
11-Oct-25
100%
EM01UPIPAB
01U IDP - Plant Layout - Plant Air
01-Oct-25
11-Oct-25
100%
EM01UPIPWB
01U IDP - Plant Layout - Potable Water
01-Oct-25
11-Oct-25
100%
EM01UPISSB
01U IDP - Plant Layout - Sanitary Sewer
01-Oct-25
11-Oct-25
100%
EM01UPIWWB
01U IDP - Plant Layout - Waste Water
01-Oct-25
11-Oct-25
100%
EM03UPIASB
03U IDP - Plant Layout - Acid Sewer
01-Oct-25
11-Oct-25
100%
EM03UPICSB
03U IDP - Plant Layout - Caustic Sewer
01-Oct-25
11-Oct-25
100%
EM03UPIFWB
03U IDP - Plant Layout - Firewater
01-Oct-25
11-Oct-25
100%
EM03UPIOSB
03U IDP - Plant Layout - Outfall Sewer
01-Oct-25
11-Oct-25
100%
EM01HEL120
01H Electrical Conceptual Layouts
01-Oct-25
09-Nov-25
100%
EM020IC126
Instrument Installation Details (90%) - IFC
07-Oct-25
18-Apr-26
100%
EM01BCV130
01B Design & Model S/S Sleeper Fdns
09-Oct-25
14-Feb-26
100%
EM01BCV120
01B Design & Model Structural Steel Sleepers
09-Oct-25
15-Feb-26
100%
EM01BCV160
01B Design & Model Major Eq. Fdns
09-Oct-25
15-Feb-26
100%
EM01UPI186
01U Planning Release - Common, SS, FW, CW, WW, AP, WP
11-Oct-25
01-Feb-26
100%
EM01API120
01A Plant Layout Model
15-Oct-25
18-Feb-26
100%
EM000U000
Start U/G Model Reviews
16-Oct-25
16-Oct-25
100%
EM01BPI123
01B Plant Layout Nozzle Release
19-Oct-25
25-Oct-25
100%
EM01JEL120
01J Electrical Conceptual Layouts
22-Oct-25
12-Nov-25
100%
EM01UPIBSC
01U Model Review Mtg (HOC/MEC) - Benfield Sewer
23-Oct-25
23-Oct-25
100%
EM01UPIPAC
01U Model Review Mtg -Plant Air
28-Oct-25
31-Oct-25
100%
EM01UPIPWC
01U Model Review Mtg -Potable Water
28-Oct-25
31-Oct-25
100%
EM01UPIWWC
01U Model Review Mtg - Waste Water
28-Oct-25
31-Oct-25
100%
EM03UPIASC
03U Model Review Mtg (HOC/MEC) - Acid Sewer
28-Oct-25
02-Nov-25
100%
EM03UPICSC
03U Model Review Mtg (HOC/MEC) - Caustic Sewer
28-Oct-25
02-Nov-25
100%
EM03UPIFWC
03U Model Review Mtg (HOC/MEC) - Firewater
28-Oct-25
02-Nov-25
100%
EM03UPIOSC
03U Model Review Mtg (HOC/MEC) - Outfall Sewer
28-Oct-25
02-Nov-25
100%
EM01UPICWC
01U Model Review Mtg - Cooling Water
29-Oct-25
01-Nov-25
100%
EM01UPIFWC
01U Model Review Mtg - Firewater
29-Oct-25
01-Nov-25
100%
EM01UPISSC
01U Model Review Mtg - Sanitary Sewer
29-Oct-25
01-Nov-25
100%
EM01API123
01A Plant Layout Nozzle Release
05-Nov-25
20-Nov-25
100%
EM03CPI123
03C Plant Layout Nozzle Release
19-Nov-25
23-Nov-25
100%
EM03UPIASD
03U Planning Release - Acid Sewer
19-Nov-25
23-Dec-25
100%
EM03UPICSD
03U Planning Release - Caustic Sewer
19-Nov-25
23-Dec-25
100%
EM03UPIFWD
03U Planning Release - Firewater
19-Nov-25
23-Dec-25
100%
EM03UPIOSD
03U Planning Release - Outfall Sewer
19-Nov-25
23-Dec-25
100%
EM03YCV130
03Y Design & Model Structural Piperack Fdns
19-Nov-25
24-Dec-25
100%
EM03CCV160
03C Design & Model Major Eq. Fdns
19-Nov-25
17-Jan-26
100%
EM03CCV110
03C Design & Model Containment Area
19-Nov-25
25-Feb-26
100%
EM05API120
05A Plant Layout Model
19-Nov-25
25-Feb-26
100%
EM05ACV120
05A Design & Model PR Structural Steel
22-Nov-25
26-Feb-26
100%
EM05ACV130
05A Design & Model Structural Piperack Fdns
03-Dec-25
24-Feb-26
100%
EM01YCV130
01Y Design & Model Structural Piperack Fdns
04-Dec-25
15-Feb-26
100%
EM01YCV120
01Y Design & Model Structural Steel Piperack
06-Dec-25
15-Feb-26
100%
EM05AEL120
05A Electrical Conceptual Layouts
17-Dec-25
19-Feb-26
100%
EM03BCV110
03B Design & Model Sumps
30-Dec-25
27-Dec-26
32%
EM05ACV160
05A Design & Model Major Eq. Fdns
03-Jan-26
27-Dec-26
31%
EM03FCV160
03F Design & Model Major Eq. Fdns
07-Jan-26
27-Dec-26
30%
EM000MCG10
GEN and ADMINISTRATIVE
13-Jan-26
27-Dec-26
29%
EM03DPI130
03D Model Review Mtg
16-Jan-26
16-Jan-26
100%
EM01YPI130
01Y Model Review Mtg
20-Jan-26
21-Jan-26
100%
EM01YPI140
01Y Model Review Comment Resolution
21-Jan-26
27-Jan-26
100%
EM01BPI130
01B Model Review Mtg
23-Jan-26
24-Jan-26
100%
EM05UPI141
05U Model Review Mtg
27-Jan-26
28-Jan-26
100%
EM01BPI121
01B Model Review Comment Resolution
27-Jan-26
31-Jan-26
100%
EM01API200
01A Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM01CPI200
01C Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM03API200
03A Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM03BPI200
03B Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM03EPI200
03E Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM05API200
05A Equipment Location Plans
28-Jan-26
27-Dec-26
26%
EM01YPI133
01Y IDP - Plant Layout
28-Jan-26
29-Jan-26
100%
EM03CPI130
03C Model Review Mtg
28-Jan-26
29-Jan-26
100%
EM03UPIFWE
03U Detail Model Development - FW, Outfall/Acid/Caustic Sewer
28-Jan-26
07-Feb-26
100%
EM01BPI200
01B Equipment Location Plans
28-Jan-26
08-Mar-26
100%
EM01DPI200
01D Equipment Location Plans
28-Jan-26
08-Mar-26
100%
EM01HPI200
01H Equipment Location Plans
28-Jan-26
08-Mar-26
100%
EM03CPI200
03C Equipment Location Plans
28-Jan-26
08-Mar-26
100%
EM03DPI200
03D Equipment Location Plans
28-Jan-26
08-Mar-26
100%
EK030PI014
Plot Plan - Utility Plant Issue IFC
28-Jan-26
29-Mar-26
100%
EM05UPI176
05U IDP - Plant Layout
29-Jan-26
31-Jan-26
100%
EM01DPI130
01D Model Review Mtg
31-Jan-26
01-Feb-26
100%
EM05UPI186
05U Planning Release
31-Jan-26
05-Feb-26
100%
EM01DCV113
01D Update Model CT Basin & Issue Dwgs-IFC
31-Jan-26
21-Mar-26
100%
EM01BPI133
01B IDP - Plant Layout
03-Feb-26
07-Feb-26
100%
EM01GCV164
01G Update Model Control Bldg Fdns & Issue Dwgs-IFC
03-Feb-26
25-Feb-26
100%
EM05UPI177
05U Detail Model Development
05-Feb-26
11-Feb-26
100%
EM01DPI133
01D IDP - Plant Layout
10-Feb-26
11-Feb-26
100%
EM01CCV160
01C Design & Model Major Eq. Fdns (Excluding EDR)
11-Feb-26
27-Dec-26
23%
EM03DPI021
03D Model Review Comment Resolution
11-Feb-26
13-Feb-26
100%
EM01UPIFWF
01U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
15-Feb-26
100%
EM03UPIFWF
03U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
15-Feb-26
100%
EM03CPI140
03C Model Review Comment Resolution
11-Feb-26
28-Feb-26
100%
EM01UPIWWF
01U IDP - Detail Design - Other HDPE (WW & DW)
11-Feb-26
04-Mar-26
100%
EM01UPISSF
01U IDP - Detail Design - Metalic Piping (SY, CW, PA & BS)
11-Feb-26
03-Apr-26
100%
EM03UPIOSF
03U IDP - Detail Design - Metalic Piping (OS)
11-Feb-26
04-Apr-26
100%
EM03UPIASF
03U IDP - Detail Design - Other HDPE (AS & NA)
11-Feb-26
11-Apr-26
100%
EM05UPI178
05U IDP - Detail Design - HDPE Piping (FW)
11-Feb-26
17-Feb-26
100%
EM03DPI133
03D IDP - Plant Layout
14-Feb-26
15-Feb-26
100%
EM01BPI132
01B Planning Release
14-Feb-26
05-Mar-26
100%
EM01YPI134
01Y Detail Model Development
18-Feb-26
27-Mar-26
100%
EM03BPI120
03B Plant Layout Model
19-Feb-26
20-Feb-26
100%
EM03FPI120
03F Plant Layout Model
22-Feb-26
12-Mar-26
100%
EM01BCV226
01B Issue Fdn IFC- 2001-FA/FB (Water Storage Tanks)
24-Feb-26
27-Dec-26
19%
EM03ECV110
03E Design & Model Containment Area
25-Feb-26
27-Dec-26
19%
EM03DPI132
03D Planning Release
25-Feb-26
25-Feb-26
100%
EM01UPIFWG
01U Iso Issue IFC - HDPE Piping FW
25-Feb-26
01-Mar-26
100%
EM03UPIFWG
03U Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
100%
EM05UPI190
05U U/G Iso Issue IFC - HDPE Piping (FW)
25-Feb-26
01-Mar-26
100%
EM03CPI133
03C IDP - Plant Layout
01-Mar-26
04-Mar-26
100%
EM01API131
01A Model Review Comment Resolution
04-Mar-26
04-Apr-26
100%
EM01DPI132
01D Planning Release
05-Mar-26
05-Mar-26
100%
EM01YPI132
01Y Planning Release
05-Mar-26
05-Mar-26
100%
EM01API130
01A Model Review Mtg
05-Mar-26
18-Mar-26
100%
EM03FPI123
03F Plant Layout Nozzle Release
11-Mar-26
18-Mar-26
100%
EM03CPI132
03C Planning Release
12-Mar-26
12-Mar-26
100%
EM01UPIWWG
01U Iso Issue IFC - Other HDPE WW & DW
12-Mar-26
14-Mar-26
100%
EM03CPI134
03C Detail Model Development
13-Mar-26
18-Apr-26
100%
EM03DCV163
03D MF302 2002-F Demineralized Water Tank - Dwgs-IFC
17-Mar-26
28-Mar-26
100%
EM01BMD228
01B Clips Release IFC (Tanks, 2001FA/FB)
18-Mar-26
01-Apr-26
100%
EM01YPI138
01Y Design / Issue Pipe Supports IFC
20-Mar-26
27-Dec-26
12%
EM03CPI138
03C Design / Issue Pipe Supports IFC
21-Mar-26
27-Dec-26
12%
EM03CCV164
03C Update Model Major Eq. Fdns & Issue Dwgs-IFC
24-Mar-26
11-Apr-26
100%
EM01DCV164
01D Update Model Major Eq. Fdns & Issue Dwgs-IFC
25-Mar-26
11-Apr-26
100%
EM03CMD229
03C Vessel Steel Release IFC (MD411 2203-F, 2204-F)
26-Mar-26
27-Dec-26
11%
EM03FMD229
03F Vessel Steel Release IFC (MD411, 2006-F)
26-Mar-26
27-Dec-26
11%
EM000ELEH2
01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC
31-Mar-26
27-Dec-26
9%
EM01JCV120
01J Design & Model Metering Enclosure
31-Mar-26
09-Apr-26
100%
EM01JCV130
01J Design & Model Metering Enclosure Fdns
31-Mar-26
09-Apr-26
100%
EM010IC123
UNIT 01 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM01BMD229
01B Vessel Steel Release IFC
01-Apr-26
27-Dec-26
9%
EM020IC124
UNIT 02 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM020IC128
Instrument Wiring Diagrams - IFC
01-Apr-26
27-Dec-26
9%
EM030IC125
UNIT 03 Instr. Location Plans - IFC
01-Apr-26
27-Dec-26
9%
EM050IC130
05B Instr. Location Plans - IFC
01-Apr-26
16-Jan-27
166.0d
8%
EM01JSY172
01J P&IDs & Line List Issue - IFD
01-Apr-26
01-Apr-26
100%
EM01YSY172
01Y P&IDs & Line List Issue - IFD
01-Apr-26
01-Apr-26
100%
EM01YCV122
01Y Update Model S/S Piperack & Issue Dwgs - IFC
03-Apr-26
27-Dec-26
8%
EM01UPICWG
01U U/G Plan Dwgs Issue IFC
04-Apr-26
27-Dec-26
7%
EM01UPISSG
01U Iso Issue IFC - Metalic Piping SY, CW, Pa & BS
04-Apr-26
17-Apr-26
100%
EM01API133
01A IDP - Plant Layout
04-Apr-26
08-Apr-26
100%
EM03CSY172
03C P&IDs & Line List Issue - IFD
10-Apr-26
10-Apr-26
100%
EM03CCV126
03C Conceptual Misc. Steel Design/ Model
11-Apr-26
27-Dec-26
5%
EM02UPI200
02U Issue U/G Material Final Release
15-Apr-26
27-Dec-26
5%
EM05UPI191
05U U/G Plan Dwgs IFC
15-Apr-26
27-Dec-26
5%
EM03BPI123
03B Plant Layout Nozzle Release
16-Apr-26
22-Apr-26
100%
EM03CCV166
03C Conceptual Misc. Foundations Design/ Model
16-Apr-26
27-Dec-26
5%
EM03YCV120
03Y Design & Model Major Structural Steel
17-Apr-26
27-Dec-26
5%
EM01UPI200
01U Issue U/G Material Final Release 90%
17-Apr-26
27-Dec-26
5%
EM03UPI200
03U Issue U/G Material Final Release (90%)
21-Apr-26
27-Dec-26
5%
EM05BEL120
05B Electrical Conceptual Layouts
21-Apr-26
27-Dec-26
5%
EM03UPI190
03U U/G Plan Dwgs Issue IFC
22-Apr-26
27-Dec-26
5%
EM03UPIASG
03U Iso Issue IFC - Other HDPE (AS & NA)
22-Apr-26
27-Dec-26
5%
EM03UPIOSG
03U Iso Issue IFC - Metalic Piping (OS)
22-Apr-26
27-Dec-26
5%
EM03CPI141
03C Detail OP's & Services Model Review Mtg
24-Apr-26
27-Dec-26
5%
EK000MF32D
05A MF312 2105-F Water Tank - Fdn Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EK020IC133
Field Bus J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
0%
EK100ELEK2
01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A
27-Dec-26
27-Dec-26
0%
EK200ELEK2
01H Develop & Issue Cable Ladder Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEJ2
01,03,05 Develop & Issue Lighting Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEK2
01,03,04,05 Develop & Issue Power Plans - IFC
27-Dec-26
27-Dec-26
0%
EM000ELEL2
01,03,04,05 Electrical Routing Plans
27-Dec-26
27-Dec-26
0%
EM000ELEM2
Dev/Issue Elect Cable/Raceway Sched IFC
27-Dec-26
27-Dec-26
0%
EM01API132
01A Planning Release
27-Dec-26
27-Dec-26
0%
EM01API134
01A Detail Model Development
27-Dec-26
27-Dec-26
0%
EM01API135
01A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01API136
01A IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01API138
01A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM01API141
01A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01API143
01A OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM01ASY172
01A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM01ASY272
01A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM01BCV123
01B Update Model S/S Sleepers & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01BCV126
01B Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM01BCV127
01B Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01BCV133
01B Update Model S/S Sleeper Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01BCV164
01B Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM01BCV166
01B Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
0%
EM01BCV167
01B Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01BPI134
01B Detail Model Development
27-Dec-26
27-Dec-26
0%
EM01BPI135
01B A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01BPI136
01B IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01BPI138
01B Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM01BPI141
01B Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01BPI143
01B OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM01BSY172
01B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM01BSY272
01B P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM01CCV164
01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Excluding EDR)
27-Dec-26
27-Dec-26
0%
EM01CCV180
01C Design & Model Major Eq. Fdns (Including EDR)
27-Dec-26
27-Dec-26
0%
EM01CCV190
01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Including EDR)
27-Dec-26
27-Dec-26
0%
EM01CPI132
01C Planning Release
27-Dec-26
27-Dec-26
0%
EM01CPI134
01C Detail Model Development
27-Dec-26
27-Dec-26
0%
EM01CPI135
01C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01CPI136
01C IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01CPI138
01C Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM01CPI141
01C Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01CPI142
01C OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM01CSY172
01C P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM01CSY272
01C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM01DCV122
01D Update Model S/S Sleepers & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01DCV126
01D Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM01DCV127
01D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01DCV133
01D Update Model S/S Sleeper Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01DCV166
01D Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
0%
EM01DCV167
01D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01DPI134
01D Detail Model Development
27-Dec-26
27-Dec-26
0%
EM01DPI135
01D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01DPI136
01D IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01DPI138
01D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM01DPI141
01D Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01DPI143
01D OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM01DSY172
01D P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM01DSY272
01D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM01HCV125
01H Design & Model Substation Fdns
27-Dec-26
27-Dec-26
0%
EM01HCV126
01H Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM01HCV127
01H Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01HCV128
01H Update Model Substation Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01HCV160
01H Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
0%
EM01HCV164
01H Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM01HCV166
01H Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
0%
EM01HCV167
01H Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01JCV122
01J Update Model Metering Enclosure & Issue Dwgs (Concrete Wall) - IFC
27-Dec-26
27-Dec-26
0%
EM01JCV133
01J Update Model Metering Enclosure Fdns & Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM01JPI130
01J Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01JPI132
01J Planning Release
27-Dec-26
27-Dec-26
0%
EM01JPI133
01J IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM01JPI134
01J Detail Model Development
27-Dec-26
27-Dec-26
0%
EM01JPI135
01J A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01JPI136
01J IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01JPI138
01J Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM01JPI140
01J Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM01JPI141
01J Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01JPI142
01J OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM01JSY272
01J P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM01YCV133
01Y Update Model Piperack Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM01YPI135
01Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM01YPI136
01Y IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM01YPI141
01Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM01YPI142
01Y OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM01YSY272
01Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM020IC127
Instrument Installation Details (10%) - IFC
27-Dec-26
27-Dec-26
0%
EM020IC129
Instrument Loop Diagrams - IFC
27-Dec-26
27-Dec-26
0%
EM020IC132
Traditional J-boxes Wiring Reports - IFC
27-Dec-26
27-Dec-26
0%
EM020IC134
DCS Marshalling Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC135
SIS Termination Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC136
ITCC Termination Report - IFC
27-Dec-26
27-Dec-26
0%
EM020IC137
Miscellaneous Wiring Report - IFC
27-Dec-26
27-Dec-26
0%
EM03ACV126
03A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ACV127
03A Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03ACV160
03A Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
0%
EM03ACV164
03A Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ACV166
03A Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ACV167
03A Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03API130
03A Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03API132
03A Planning Release
27-Dec-26
27-Dec-26
0%
EM03API133
03A IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM03API134
03A Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03API135
03A A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03API136
03A IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03API138
03A Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03API140
03A Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03API141
03A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03API142
03A OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03ASY172
03A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03ASY272
03A P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03BCV112
03B Update Model Sumps & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03BCV126
03B Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03BCV127
03B Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03BCV166
03B Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03BCV167
03B Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03BMD229
03B Vessel Steel Release IFC
27-Dec-26
27-Dec-26
0%
EM03BPI130
03B Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03BPI132
03B Planning Release
27-Dec-26
27-Dec-26
0%
EM03BPI133
03B IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM03BPI134
03B Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03BPI135
03B A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03BPI136
03B IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03BPI138
03B Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03BPI140
03B Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03BPI141
03B Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03BPI142
03B OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03BSY172
03B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03BSY272
03B P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03CCV127
03C Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03CCV167
03C Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03CPI135
03C A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03CPI136
03C IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03CPI142
03C OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03CSY272
03C P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03DCV126
03D Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03DCV127
03D Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03DCV164
03D Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03DCV166
03D Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03DCV167
03D Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03DPI134
03D Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03DPI135
03D A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03DPI136
03D IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03DPI138
03D Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03DPI141
03D Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03DPI143
03D OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM03DSY172
03D P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03DSY272
03D P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03ECV112
03E Update Model Containment Area & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ECV126
03E Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ECV127
03E Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03ECV160
03E Design & Model Major Eq. Fdns
27-Dec-26
27-Dec-26
0%
EM03ECV164
03E Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03ECV166
03E Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03ECV167
03E Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03EPI123
03E Plant Layout Nozzle Release
27-Dec-26
27-Dec-26
0%
EM03EPI130
03E Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03EPI132
03E Planning Release
27-Dec-26
27-Dec-26
0%
EM03EPI133
03E IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM03EPI134
03E Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03EPI135
03E A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03EPI136
03E IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03EPI138
03E Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03EPI141
03E Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03EPI142
03E Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03EPI143
03E OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03ESY172
03E P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03ESY272
03E P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03FCV126
03F Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM03FCV127
03F Model Misc. Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03FCV164
03F Update Model Major Eq. Fdns & Issue Dwgs-IFC
27-Dec-26
27-Dec-26
0%
EM03FCV166
03F Conceptual Misc. Foundations Design/ Model
27-Dec-26
27-Dec-26
0%
EM03FCV167
03F Update Model Misc Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03FPI130
03F Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03FPI132
03F Planning Release
27-Dec-26
27-Dec-26
0%
EM03FPI133
03F IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM03FPI134
03F Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03FPI135
03F A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03FPI136
03F IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03FPI138
03F Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03FPI141
03F Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03FPI142
03F Detail OP's & Service Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03FPI143
03F OP's & Serv. Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM03FPI200
03F Equipment Location Plans
27-Dec-26
27-Dec-26
0%
EM03FSY172
03F P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03FSY272
03F P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM03YCV122
03Y Update Model Struct Steel & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03YCV133
03Y Update Model Piperack Fdns & Issue Dwgs - IFC
27-Dec-26
27-Dec-26
0%
EM03YPI130
03Y Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03YPI132
03Y Planning Release
27-Dec-26
27-Dec-26
0%
EM03YPI133
03Y IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM03YPI134
03Y Detail Model Development
27-Dec-26
27-Dec-26
0%
EM03YPI135
03Y A/G Piping Iso's - Issue IFC
27-Dec-26
27-Dec-26
0%
EM03YPI136
03Y IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM03YPI138
03Y Design / Issue Pipe Supports IFC
27-Dec-26
27-Dec-26
0%
EM03YPI141
03Y Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM03YPI143
03Y OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM03YSY172
03Y P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM03YSY272
03Y P&IDs & Line List Issue - IFC
27-Dec-26
27-Dec-26
0%
EM04API120
04A Plant Layout Model
27-Dec-26
27-Dec-26
0%
EM04API134
04A Plant Detail Model Development
27-Dec-26
27-Dec-26
0%
EM04API138
04A Design / Issue Pipe & Supports IFC
27-Dec-26
27-Dec-26
0%
EM04API200
04A Issue U/G Material Final Release
27-Dec-26
27-Dec-26
0%
EM05ACV126
05A Conceptual Misc. Steel Design/ Model
27-Dec-26
27-Dec-26
0%
EM05ACV166
05A Conceptual Misc. Foundation Design/ Model
27-Dec-26
27-Dec-26
0%
EM05AMD229
05A Vessel Steel Release IFC
27-Dec-26
27-Dec-26
0%
EM05API130
05A Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API132
05A Planning Release
27-Dec-26
27-Dec-26
0%
EM05API133
05A IDP - Plant Layout
27-Dec-26
27-Dec-26
0%
EM05API134
05A Detail Model Development
27-Dec-26
27-Dec-26
0%
EM05API136
05A IDP - Detail Design
27-Dec-26
27-Dec-26
0%
EM05API140
05A Model Review Comment Resolution
27-Dec-26
27-Dec-26
0%
EM05API142
05A Detail OP's & Services Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05API143
05A OP's & Serv. Model Review Comments Resolution
27-Dec-26
27-Dec-26
0%
EM05BPI120
05B Plant Layout Model
27-Dec-26
27-Dec-26
0%
EM05BPI130
05B Model Review Mtg
27-Dec-26
27-Dec-26
0%
EM05BSY172
05B P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EM05UPI200
05U Issue U/G Material Final Release
27-Dec-26
27-Dec-26
0%
EM5ASY172
05A P&IDs & Line List Issue - IFD
27-Dec-26
27-Dec-26
0%
EK020IC131
Instrument Loop Diagrams FF - IFC
30-Dec-26
03-Jan-27
530.0d
0%
EM000ELEN3
01,03 Equipment Interconnection Diagrams
30-Dec-26
30-Jan-27
511.0d
0%
EM05ACV122
05A Update Model PR Struct Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
21.0d
0%
EM05ACV127
05A Model Misc. Steel & Issue Dwgs - IFC
30-Dec-26
10-Jan-27
25.0d
0%
EM05ACV164
05A Update Model Major Eq. Fdns & Issue Dwgs-IFC
30-Dec-26
27-Jan-27
-14.0d
0%
EM05API135
05A A/G Piping Iso's - Issue IFC
30-Dec-26
03-Jan-27
90.0d
0%
EM05API138
05A Design / Issue Pipe Supports IFC
30-Dec-26
03-Jan-27
162.0d
0%
EM05BCV122
05B Design / Model / IFC - Sleeper Steel & FDN's
30-Dec-26
24-Jan-27
71.0d
0%
EM05BCV133
05B Design / Model / IFC - S/S at Jetty
30-Dec-26
24-Jan-27
71.0d
0%
EM05BPI141
05B Model Review Comment Resolution
30-Dec-26
10-Jan-27
75.0d
0%
EM05ACV133
05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC
01-Jan-27
10-Jan-27
121.0d
0%
EM5ASY272
05A P&IDs & Line List Issue - IFC
01-Jan-27
01-Jan-27
164.0d
0%
EM5BSY272
05B P&IDs & Line List Issue - IFC
01-Jan-27
01-Jan-27
267.0d
0%
EM000IC100
Instrument Index - IFC
06-Jan-27
06-Jan-27
530.0d
0%
EM05BPI133
05B IDP - Plant Layout
13-Jan-27
14-Jan-27
75.0d
0%
EM05ACV167
05A Update Model Misc Fdns & Issue Dwgs - IFC
15-Jan-27
24-Jan-27
111.0d
0%
EM05BCV167
05B Design / Model / IFC - Equip. Fdn's.
20-Jan-27
20-Jan-27
221.0d
0%
EM05BPI132
05B Planning Release
20-Jan-27
24-Jan-27
75.0d
0%
EM05BPI200
05B Equipment Location Plans
20-Jan-27
24-Jan-27
221.0d
0%
EM05BPI134
05B Detail Model Development
27-Jan-27
31-Jan-27
75.0d
0%
EM05BPI142
05B Detail OP's & Services Model Review Mtg
03-Feb-27
03-Feb-27
75.0d
0%
EM05BPI143
05B OP's & Serv. Model Review Comments Resolution
04-Feb-27
06-Feb-27
75.0d
0%
EM05BPI136
05B IDP - Detail Design
07-Feb-27
10-Feb-27
75.0d
0%
EM05BPI135
05B A/G Piping Iso's - Issue IFC
14-Feb-27
21-Feb-27
75.0d
0%
EM05BPI138
05B Design / Issue Pipe Supports IFC
14-Feb-27
21-Feb-27
230.0d
0%
Feb 2025 Mar 2025 Apr 2025 May 2025 Jun 2025 Jul 2025 Aug 2025 Sep 2025 Oct 2025 Nov 2025 Dec 2025 Jan 2026 Feb 2026 Mar 2026 Apr 2026 May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Jan 2027 Feb 2027 Data Date
EM000MD42C — Prepare & Issue Prelim. RFQ - MD402 to Proc. | 12-Feb-25 → 16-Feb-25 | Complete 100% | float — EM000MD42C EM000PI025 — Develop Piping Specs (PDS) | 19-Feb-25 → 23-Jul-25 | Complete 100% | float — EM000PI025 EM000MD22C — Prepare & Issue Prelim. RFQ - MD202 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD44C — Prepare & Issue Prelim. RFQ - MD404 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD46C — Prepare & Issue Prelim. RFQ - MD411 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM00MD45C — Prepare & Issue Prelim. RFQ - MD405 to Proc. | 26-Feb-25 → 28-Feb-25 | Complete 100% | float — EM000MD22D — Technical Evaluation - MD202 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD22D EM000MD42D — Technical Evaluation - MD402 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD42D EM000MD44D — Technical Evaluation - MD404 | 22-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD44D EM000MD46D — Technical Evaluation - MD411 | 22-Mar-25 → 19-Apr-25 | Complete 100% | float — EM000MD46D EM000MD45D — Technical Evaluation - MD405 | 26-Mar-25 → 18-Apr-25 | Complete 100% | float — EM000MD45D EM000MD47F — Develop & Issue Inquiry for ERW - MD406 | 27-Apr-25 → 11-May-25 | Complete 100% | float — EM000MD47F EM000MD42E — Prepare & Issue Purchase ERW - MD402 | 01-May-25 → 04-May-25 | Complete 100% | float — EM000MD44E — Prepare & Issue Purchase ERW - MD404 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD45E — Prepare & Issue Purchase ERW - MD405 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD46E — Prepare & Issue Purchase ERW - MD411 | 03-Jun-25 → 05-Jun-25 | Complete 100% | float — EM000MD22E — Prepare & Issue Purchase ERW - MD202 | 10-Jun-25 → 13-Jun-25 | Complete 100% | float — EM03EPI120 — 03E Plant Layout Model | 14-Jun-25 → 27-Dec-26 | In Progress 56% | float — EM03EPI120 EM01YPI120 — 01Y Plant Layout Model | 14-Jun-25 → 18-Dec-25 | Complete 100% | float — EM01YPI120 EM03EEL120 — 03E Electrical Conceptual Layouts | 01-Jul-25 → 01-Mar-26 | Complete 100% | float — EM03EEL120 EM000MD47D — Technical Evaluation - MD406 | 02-Jul-25 → 06-Jul-25 | Complete 100% | float — EM000MD47D EM03API120 — 03A Plant Layout Model | 22-Jul-25 → 27-Dec-26 | In Progress 53% | float — EM03API120 EM03YPI120 — 03Y Plant Layout Model | 22-Jul-25 → 27-Dec-26 | In Progress 53% | float — EM03YPI120 EM03AEL120 — 03A Electrical Conceptual Layouts | 23-Jul-25 → 27-Sep-25 | Complete 100% | float — EM03AEL120 EM03DPI120 — 03D Plant Layout Model | 08-Aug-25 → 15-Feb-26 | Complete 100% | float — EM03DPI120 EM03DEL120 — 03D Electrical Conceptual Layouts | 09-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03DEL120 EM03BEL120 — 03B Electrical Conceptual Layouts | 12-Aug-25 → 19-Oct-25 | Complete 100% | float — EM03BEL120 EM03API123 — 03A Plant Layout Nozzle Release | 15-Aug-25 → 27-Sep-25 | Complete 100% | float — EM03API123 EM000MD47E — Prepare & Issue Purchase ERW - MD406 | 16-Aug-25 → 21-Aug-25 | Complete 100% | float — EM000MD47E PM000MD45N — Recv. Planning V. Data MD405 | 16-Aug-25 → 02-Sep-25 | Complete 100% | float — PM000MD45N PM000MD42N — Recv. Planning V. Data MD402 | 16-Aug-25 → 19-Oct-25 | Complete 100% | float — PM000MD42N PM000MD22N — Recv. Planning V. Data MD202 | 16-Aug-25 → 12-Nov-25 | Complete 100% | float — PM000MD22N EM03YEL120 — 03Y Electrical Conceptual Layouts | 19-Aug-25 → 11-Oct-25 | Complete 100% | float — EM03YEL120 EM03FEL120 — 03F Electrical Conceptual Layouts | 19-Aug-25 → 23-Oct-25 | Complete 100% | float — EM03FEL120 EM01BPI120 — 01B Plant Layout Model | 21-Aug-25 → 01-Feb-26 | Complete 100% | float — EM01BPI120 EM01CPI120 — 01C Plant Layout Model | 24-Aug-25 → 27-Dec-26 | In Progress 50% | float — EM01CPI120 PM000MD46N — Recv. Planning V. Data MD411 | 27-Aug-25 → 13-Sep-25 | Complete 100% | float — PM000MD46N EM01YEL120 — 01Y Electrical Conceptual Layouts | 28-Aug-25 → 03-Oct-25 | Complete 100% | float — EM01YEL120 EM01CEL120 — 01C Electrical Conceptual Layouts | 02-Sep-25 → 17-Feb-26 | Complete 100% | float — EM01CEL120 EM01DCV110 — 01D Design & Model Cooling Tower Basin | 03-Sep-25 → 20-Nov-25 | Complete 100% | float — EM01DCV110 EM01DPI120 — 01D Plant Layout Model | 03-Sep-25 → 29-Jan-26 | Complete 100% | float — EM01DPI120 EM01DCV120 — 01D Design & Model Structural Steel Sleepers | 03-Sep-25 → 01-Feb-26 | Complete 100% | float — EM01DCV120 EM01DCV160 — 01D Design & Model Major Eq. Fdns | 03-Sep-25 → 01-Feb-26 | Complete 100% | float — EM01DCV160 PM000MD44N — Recv. Planning V. Data MD404 | 17-Sep-25 → 30-Sep-25 | Complete 100% | float — PM000MD44N EM03DPI123 — 03D Plant Layout Nozzle Release | 18-Sep-25 → 27-Sep-25 | Complete 100% | float — EM03DPI123 EM01BEL120 — 01B Electrical Conceptual Layouts | 21-Sep-25 → 03-Oct-25 | Complete 100% | float — EM01BEL120 EM01DEL120 — 01D Electrical Conceptual Layouts | 21-Sep-25 → 03-Oct-25 | Complete 100% | float — EM01DEL120 EM01GCV160 — 01G Design & Model Control Building Fdns | 21-Sep-25 → 10-Dec-25 | Complete 100% | float — EM01GCV160 PM000MD47N — Recv. Planning V. Data MD406 | 23-Sep-25 → 09-Oct-25 | Complete 100% | float — PM000MD47N EM03DCV160 — 03D Design & Model Major Eq. Fdns | 24-Sep-25 → 13-Nov-25 | Complete 100% | float — EM03DCV160 EM01DCV130 — 01D Design & Model S/S Sleeper Fdns | 25-Sep-25 → 01-Feb-26 | Complete 100% | float — EM01DCV130 EM01EEL120 — 01E Electrical Conceptual Layouts | 27-Sep-25 → 12-Nov-25 | Complete 100% | float — EM01EEL120 EM01AEL120 — 01A Electrical Conceptual Layouts | 01-Oct-25 → 08-Oct-25 | Complete 100% | float — EM01AEL120 EM05UPI175 — 05U Plant Layout Model - Common | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM05UPI175 EM000CV164 — Issue Anchor Bolts,Rebar, & Misc. Fnd Matl. Take-Off's to OCI | 01-Oct-25 → 29-Oct-25 | Complete 100% | float — EM000CV164 EM03CEL120 — 03C Electrical Conceptual Layouts | 01-Oct-25 → 06-Nov-25 | Complete 100% | float — EM03CEL120 EM03CPI120 — 03C Plant Layout Model | 01-Oct-25 → 17-Dec-25 | Complete 100% | float — EM03CPI120 EM01JPI120 — 01J Plant Layout Model | 01-Oct-25 → 17-Apr-26 | Complete 100% | float — EM01JPI120 EM01UPIBSB — 01U IDP - Plant Layout - Benfield Sewer | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPIBSB EM01UPICWB — 01U IDP - Plant Layout - Cooling Water | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPICWB EM01UPIFWB — 01U IDP - Plant Layout - Firewater | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPIFWB EM01UPIPAB — 01U IDP - Plant Layout - Plant Air | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPIPAB EM01UPIPWB — 01U IDP - Plant Layout - Potable Water | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPIPWB EM01UPISSB — 01U IDP - Plant Layout - Sanitary Sewer | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPISSB EM01UPIWWB — 01U IDP - Plant Layout - Waste Water | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM01UPIWWB EM03UPIASB — 03U IDP - Plant Layout - Acid Sewer | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM03UPIASB EM03UPICSB — 03U IDP - Plant Layout - Caustic Sewer | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM03UPICSB EM03UPIFWB — 03U IDP - Plant Layout - Firewater | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM03UPIFWB EM03UPIOSB — 03U IDP - Plant Layout - Outfall Sewer | 01-Oct-25 → 11-Oct-25 | Complete 100% | float — EM03UPIOSB EM01HEL120 — 01H Electrical Conceptual Layouts | 01-Oct-25 → 09-Nov-25 | Complete 100% | float — EM01HEL120 EM020IC126 — Instrument Installation Details (90%) - IFC | 07-Oct-25 → 18-Apr-26 | Complete 100% | float — EM020IC126 EM01BCV130 — 01B Design & Model S/S Sleeper Fdns | 09-Oct-25 → 14-Feb-26 | Complete 100% | float — EM01BCV130 EM01BCV120 — 01B Design & Model Structural Steel Sleepers | 09-Oct-25 → 15-Feb-26 | Complete 100% | float — EM01BCV120 EM01BCV160 — 01B Design & Model Major Eq. Fdns | 09-Oct-25 → 15-Feb-26 | Complete 100% | float — EM01BCV160 EM01UPI186 — 01U Planning Release - Common, SS, FW, CW, WW, AP, WP | 11-Oct-25 → 01-Feb-26 | Complete 100% | float — EM01UPI186 EM01API120 — 01A Plant Layout Model | 15-Oct-25 → 18-Feb-26 | Complete 100% | float — EM01API120 EM000U000 — Start U/G Model Reviews | 16-Oct-25 | Complete EM01BPI123 — 01B Plant Layout Nozzle Release | 19-Oct-25 → 25-Oct-25 | Complete 100% | float — EM01BPI123 EM01JEL120 — 01J Electrical Conceptual Layouts | 22-Oct-25 → 12-Nov-25 | Complete 100% | float — EM01JEL120 EM01UPIBSC — 01U Model Review Mtg (HOC/MEC) - Benfield Sewer | 23-Oct-25 → 23-Oct-25 | Complete 100% | float — EM01UPIPAC — 01U Model Review Mtg -Plant Air | 28-Oct-25 → 31-Oct-25 | Complete 100% | float — EM01UPIPWC — 01U Model Review Mtg -Potable Water | 28-Oct-25 → 31-Oct-25 | Complete 100% | float — EM01UPIWWC — 01U Model Review Mtg - Waste Water | 28-Oct-25 → 31-Oct-25 | Complete 100% | float — EM03UPIASC — 03U Model Review Mtg (HOC/MEC) - Acid Sewer | 28-Oct-25 → 02-Nov-25 | Complete 100% | float — EM03UPIASC EM03UPICSC — 03U Model Review Mtg (HOC/MEC) - Caustic Sewer | 28-Oct-25 → 02-Nov-25 | Complete 100% | float — EM03UPICSC EM03UPIFWC — 03U Model Review Mtg (HOC/MEC) - Firewater | 28-Oct-25 → 02-Nov-25 | Complete 100% | float — EM03UPIFWC EM03UPIOSC — 03U Model Review Mtg (HOC/MEC) - Outfall Sewer | 28-Oct-25 → 02-Nov-25 | Complete 100% | float — EM03UPIOSC EM01UPICWC — 01U Model Review Mtg - Cooling Water | 29-Oct-25 → 01-Nov-25 | Complete 100% | float — EM01UPIFWC — 01U Model Review Mtg - Firewater | 29-Oct-25 → 01-Nov-25 | Complete 100% | float — EM01UPISSC — 01U Model Review Mtg - Sanitary Sewer | 29-Oct-25 → 01-Nov-25 | Complete 100% | float — EM01API123 — 01A Plant Layout Nozzle Release | 05-Nov-25 → 20-Nov-25 | Complete 100% | float — EM01API123 EM03CPI123 — 03C Plant Layout Nozzle Release | 19-Nov-25 → 23-Nov-25 | Complete 100% | float — EM03CPI123 EM03UPIASD — 03U Planning Release - Acid Sewer | 19-Nov-25 → 23-Dec-25 | Complete 100% | float — EM03UPIASD EM03UPICSD — 03U Planning Release - Caustic Sewer | 19-Nov-25 → 23-Dec-25 | Complete 100% | float — EM03UPICSD EM03UPIFWD — 03U Planning Release - Firewater | 19-Nov-25 → 23-Dec-25 | Complete 100% | float — EM03UPIFWD EM03UPIOSD — 03U Planning Release - Outfall Sewer | 19-Nov-25 → 23-Dec-25 | Complete 100% | float — EM03UPIOSD EM03YCV130 — 03Y Design & Model Structural Piperack Fdns | 19-Nov-25 → 24-Dec-25 | Complete 100% | float — EM03YCV130 EM03CCV160 — 03C Design & Model Major Eq. Fdns | 19-Nov-25 → 17-Jan-26 | Complete 100% | float — EM03CCV160 EM03CCV110 — 03C Design & Model Containment Area | 19-Nov-25 → 25-Feb-26 | Complete 100% | float — EM03CCV110 EM05API120 — 05A Plant Layout Model | 19-Nov-25 → 25-Feb-26 | Complete 100% | float — EM05API120 EM05ACV120 — 05A Design & Model PR Structural Steel | 22-Nov-25 → 26-Feb-26 | Complete 100% | float — EM05ACV120 EM05ACV130 — 05A Design & Model Structural Piperack Fdns | 03-Dec-25 → 24-Feb-26 | Complete 100% | float — EM05ACV130 EM01YCV130 — 01Y Design & Model Structural Piperack Fdns | 04-Dec-25 → 15-Feb-26 | Complete 100% | float — EM01YCV130 EM01YCV120 — 01Y Design & Model Structural Steel Piperack | 06-Dec-25 → 15-Feb-26 | Complete 100% | float — EM01YCV120 EM05AEL120 — 05A Electrical Conceptual Layouts | 17-Dec-25 → 19-Feb-26 | Complete 100% | float — EM05AEL120 EM03BCV110 — 03B Design & Model Sumps | 30-Dec-25 → 27-Dec-26 | In Progress 32% | float — EM03BCV110 EM05ACV160 — 05A Design & Model Major Eq. Fdns | 03-Jan-26 → 27-Dec-26 | In Progress 31% | float — EM05ACV160 EM03FCV160 — 03F Design & Model Major Eq. Fdns | 07-Jan-26 → 27-Dec-26 | In Progress 30% | float — EM03FCV160 EM000MCG10 — GEN and ADMINISTRATIVE | 13-Jan-26 → 27-Dec-26 | In Progress 29% | float — EM000MCG10 EM03DPI130 — 03D Model Review Mtg | 16-Jan-26 → 16-Jan-26 | Complete 100% | float — EM01YPI130 — 01Y Model Review Mtg | 20-Jan-26 → 21-Jan-26 | Complete 100% | float — EM01YPI140 — 01Y Model Review Comment Resolution | 21-Jan-26 → 27-Jan-26 | Complete 100% | float — EM01YPI140 EM01BPI130 — 01B Model Review Mtg | 23-Jan-26 → 24-Jan-26 | Complete 100% | float — EM05UPI141 — 05U Model Review Mtg | 27-Jan-26 → 28-Jan-26 | Complete 100% | float — EM01BPI121 — 01B Model Review Comment Resolution | 27-Jan-26 → 31-Jan-26 | Complete 100% | float — EM01BPI121 EM01API200 — 01A Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM01API200 EM01CPI200 — 01C Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM01CPI200 EM03API200 — 03A Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM03API200 EM03BPI200 — 03B Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM03BPI200 EM03EPI200 — 03E Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM03EPI200 EM05API200 — 05A Equipment Location Plans | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EM05API200 EM01YPI133 — 01Y IDP - Plant Layout | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — EM03CPI130 — 03C Model Review Mtg | 28-Jan-26 → 29-Jan-26 | Complete 100% | float — EM03UPIFWE — 03U Detail Model Development - FW, Outfall/Acid/Caustic Sewer | 28-Jan-26 → 07-Feb-26 | Complete 100% | float — EM03UPIFWE EM01BPI200 — 01B Equipment Location Plans | 28-Jan-26 → 08-Mar-26 | Complete 100% | float — EM01BPI200 EM01DPI200 — 01D Equipment Location Plans | 28-Jan-26 → 08-Mar-26 | Complete 100% | float — EM01DPI200 EM01HPI200 — 01H Equipment Location Plans | 28-Jan-26 → 08-Mar-26 | Complete 100% | float — EM01HPI200 EM03CPI200 — 03C Equipment Location Plans | 28-Jan-26 → 08-Mar-26 | Complete 100% | float — EM03CPI200 EM03DPI200 — 03D Equipment Location Plans | 28-Jan-26 → 08-Mar-26 | Complete 100% | float — EM03DPI200 EK030PI014 — Plot Plan - Utility Plant Issue IFC | 28-Jan-26 → 29-Mar-26 | Complete 100% | float — EK030PI014 EM05UPI176 — 05U IDP - Plant Layout | 29-Jan-26 → 31-Jan-26 | Complete 100% | float — EM01DPI130 — 01D Model Review Mtg | 31-Jan-26 → 01-Feb-26 | Complete 100% | float — EM05UPI186 — 05U Planning Release | 31-Jan-26 → 05-Feb-26 | Complete 100% | float — EM05UPI186 EM01DCV113 — 01D Update Model CT Basin & Issue Dwgs-IFC | 31-Jan-26 → 21-Mar-26 | Complete 100% | float — EM01DCV113 EM01BPI133 — 01B IDP - Plant Layout | 03-Feb-26 → 07-Feb-26 | Complete 100% | float — EM01BPI133 EM01GCV164 — 01G Update Model Control Bldg Fdns & Issue Dwgs-IFC | 03-Feb-26 → 25-Feb-26 | Complete 100% | float — EM01GCV164 EM05UPI177 — 05U Detail Model Development | 05-Feb-26 → 11-Feb-26 | Complete 100% | float — EM05UPI177 EM01DPI133 — 01D IDP - Plant Layout | 10-Feb-26 → 11-Feb-26 | Complete 100% | float — EM01CCV160 — 01C Design & Model Major Eq. Fdns (Excluding EDR) | 11-Feb-26 → 27-Dec-26 | In Progress 23% | float — EM01CCV160 EM03DPI021 — 03D Model Review Comment Resolution | 11-Feb-26 → 13-Feb-26 | Complete 100% | float — EM01UPIFWF — 01U IDP - Detail Design - HDPE Piping (FW) | 11-Feb-26 → 15-Feb-26 | Complete 100% | float — EM01UPIFWF EM03UPIFWF — 03U IDP - Detail Design - HDPE Piping (FW) | 11-Feb-26 → 15-Feb-26 | Complete 100% | float — EM03UPIFWF EM03CPI140 — 03C Model Review Comment Resolution | 11-Feb-26 → 28-Feb-26 | Complete 100% | float — EM03CPI140 EM01UPIWWF — 01U IDP - Detail Design - Other HDPE (WW & DW) | 11-Feb-26 → 04-Mar-26 | Complete 100% | float — EM01UPIWWF EM01UPISSF — 01U IDP - Detail Design - Metalic Piping (SY, CW, PA & BS) | 11-Feb-26 → 03-Apr-26 | Complete 100% | float — EM01UPISSF EM03UPIOSF — 03U IDP - Detail Design - Metalic Piping (OS) | 11-Feb-26 → 04-Apr-26 | Complete 100% | float — EM03UPIOSF EM03UPIASF — 03U IDP - Detail Design - Other HDPE (AS & NA) | 11-Feb-26 → 11-Apr-26 | Complete 100% | float — EM03UPIASF EM05UPI178 — 05U IDP - Detail Design - HDPE Piping (FW) | 11-Feb-26 → 17-Feb-26 | Complete 100% | float — EM05UPI178 EM03DPI133 — 03D IDP - Plant Layout | 14-Feb-26 → 15-Feb-26 | Complete 100% | float — EM01BPI132 — 01B Planning Release | 14-Feb-26 → 05-Mar-26 | Complete 100% | float — EM01BPI132 EM01YPI134 — 01Y Detail Model Development | 18-Feb-26 → 27-Mar-26 | Complete 100% | float — EM01YPI134 EM03BPI120 — 03B Plant Layout Model | 19-Feb-26 → 20-Feb-26 | Complete 100% | float — EM03FPI120 — 03F Plant Layout Model | 22-Feb-26 → 12-Mar-26 | Complete 100% | float — EM03FPI120 EM01BCV226 — 01B Issue Fdn IFC- 2001-FA/FB (Water Storage Tanks) | 24-Feb-26 → 27-Dec-26 | In Progress 19% | float — EM01BCV226 EM03ECV110 — 03E Design & Model Containment Area | 25-Feb-26 → 27-Dec-26 | In Progress 19% | float — EM03ECV110 EM03DPI132 — 03D Planning Release | 25-Feb-26 → 25-Feb-26 | Complete 100% | float — EM01UPIFWG — 01U Iso Issue IFC - HDPE Piping FW | 25-Feb-26 → 01-Mar-26 | Complete 100% | float — EM01UPIFWG EM03UPIFWG — 03U Iso Issue IFC - HDPE Piping (FW) | 25-Feb-26 → 01-Mar-26 | Complete 100% | float — EM03UPIFWG EM05UPI190 — 05U U/G Iso Issue IFC - HDPE Piping (FW) | 25-Feb-26 → 01-Mar-26 | Complete 100% | float — EM05UPI190 EM03CPI133 — 03C IDP - Plant Layout | 01-Mar-26 → 04-Mar-26 | Complete 100% | float — EM01API131 — 01A Model Review Comment Resolution | 04-Mar-26 → 04-Apr-26 | Complete 100% | float — EM01API131 EM01DPI132 — 01D Planning Release | 05-Mar-26 → 05-Mar-26 | Complete 100% | float — EM01YPI132 — 01Y Planning Release | 05-Mar-26 → 05-Mar-26 | Complete 100% | float — EM01API130 — 01A Model Review Mtg | 05-Mar-26 → 18-Mar-26 | Complete 100% | float — EM01API130 EM03FPI123 — 03F Plant Layout Nozzle Release | 11-Mar-26 → 18-Mar-26 | Complete 100% | float — EM03FPI123 EM03CPI132 — 03C Planning Release | 12-Mar-26 → 12-Mar-26 | Complete 100% | float — EM01UPIWWG — 01U Iso Issue IFC - Other HDPE WW & DW | 12-Mar-26 → 14-Mar-26 | Complete 100% | float — EM03CPI134 — 03C Detail Model Development | 13-Mar-26 → 18-Apr-26 | Complete 100% | float — EM03CPI134 EM03DCV163 — 03D MF302 2002-F Demineralized Water Tank - Dwgs-IFC | 17-Mar-26 → 28-Mar-26 | Complete 100% | float — EM03DCV163 EM01BMD228 — 01B Clips Release IFC (Tanks, 2001FA/FB) | 18-Mar-26 → 01-Apr-26 | Complete 100% | float — EM01BMD228 EM01YPI138 — 01Y Design / Issue Pipe Supports IFC | 20-Mar-26 → 27-Dec-26 | In Progress 12% | float — EM01YPI138 EM03CPI138 — 03C Design / Issue Pipe Supports IFC | 21-Mar-26 → 27-Dec-26 | In Progress 12% | float — EM03CPI138 EM03CCV164 — 03C Update Model Major Eq. Fdns & Issue Dwgs-IFC | 24-Mar-26 → 11-Apr-26 | Complete 100% | float — EM03CCV164 EM01DCV164 — 01D Update Model Major Eq. Fdns & Issue Dwgs-IFC | 25-Mar-26 → 11-Apr-26 | Complete 100% | float — EM01DCV164 EM03CMD229 — 03C Vessel Steel Release IFC (MD411 2203-F, 2204-F) | 26-Mar-26 → 27-Dec-26 | In Progress 11% | float — EM03CMD229 EM03FMD229 — 03F Vessel Steel Release IFC (MD411, 2006-F) | 26-Mar-26 → 27-Dec-26 | In Progress 11% | float — EM03FMD229 EM000ELEH2 — 01,03,05 Develop & Issue Earthing / Grounding Dwgs - IFC | 31-Mar-26 → 27-Dec-26 | In Progress 9% | float — EM000ELEH2 EM01JCV120 — 01J Design & Model Metering Enclosure | 31-Mar-26 → 09-Apr-26 | Complete 100% | float — EM01JCV120 EM01JCV130 — 01J Design & Model Metering Enclosure Fdns | 31-Mar-26 → 09-Apr-26 | Complete 100% | float — EM01JCV130 EM010IC123 — UNIT 01 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM010IC123 EM01BMD229 — 01B Vessel Steel Release IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM01BMD229 EM020IC124 — UNIT 02 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM020IC124 EM020IC128 — Instrument Wiring Diagrams - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM020IC128 EM030IC125 — UNIT 03 Instr. Location Plans - IFC | 01-Apr-26 → 27-Dec-26 | In Progress 9% | float — EM030IC125 EM050IC130 — 05B Instr. Location Plans - IFC | 01-Apr-26 → 16-Jan-27 | In Progress 8% | float 166.0d EM050IC130 EM01JSY172 — 01J P&IDs & Line List Issue - IFD | 01-Apr-26 | Complete EM01YSY172 — 01Y P&IDs & Line List Issue - IFD | 01-Apr-26 | Complete EM01YCV122 — 01Y Update Model S/S Piperack & Issue Dwgs - IFC | 03-Apr-26 → 27-Dec-26 | In Progress 8% | float — EM01YCV122 EM01UPICWG — 01U U/G Plan Dwgs Issue IFC | 04-Apr-26 → 27-Dec-26 | In Progress 7% | float — EM01UPICWG EM01UPISSG — 01U Iso Issue IFC - Metalic Piping SY, CW, Pa & BS | 04-Apr-26 → 17-Apr-26 | Complete 100% | float — EM01UPISSG EM01API133 — 01A IDP - Plant Layout | 04-Apr-26 → 08-Apr-26 | Complete 100% | float — EM01API133 EM03CSY172 — 03C P&IDs & Line List Issue - IFD | 10-Apr-26 | Complete EM03CCV126 — 03C Conceptual Misc. Steel Design/ Model | 11-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03CCV126 EM02UPI200 — 02U Issue U/G Material Final Release | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM02UPI200 EM05UPI191 — 05U U/G Plan Dwgs IFC | 15-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM05UPI191 EM03BPI123 — 03B Plant Layout Nozzle Release | 16-Apr-26 → 22-Apr-26 | Complete 100% | float — EM03BPI123 EM03CCV166 — 03C Conceptual Misc. Foundations Design/ Model | 16-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03CCV166 EM03YCV120 — 03Y Design & Model Major Structural Steel | 17-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03YCV120 EM01UPI200 — 01U Issue U/G Material Final Release 90% | 17-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM01UPI200 EM03UPI200 — 03U Issue U/G Material Final Release (90%) | 21-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03UPI200 EM05BEL120 — 05B Electrical Conceptual Layouts | 21-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM05BEL120 EM03UPI190 — 03U U/G Plan Dwgs Issue IFC | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03UPI190 EM03UPIASG — 03U Iso Issue IFC - Other HDPE (AS & NA) | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03UPIASG EM03UPIOSG — 03U Iso Issue IFC - Metalic Piping (OS) | 22-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03UPIOSG EM03CPI141 — 03C Detail OP's & Services Model Review Mtg | 24-Apr-26 → 27-Dec-26 | In Progress 5% | float — EM03CPI141 EK000MF32D — 05A MF312 2105-F Water Tank - Fdn Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK020IC133 — Field Bus J-boxes Wiring Reports - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK100ELEK2 — 01,03,04,05 Develop & Issue Cable Ladder Plans - IFC Except 01H & 05A | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK200ELEK2 — 01H Develop & Issue Cable Ladder Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEJ2 — 01,03,05 Develop & Issue Lighting Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEK2 — 01,03,04,05 Develop & Issue Power Plans - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEL2 — 01,03,04,05 Electrical Routing Plans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM000ELEM2 — Dev/Issue Elect Cable/Raceway Sched IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API132 — 01A Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API134 — 01A Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API135 — 01A A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API136 — 01A IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API138 — 01A Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API141 — 01A Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01API143 — 01A OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01ASY172 — 01A P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM01ASY272 — 01A P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM01BCV123 — 01B Update Model S/S Sleepers & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV126 — 01B Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV127 — 01B Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV133 — 01B Update Model S/S Sleeper Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV164 — 01B Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV166 — 01B Conceptual Misc. Foundation Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BCV167 — 01B Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI134 — 01B Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI135 — 01B A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI136 — 01B IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI138 — 01B Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI141 — 01B Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BPI143 — 01B OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01BSY172 — 01B P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM01BSY272 — 01B P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM01CCV164 — 01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Excluding EDR) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CCV180 — 01C Design & Model Major Eq. Fdns (Including EDR) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CCV190 — 01C Update Model Major Eq. Fdns & Issue Dwgs-IFC (Including EDR) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI132 — 01C Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI134 — 01C Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI135 — 01C A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI136 — 01C IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI138 — 01C Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI141 — 01C Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CPI142 — 01C OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01CSY172 — 01C P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM01CSY272 — 01C P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM01DCV122 — 01D Update Model S/S Sleepers & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DCV126 — 01D Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DCV127 — 01D Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DCV133 — 01D Update Model S/S Sleeper Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DCV166 — 01D Conceptual Misc. Foundation Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DCV167 — 01D Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI134 — 01D Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI135 — 01D A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI136 — 01D IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI138 — 01D Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI141 — 01D Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DPI143 — 01D OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01DSY172 — 01D P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM01DSY272 — 01D P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM01HCV125 — 01H Design & Model Substation Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV126 — 01H Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV127 — 01H Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV128 — 01H Update Model Substation Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV160 — 01H Design & Model Major Eq. Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV164 — 01H Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV166 — 01H Conceptual Misc. Foundation Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01HCV167 — 01H Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JCV122 — 01J Update Model Metering Enclosure & Issue Dwgs (Concrete Wall) - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JCV133 — 01J Update Model Metering Enclosure Fdns & Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI130 — 01J Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI132 — 01J Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI133 — 01J IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI134 — 01J Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI135 — 01J A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI136 — 01J IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI138 — 01J Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI140 — 01J Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI141 — 01J Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JPI142 — 01J OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01JSY272 — 01J P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM01YCV133 — 01Y Update Model Piperack Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01YPI135 — 01Y A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01YPI136 — 01Y IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01YPI141 — 01Y Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01YPI142 — 01Y OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM01YSY272 — 01Y P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM020IC127 — Instrument Installation Details (10%) - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC129 — Instrument Loop Diagrams - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC132 — Traditional J-boxes Wiring Reports - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC134 — DCS Marshalling Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC135 — SIS Termination Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC136 — ITCC Termination Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM020IC137 — Miscellaneous Wiring Report - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV126 — 03A Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV127 — 03A Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV160 — 03A Design & Model Major Eq. Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV164 — 03A Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV166 — 03A Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ACV167 — 03A Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API130 — 03A Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API132 — 03A Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API133 — 03A IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API134 — 03A Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API135 — 03A A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API136 — 03A IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API138 — 03A Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API140 — 03A Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API141 — 03A Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03API142 — 03A OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ASY172 — 03A P&IDs & Line List Issue - IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ASY272 — 03A P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03BCV112 — 03B Update Model Sumps & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV126 — 03B Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV127 — 03B Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV166 — 03B Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BCV167 — 03B Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BMD229 — 03B Vessel Steel Release IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI130 — 03B Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI132 — 03B Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI133 — 03B IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI134 — 03B Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI135 — 03B A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI136 — 03B IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI138 — 03B Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI140 — 03B Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI141 — 03B Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BPI142 — 03B OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03BSY172 — 03B P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM03BSY272 — 03B P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03CCV127 — 03C Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CCV167 — 03C Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CPI135 — 03C A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CPI136 — 03C IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CPI142 — 03C OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03CSY272 — 03C P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03DCV126 — 03D Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV127 — 03D Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV164 — 03D Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV166 — 03D Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DCV167 — 03D Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI134 — 03D Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI135 — 03D A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI136 — 03D IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI138 — 03D Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI141 — 03D Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DPI143 — 03D OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03DSY172 — 03D P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM03DSY272 — 03D P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03ECV112 — 03E Update Model Containment Area & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV126 — 03E Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV127 — 03E Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV160 — 03E Design & Model Major Eq. Fdns | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV164 — 03E Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV166 — 03E Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ECV167 — 03E Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI123 — 03E Plant Layout Nozzle Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI130 — 03E Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI132 — 03E Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI133 — 03E IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI134 — 03E Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI135 — 03E A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI136 — 03E IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI138 — 03E Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI141 — 03E Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI142 — 03E Detail OP's & Service Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03EPI143 — 03E OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03ESY172 — 03E P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM03ESY272 — 03E P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03FCV126 — 03F Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV127 — 03F Model Misc. Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV164 — 03F Update Model Major Eq. Fdns & Issue Dwgs-IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV166 — 03F Conceptual Misc. Foundations Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FCV167 — 03F Update Model Misc Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI130 — 03F Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI132 — 03F Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI133 — 03F IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI134 — 03F Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI135 — 03F A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI136 — 03F IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI138 — 03F Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI141 — 03F Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI142 — 03F Detail OP's & Service Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI143 — 03F OP's & Serv. Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FPI200 — 03F Equipment Location Plans | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03FSY172 — 03F P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM03FSY272 — 03F P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM03YCV122 — 03Y Update Model Struct Steel & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YCV133 — 03Y Update Model Piperack Fdns & Issue Dwgs - IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI130 — 03Y Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI132 — 03Y Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI133 — 03Y IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI134 — 03Y Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI135 — 03Y A/G Piping Iso's - Issue IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI136 — 03Y IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI138 — 03Y Design / Issue Pipe Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI141 — 03Y Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YPI143 — 03Y OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM03YSY172 — 03Y P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EM03YSY272 — 03Y P&IDs & Line List Issue - IFC | 27-Dec-26 | Not Started EM04API120 — 04A Plant Layout Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM04API134 — 04A Plant Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM04API138 — 04A Design / Issue Pipe & Supports IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM04API200 — 04A Issue U/G Material Final Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05ACV126 — 05A Conceptual Misc. Steel Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05ACV166 — 05A Conceptual Misc. Foundation Design/ Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05AMD229 — 05A Vessel Steel Release IFC | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API130 — 05A Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API132 — 05A Planning Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API133 — 05A IDP - Plant Layout | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API134 — 05A Detail Model Development | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API136 — 05A IDP - Detail Design | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API140 — 05A Model Review Comment Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API142 — 05A Detail OP's & Services Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05API143 — 05A OP's & Serv. Model Review Comments Resolution | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI120 — 05B Plant Layout Model | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BPI130 — 05B Model Review Mtg | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05BSY172 — 05B P&IDs & Line List Issue - IFD | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM05UPI200 — 05U Issue U/G Material Final Release | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EM5ASY172 — 05A P&IDs & Line List Issue - IFD | 27-Dec-26 | Not Started EK020IC131 — Instrument Loop Diagrams FF - IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 530.0d EK020IC131 EM000ELEN3 — 01,03 Equipment Interconnection Diagrams | 30-Dec-26 → 30-Jan-27 | Not Started 0% | float 511.0d EM000ELEN3 EM05ACV122 — 05A Update Model PR Struct Steel & Issue Dwgs - IFC | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 21.0d EM05ACV122 EM05ACV127 — 05A Model Misc. Steel & Issue Dwgs - IFC | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 25.0d EM05ACV127 EM05ACV164 — 05A Update Model Major Eq. Fdns & Issue Dwgs-IFC | 30-Dec-26 → 27-Jan-27 | Not Started 0% | float -14.0d EM05ACV164 EM05API135 — 05A A/G Piping Iso's - Issue IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 90.0d EM05API135 EM05API138 — 05A Design / Issue Pipe Supports IFC | 30-Dec-26 → 03-Jan-27 | Not Started 0% | float 162.0d EM05API138 EM05BCV122 — 05B Design / Model / IFC - Sleeper Steel & FDN's | 30-Dec-26 → 24-Jan-27 | Not Started 0% | float 71.0d EM05BCV122 EM05BCV133 — 05B Design / Model / IFC - S/S at Jetty | 30-Dec-26 → 24-Jan-27 | Not Started 0% | float 71.0d EM05BCV133 EM05BPI141 — 05B Model Review Comment Resolution | 30-Dec-26 → 10-Jan-27 | Not Started 0% | float 75.0d EM05BPI141 EM05ACV133 — 05A Update Model Structural Piperack Fdns & Issue Dwgs - IFC | 01-Jan-27 → 10-Jan-27 | Not Started 0% | float 121.0d EM05ACV133 EM5ASY272 — 05A P&IDs & Line List Issue - IFC | 01-Jan-27 | Not Started EM5BSY272 — 05B P&IDs & Line List Issue - IFC | 01-Jan-27 | Not Started EM000IC100 — Instrument Index - IFC | 06-Jan-27 → 06-Jan-27 | Not Started 0% | float 530.0d EM05BPI133 — 05B IDP - Plant Layout | 13-Jan-27 → 14-Jan-27 | Not Started 0% | float 75.0d EM05ACV167 — 05A Update Model Misc Fdns & Issue Dwgs - IFC | 15-Jan-27 → 24-Jan-27 | Not Started 0% | float 111.0d EM05ACV167 EM05BCV167 — 05B Design / Model / IFC - Equip. Fdn's. | 20-Jan-27 → 20-Jan-27 | Not Started 0% | float 221.0d EM05BPI132 — 05B Planning Release | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 75.0d EM05BPI132 EM05BPI200 — 05B Equipment Location Plans | 20-Jan-27 → 24-Jan-27 | Not Started 0% | float 221.0d EM05BPI200 EM05BPI134 — 05B Detail Model Development | 27-Jan-27 → 31-Jan-27 | Not Started 0% | float 75.0d EM05BPI134 EM05BPI142 — 05B Detail OP's & Services Model Review Mtg | 03-Feb-27 → 03-Feb-27 | Not Started 0% | float 75.0d EM05BPI143 — 05B OP's & Serv. Model Review Comments Resolution | 04-Feb-27 → 06-Feb-27 | Not Started 0% | float 75.0d EM05BPI136 — 05B IDP - Detail Design | 07-Feb-27 → 10-Feb-27 | Not Started 0% | float 75.0d EM05BPI135 — 05B A/G Piping Iso's - Issue IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 75.0d EM05BPI135 EM05BPI138 — 05B Design / Issue Pipe Supports IFC | 14-Feb-27 → 21-Feb-27 | Not Started 0% | float 230.0d EM05BPI138