Showing 13
activities
in SY Systems Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK000MF32A
05A MF312 2105-F Water Tank - Process Load Sht.
19-Mar-25
26-Mar-25
—
100%
EK050SY020
050 Dock/Storage P&ID development IDR Issue
06-Apr-25
25-Apr-25
—
100%
EK050SY030
050 Dock/Storage P&ID IDR Meeting milestone
02-May-25
03-May-25
—
100%
EK050SY040
050 Dock/Storage P&IDs - ICA Issue development
04-May-25
20-Jun-25
—
100%
EK050SY050
050 Dock/Storage P&IDs - ICA Issue Milestone
20-Jun-25
20-Jun-25
—
100%
EK050SY060
050 Dock/Storage P&ID's - IPL Issue Development
25-Jun-25
11-Oct-25
—
100%
EK050SY135
050 Dock/Storage CV & FE Process Data
01-Aug-25
15-Aug-25
—
100%
EK050SY150
050 Relief Valve Calculations - Dock/Storage
20-Aug-25
25-Sep-25
—
100%
EK050SY185
050 SP Item Data Sheets - Dock/Storage
25-Sep-25
24-Dec-25
—
100%
EK050SY155
050 Issue Requisition - PSA08 Relief Valves - Dock/Storage
05-Oct-25
19-Nov-25
—
100%
EK050SY090
050 Dock/Storage P&IDs IPL Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05ASY170
05A OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%
EK05BSY170
05B OSBL P&IDs IPL & Line List Issue Milestone
11-Oct-25
11-Oct-25
—
100%