EBCF-4

EBIC Construction Forecast (27-Jan-07)

Data Date: 23-Apr-26
Plan: 22-Jan-25 – 27-Mar-29
Legend: Not Started In Progress Complete Critical Milestone Showing 7 activities in MD Vessels Engineering × clear
Code
Activity
Start
Finish
Flt
%
EK000MF32C
05A MF312 2105-F Water Tank - Issue Data for Subcontract
27-Mar-25
09-Apr-25
100%
PK05AMF05
05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract)
11-Feb-26
27-Dec-26
23%
PK000MF32D
05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF33
05A MF312 2105-F - Piping Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF34
05A MF312 2105-F - Civil Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF35
05A MF312 2105-F - E&I Prod. V. Data (Subcontract)
11-Feb-26
03-Mar-26
100%
PK05AMF25
05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract)
27-Dec-26
27-Dec-26
0%
Q1 2025 Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Data Date
EK000MF32C — 05A MF312 2105-F Water Tank - Issue Data for Subcontract | 27-Mar-25 → 09-Apr-25 | Complete 100% | float — PK05AMF05 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Foundation V. Data (Subcontract) | 11-Feb-26 → 27-Dec-26 | In Progress 23% | float — PK05AMF05 PK000MF32D — 05A MF312 2105-F Water Tank - Fdn. Vendor Data (From Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF33 — 05A MF312 2105-F - Piping Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF34 — 05A MF312 2105-F - Civil Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF35 — 05A MF312 2105-F - E&I Prod. V. Data (Subcontract) | 11-Feb-26 → 03-Mar-26 | Complete 100% | float — PK05AMF25 — 05A MF311 2101/2102-F Ammonia Storage Tanks - Prod. V. Data (Subcontract) | 27-Dec-26 → 27-Dec-26 | Not Started 0% | float —