EBCF-4
EBIC Construction Forecast (27-Jan-07)
Legend:
Not Started
In Progress
Complete
Critical
Milestone
Showing 31
activities
in MJ Machinery Engineering
× clear
Code
Activity
Start
Finish
Flt
%
PK000MJ37Q
Prepare & Issue Prelim. RFQ - MJ307 to Proc.
31-May-25
12-Jun-25
—
100%
PK000MJ37E
Technical Evaluation - MJ307
19-Jul-25
06-Dec-25
—
100%
PK05AMJ154
05A Recv. Planning V. Data - Pumps 2106/7-J
17-Sep-25
17-Sep-25
—
100%
PK05AML100
05A Recv. Planning V. Data - Special Equip.
01-Oct-25
01-Oct-25
—
100%
PK05BML100
05B Recv. Planning V. Data - Special Equip. 2102-L
01-Oct-25
01-Oct-25
—
100%
PK05AMLV01
05A ML330 2101-L - Piping Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV02
05A ML330 2101-L - Civil Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMLV03
05A ML330 2101-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05BMLV03
05B ML512 2102-L - E&I Prod. V. Data
31-Dec-25
27-Dec-26
—
32%
PK05AMJV01
05A MJ305 2106-J,2107-J - Piping Prod. V. Data
31-Dec-25
03-Mar-26
—
100%
PK05AMJV02
05A MJ305 2106-J,2107-J - Civil Prod. V. Data
31-Dec-25
20-Mar-26
—
100%
PK05AMJV03
05A MJ305 2106-J,2107-J - E&I Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV01
05B ML512 2102-L - Piping Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK05BMLV02
05B ML512 2102-L - Civil Prod. V. Data
31-Dec-25
21-Mar-26
—
100%
PK000MJ38Q
Prepare & Issue Prelim. RFQ - MJ308 to Proc.
01-Jan-26
13-Jan-26
—
100%
PK05AMJV04
05A MJ307 2100-JA/JB - Piping Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV05
05A MJ307 2100-JA/JB - Civil Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK05AMJV06
05A MJ307 2100-JA/JB - E&I Prod. V. Data
20-Jan-26
27-Dec-26
—
28%
PK000MJ37T
Recv. Planning V. Data MJ307
20-Jan-26
23-Jan-26
—
100%
PK000MJ38E
Technical Evaluation - MJ308
10-Feb-26
27-Mar-26
—
100%
PK05AMLV04
05A ML501 2103-L - Piping Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV05
05A ML501 2103-L - Civil Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05AMLV06
05A ML501 2103-L - E&I Prod. V. Data
25-Feb-26
27-Dec-26
—
19%
PK05BMU06
05B MU311 2109-LA/LB, 2110-L - Piping Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK05BMU07
05B MU311 2109-LA/LB, 2110-L - Civil Prod. V. Data
14-Mar-26
27-Dec-26
—
14%
PK05AMJV07
05A MJ392 2105-JA/JB - Piping Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV08
05A MJ392 2105-JA/JB - Civil Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK05AMJV09
05A MJ392 2105-JA/JB - E&I Prod. V. Data
18-Mar-26
27-Dec-26
—
13%
PK000MJ38T
Recv. Planning V. Data MJ308
23-Apr-26
27-Dec-26
—
5%
PK05AMJV10
05A MJ731 2108-J - Civil Prod. V. Data
27-Dec-26
27-Dec-26
—
0%
PK05AMJV11
05A MJ731 2108-J - E&I Prod. V. Data
27-Dec-26
27-Dec-26
—
0%