EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 12 activities in PI Piping Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK050PI005
Develop Plot Plan & ID Areas - Dock/Storage IFI
02-Mar-25
09-Mar-25
100%
EK050PI010
Develop Plot Plan & ID Areas - Dock/Storage ICA
23-Mar-25
11-Oct-25
100%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
59%
EK05API030
05A Conceptual Layout - Supersketches
12-Aug-25
28-Sep-25
100%
EK050PI012
Plot Plan - Dock/Storage Issue IPL
16-Sep-25
26-Oct-25
100%
EK050PI011
Plot Plan - Dock/Storage Client ICA Approval
11-Oct-25
26-Oct-25
100%
EK050PI013
Plot Plan - Dock/Storage Issue IPL
01-Jan-26
23-Jan-26
100%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
26%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
13%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec 04-Jan 11-Jan 18-Jan 25-Jan Data Date
EK050PI005 — Develop Plot Plan & ID Areas - Dock/Storage IFI | 02-Mar-25 → 09-Mar-25 | Complete 100% | float — EK050PI005 EK050PI010 — Develop Plot Plan & ID Areas - Dock/Storage ICA | 23-Mar-25 → 11-Oct-25 | Complete 100% | float — EK050PI010 EK05BPI030 — 05B Conceptual Layout - Supersketches | 07-May-25 → 27-Dec-26 | In Progress 59% | float — EK05BPI030 EK05API030 — 05A Conceptual Layout - Supersketches | 12-Aug-25 → 28-Sep-25 | Complete 100% | float — EK05API030 EK050PI012 — Plot Plan - Dock/Storage Issue IPL | 16-Sep-25 → 26-Oct-25 | Complete 100% | float — EK050PI012 EK050PI011 — Plot Plan - Dock/Storage Client ICA Approval | 11-Oct-25 → 26-Oct-25 | Complete 100% | float — EK050PI011 EK050PI013 — Plot Plan - Dock/Storage Issue IPL | 01-Jan-26 → 23-Jan-26 | Complete 100% | float — EK050PI013 EK050PI014 — Plot Plan - Dock/Storage Issue IFC | 28-Jan-26 → 27-Dec-26 | In Progress 26% | float — EK050PI014 EK050PI006 — Site Data Needed - Loading Area (SPDC) | 18-Mar-26 → 27-Dec-26 | In Progress 13% | float — EK050PI006 EK05API050 — 05A Model Comment Resolution Approval | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05BPI035 — 05B Plot Plan | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float — EK05BPI050 — 05B Model Comment Resolution Approval | 15-Jan-27 → 17-Jan-27 | Not Started 0% | float 75.0d EK05BPI050