EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 12
activities
in PI Piping Engineering
× clear
Code
Activity
Start
Finish
Flt
%
EK050PI005
Develop Plot Plan & ID Areas - Dock/Storage IFI
02-Mar-25
09-Mar-25
—
100%
EK050PI010
Develop Plot Plan & ID Areas - Dock/Storage ICA
23-Mar-25
11-Oct-25
—
100%
EK05BPI030
05B Conceptual Layout - Supersketches
07-May-25
27-Dec-26
—
59%
EK05API030
05A Conceptual Layout - Supersketches
12-Aug-25
28-Sep-25
—
100%
EK050PI012
Plot Plan - Dock/Storage Issue IPL
16-Sep-25
26-Oct-25
—
100%
EK050PI011
Plot Plan - Dock/Storage Client ICA Approval
11-Oct-25
26-Oct-25
—
100%
EK050PI013
Plot Plan - Dock/Storage Issue IPL
01-Jan-26
23-Jan-26
—
100%
EK050PI014
Plot Plan - Dock/Storage Issue IFC
28-Jan-26
27-Dec-26
—
26%
EK050PI006
Site Data Needed - Loading Area (SPDC)
18-Mar-26
27-Dec-26
—
13%
EK05API050
05A Model Comment Resolution Approval
27-Dec-26
27-Dec-26
—
0%
EK05BPI035
05B Plot Plan
27-Dec-26
27-Dec-26
—
0%
EK05BPI050
05B Model Comment Resolution Approval
15-Jan-27
17-Jan-27
75.0d
0%