EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000MF32C
05A MF312 2105-F Water Tank - Issue Data for Subcontract
27-Mar-25
09-Apr-25
100%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
23%
PK000MF32D
05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF33
05A MF312 2105-F - Piping Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF34
05A MF312 2105-F - Civil Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF35
05A MF312 2105-F - E&I Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
0%
24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-May 12-May 19-May 26-May 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun 07-Jul 14-Jul 21-Jul 28-Jul 04-Aug 11-Aug 18-Aug 25-Aug 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Oct 13-Oct 20-Oct 27-Oct 03-Nov 10-Nov 17-Nov 24-Nov 01-Dec 08-Dec 15-Dec 22-Dec 29-Dec 05-Jan 12-Jan 19-Jan 26-Jan 02-Feb 09-Feb 16-Feb 23-Feb 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May 01-Jun 08-Jun 15-Jun 22-Jun 29-Jun 06-Jul 13-Jul 20-Jul 27-Jul 03-Aug 10-Aug 17-Aug 24-Aug 31-Aug 07-Sep 14-Sep 21-Sep 28-Sep 05-Oct 12-Oct 19-Oct 26-Oct 02-Nov 09-Nov 16-Nov 23-Nov 30-Nov 07-Dec 14-Dec 21-Dec 28-Dec Data Date
EK000MF32C — 05A MF312 2105-F Water Tank - Issue Data for Subcontract | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — EK000MF32C PK05AMF05 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract) | 11-Feb-26 → 27-Dec-26 | In Progress 23% | float — PK05AMF05 PK000MF32D — 05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK000MF32D PK05AMF33 — 05A MF312 2105-F - Piping Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF33 PK05AMF34 — 05A MF312 2105-F - Civil Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF34 PK05AMF35 — 05A MF312 2105-F - E&I Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF35 PK05AMF25 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —